Supplemental Agreement for work within scope
A00039 · Case 00029-4 revised access drives, part 2 final, design/build sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$211,740
Change Order
A00038 · Case 00029-3 revised access drives, part 1 supplement 2, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$40,000
Change Order
A00037 · Case 00029-2 revised access drives, part 1 supplement 1, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$20,000
Change Order
A00036 · Case 00029-1 revised access drives, part 1, notice to proceed, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, TN
$100,000
Supplemental Agreement for work within scope
A00035 · Case 00027 miscellaneous engineering changes (remove existing light pole base, install daylight controllers, install 6" pipe sleeve, incorporate specification…
$25,900
Supplemental Agreement for work within scope
A00034 · Case 00028 weather time extension, design/build sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$0
Supplemental Agreement for work within scope
A00033 · Case 00025 install 1/2" sanded pine plywood on divider walls, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$7,240
Supplemental Agreement for work within scope
A00032 · Case 00026-2 increase overhead door height, part 2 final, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, TN
$24,000
Change Order
A00031 · Case 00026-1 increase overhead door height, part 1 notice to proceed, sustainment brigade tactical equipment maintenance facilities, FT. Campbell , TN
$30,000
Supplemental Agreement for work within scope
A00030 · Case 00024 install soffit under canopy off corridor 129 on both temf buildings, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$8,870
Supplemental Agreement for work within scope
A00029 · Case 00023-2 light pole rock removak, part 2 final, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
-$2,065
Supplemental Agreement for work within scope
A00028 · Case 00022 HVAC changes, design/build tactical equipment maintenance facilities (sustainment brigade), FT. Campbell, KY
$56,838
Supplemental Agreement for work within scope
A00027 · Case 00019 west ditch improvement, design/build sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$44,000
Change Order
A00026 · Case 00023-1 light pole removal, part 1 notice to proceed - remove rock encountered under areas where light pole bases and grounding grid are to be installed,…
$6,500
Supplemental Agreement for work within scope
A00025 · Case 00020 install 2 transformers in tactical equipment maintenance facility b, sustainment brigade tactical equipment maintenance facilites, FT. Campbell, KY
$55,291
Supplemental Agreement for work within scope
A00024 · Case 00021 time extension due to weather delays, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$0
Supplemental Agreement for work within scope
A00023 · Case 00017 miscellaneous engineering changes including add galvanized beam, construct 6" wide concrete curb, extend ceiling deck, return cable and credit…
$10,356
Supplemental Agreement for work within scope
A00022 · Case 00018 additional communication lines, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, TN
$9,000
Other Administrative Action
P00002
$0
Supplemental Agreement for work within scope
A00021 · Case 00013 construct CMU partition walls according to revised details, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$0
Supplemental Agreement for work within scope
A00020 · Case 00016 remove rock encountered shallower than 13' from existing ground surface, sustainment brigade tactical equipment maintenance facilities, FT. Campbell,…
$11,150
Other Administrative Action
P00001 · Admin MOD to adjust the period of performance to state 650 days instead of 590 days from notice to proceed; TJC engineering
$0
Supplemental Agreement for work within scope
A00019 · Case 00015 credit modification for revised specifications for roller compacted concrete, tactical equipment maintenance facilities, FT. Campbell, KY
-$10,000
Supplemental Agreement for work within scope
A00018 · Case 00004-3 temf a rock removal, part 2 final - remove rock encountered shallower than 13' from existing ground surface to minimum depth of 2' below sub…
$24,500
Supplemental Agreement for work within scope
A00017
$0
Supplemental Agreement for work within scope
A00016 · Case 00012 time extension due to weather delays, design/build sustainment brigade tactical equipment maintenance facilities, FT. Campbell, TN
$0
Supplemental Agreement for work within scope
A00015 · Case 00005 move 6" sanitary sewer line from mechanical room to men's restroom and underneath building, sustainment brigade tactical equipment maintenance…
$8,000
Supplemental Agreement for work within scope
A00014 · Case 0009-2 east gabion wall outflow, part 2 final, including additional site work construction to avoid erosion, sustainment brigade tactical equipment…
$4,815
Supplemental Agreement for work within scope
A00013 · Case 00010 miscellaneous engineering changes including adding conduit and CAT 5 cable for energy management control system; providing rebar for concrete light…
$52,000
Supplemental Agreement for work within scope
A00012 · Case 00003-2 add low mobility grouting, part 2 final, design/build tactical equipment maintenance facilities, FT. Campbell, KY
$90,900
Supplemental Agreement for work within scope
A00011 · Case 00011 time extension due to weather delays, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, KY
$0
Change Order
A00010 · Case 00004-2 part 1 supplement 1, remove rock encountered at depths shallower than 13' from existing ground surface to a minimum depth of 2' below subgrade,…
$42,500
Supplemental Agreement for work within scope
A00009 · Case 00007 sinkhole remediation including removal and stockpiling of topsoil, excavation, lining with geotextile filter fabric, filling with limestone rock…
$9,913
Change Order
A00008 · Case 0009-1 east gabion wall outflow, part 1 notice to proceed, provide additional site work construction at "TOE" of eastern gabion wall on site a,…
$20,000
Supplemental Agreement for work within scope
A00007 · Case 0001 site design changes to temf a including perforated under drains at gravel clear zone; add gabion wall under drains; remove storm line 4; add 5 6"…
$62,000
Supplemental Agreement for work within scope
A00006 · Case 008 revise 25 drawings for temf a and temf b, sustainment brigade tactical equipment maintenance facilities, FT. Campbell, TN
$0
Supplemental Agreement for work within scope
A00005 · Case 0006 time extension due to weather delays, sustainment brigade tactical equipment maintenance facility, FT. Campbell, KY
$0
Change Order
A00003 · Case 0003-1 add low mobility grouting, part 1 notice to proceed to provide additional 65 injections to a maximum depth of 32', sustainment brigade tactical…
$50,000
Change Order
A00004 · Case 0004-1 rock removak, part 1 notice to proceed, to remove rock encountered at depths less than 13' from ground surface to a minimum of 2' below subgrade,…
$20,000
Supplemental Agreement for work within scope
A00002 · Case 00002-2 reroute communication lines, part 2 final: provide 25 pairs of copper and 12 strands of fiber communication cables to bldg 6871, 100 pairs of…
-$2,337
Change Order
A00001 · Case 00002-1 reroute communications lines, part 1 notice to proceed, to include providing 25 pairs of copper communication cables and 12 strands of fiber…
$20,000
Original award
$23,597,213
Show all 42
Quick answers
Who was awarded contract W912QR12C0037?
W912QR12C0037 was awarded to TJC Engineering, Inc. by ENDIST Louisville (US Army Corps of Engineers) on May 16, 2012.
How much is contract W912QR12C0037 worth?
The government has obligated $24,648,324 on W912QR12C0037.
Was contract W912QR12C0037 competed?
The extent of competition for W912QR12C0037 was full and open competition after exclusion of sources. The government received 14 offers. It was set aside: Total Small Business.