Additions and alterations to building 1575 at scott air force base, IL.

Ended Definitive Contract Awarded Last action

Contract number
W912QR20C0028
Awardee
Awarding agency
Obligated
$36,944,319

Award facts

Opportunity
Contract value 100% obligated
  • $36,944,319.33 Current, with exercised options
  • $37,110,319.33 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Scott AFB, IL 62225, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00030 · CR 165, loading dock pavement $51,813
Supplemental Agreement for work within scope A00025 · Change request 00066 reduction in parking spaces $247,830
Supplemental Agreement for work within scope A00024 · Change request 00120 install equipment for advanced metering 00167 REA modification delay $402,227
Supplemental Agreement for work within scope A00023 · CR 0028-2 part 2 final repair existing utility lines -$9,750
Supplemental Agreement for work within scope A00022 · CR 00158 PH 4 electronic security system changes CR 00160 keep door at column 6.5 h-ESS $9,295
Supplemental Agreement for work within scope A00021 · 073 manbars AHUS1-4 113 chng ldng dock pathway 130 fire rated opnings 132 downspouts indstrl addtn 133 shear wall anchrs 135 shear wall steel at mech opngs… $202,828
Supplemental Agreement for work within scope A00020 · Change request 00144 REA for time - commissioning $0
Change Order A00019 · Base work $0
Supplemental Agreement for work within scope A00018 · CR46RMVE TP1,CR47PRTCT COM lines, CR48RMV exstng hsekpng AHU 1-4,CR61DLT STC RTG, CR94MECH RM roof, CR114CHNGE doors, CR119CHNG hngs, CR122EMRG blsts,… $221,008
Other Administrative Action A00017 · CR 00128 correct funding CR91 scott AFB IL $0
Supplemental Agreement for work within scope A00016 · 15 dlte reqm RPL lintels 03 altr SE rtrn duct 44 remve abdned STM PPG 45 accs DRS AHUS1-4 64 mdfy lfts 105 EXT lght ctrl 106 relct ADA prking 110 cble path… $241,693
Supplemental Agreement for work within scope A00015 $84,152
Supplemental Agreement for work within scope A00014 · Base work $121,052
Supplemental Agreement for work within scope A00013 · Case 00084 freeze protection cooling tower piping, case 00086 reinforcement to support for parapets, case 00088 roof parapet transition scott AFB IL $192,610
Supplemental Agreement for work within scope A00012 $66,820
Supplemental Agreement for work within scope A00011 $206,274
Supplemental Agreement for work within scope A00010 · Base work $184,552
Supplemental Agreement for work within scope A00009 · Case 0069 lower UF cable trays scott AFB IL $54,700
Supplemental Agreement for work within scope A00008 · All alter consolidated comm facility scott AFB IL cases 0020, 0027, 0029, 0031, 0040, 0050, 0051, 0053, 0054, 0055 $237,587
Exercise an Option P00006 · Exercise option 1 - install cabinets $406,000
Supplemental Agreement for work within scope A00007 · CR 0036 RMV hskpg & vibrator pads ahus 5-8-west add alter consolidated comm facility, scott AFB, IL $14,911
Supplemental Agreement for work within scope A00006 · Base work $102,526
Supplemental Agreement for work within scope A00005 · CR 004 change access floor surface CR 018 demolition access floor surface CR 032 RE-route chilled water piping -NW loop CR 034 update contractor information… $378,312
Supplemental Agreement for work within scope P00005 · CR 006 change project phasing plan , consolidated comm facility $1,612,764
Supplemental Agreement for work within scope A00004 $51,138
Supplemental Agreement for work within scope A00003 $83,867
Supplemental Agreement for work within scope A00002 · Base work $64,111
Change Order A00001 · CR 0028-1 repair existing utility lines part i NTP- consolidated comm facility $50,000
Exercise an Option P00004 · Modification to exercise options 2, 3, and 12 for communications building 1575 at scott air force base. $1,524,000
Other Administrative Action P00003 · Issuance of the notice to proceed. $0
Exercise an Option P00002 · Exercising bid option 4 electronic security system (ESS) devices $42,000
Other Administrative Action P00001 · Modification to issue the notice to proceed. $0
Original award $30,100,000
Show all 33

About this award

This is a $37,110,319.33 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) Louisville District to River City Construction LLC for additions and alterations to Building 1575 at Scott Air Force Base in Illinois. The project includes constructing a 23,702 square foot administrative addition and renovating the existing 50,965 square foot computer data center, including seismic retrofitting, mechanical and electrical system upgrades, and new data cabinets. This contract was competitively awarded and does not have a set-aside designation. The original solicitation was a pre-solicitation notice posted in February 2020, with proposals due in April 2020. The expected contract duration is 894 calendar days from the notice to proceed.

Quick answers

Who was awarded contract W912QR20C0028?

W912QR20C0028 was awarded to River City Construction LLC by ENDIST Louisville (US Army Corps of Engineers) on July 29, 2020.

How much is contract W912QR20C0028 worth?

The government has obligated $36,944,319 on W912QR20C0028. Its potential value, with all options, is $37,110,319.

Was contract W912QR20C0028 competed?

The extent of competition for W912QR20C0028 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award