Supplemental Agreement for work within scope
A00032 · Case 052 changes to power for building 455, advanced power and thermal research laboratory, wright-patterson AFB, OH
$5,711
Supplemental Agreement for work within scope
A00031 · Case 053 repair storm line - install 3 additional rows of straw bales and silt fence, remove erosion control once vegetation has BEN substantiated, advanced…
$5,627
Supplemental Agreement for work within scope
A00030 · Case 050 add requirement to furnish and install approximately 350 linear feet of PVC waterline at north end of building 450 and 350 LF of PVC waterline at south…
$34,359
Supplemental Agreement for work within scope
A00029 · Case 049 process water loops including installation of new hose connections to existing chilled water lines to create loop between adjacent supply and return…
$23,100
Supplemental Agreement for work within scope
A00028 · Case 044 delete requirement to relocate and install UPS battery and add requirement to remove refrigerant from all HVAC equipment; case 047 add 1 access control…
$6,750
Supplemental Agreement for work within scope
A00027 · Case 013 delete partial demolition and construction of building enclosure activities at building 20450, advanced power and thermal research laboratory,…
$249,000
Supplemental Agreement for work within scope
P00006 · Cases 0046 part 2 final to modifications P00003 & P00004 including architectural, mechanical, and electrical revisions, advanced power and thermal research…
$505,293
Supplemental Agreement for work within scope
P00005 · Case 048 delete requirement to design and install new metal panels on face of concrete wall abutting building 451; delete requirement to remove concrete wall…
-$25,000
Supplemental Agreement for work within scope
P00004 · Case 0046-2 architectural revisioins to fixed casework in 7 lab spaces; mechanical revisions to 29 lab spaces; electrical work in 31 lab spaces, part 1…
$200,000
Supplemental Agreement for work within scope
A00026 · Case 045 install and test new isolation grounding system, conversion of advanced power and thermal research laboratory, wright-patterson AFB, OH
$107,000
Supplemental Agreement for work within scope
A00025 · Case 043 exchange 45 of the 36" base cabinets , delete casework, and revise construction release drawings, conversion for advanced power and thermal research…
-$45,824
Change Order
P00003 · Case 0046 complete utility connections to research equipment and architectural revisions to accommodate equipment within newly constructed lab spaces in…
$300,000
Supplemental Agreement for work within scope
A00024 · Case 039 build-out and construct batterly lab build out, conversion of advanced power and thermal research laboratory, wright-patterson AFB, OH
$191,859
Change Order
A00023 · Advanced power & thermal research lab
$81,900
Supplemental Agreement for work within scope
A00022 · Case 023 provide electronic direct digital HVAC controls for electrochemistry lab; case 037 delete requirement to perform air barrier and thermography testing…
-$13,000
Change Order
A00021 · Advanced power & thermal research lab
$0
Supplemental Agreement for work within scope
A00020 · Case 041 delete requirement to furnish and install eye wash station; add requirement to provide and install light fixture; delete requirement to install 19…
-$26,000
Supplemental Agreement for work within scope
A00019 · Case 031 delete requirement to design, fabricate and construct roof access penthouse and associated stairs, railings and access items located on 3RD floor…
-$16,033
Additional Work (new agreement, FAR part 6 applies)
A00018
$44,800
Change Order
A00017 · Advanced power & thermal research lab
-$8,500
Supplemental Agreement for work within scope
A00016 · Case 028 add power outlets in communications equipment rooms, advanced power and thermal research laboratory, wright-patterson AFB, OH
$7,813
Other Administrative Action
A00015 · Case 015, correct appropriation and accounting data for case 009, advanced power and thermal research laboratory, wright-patterson AFB, OH
$0
Supplemental Agreement for work within scope
A00014 · Case 035 add infrastructure for 4 additional wireless LAN drops on each floor of building 23, conversion for advanced power and thermal research laboratory,…
$5,967
Supplemental Agreement for work within scope
A00013 · Case 017 changes to cooling tower including open cell in lieu of evaporative closed loop towers, conversion of advanced power and thermal research laboratory,…
-$159,448
Supplemental Agreement for work within scope
A00012 · Case 0009 delete laboratory equipment according to schedule provided, conversion for advanced power and thermal research laboratory, wright-patterson AFB, OH
-$233,739
Supplemental Agreement for work within scope
A00011 · Case 024 increase STC rating of mechanical doors, provide dedicated area for electrical/mechanical service equipment and test sound attenuation values; case 027…
-$19,300
Supplemental Agreement for work within scope
A00010 · Case 005 eliminate opening between 2ND and 3RD floors at east and west ends of new 3-story building in building 23, building conversion for advanced power and…
$73,145
Supplemental Agreement for work within scope
A00009 · Case 030 differing site condition, remove and dispose of reinforced concrete structures, anchors and steel bed plates found beneath existing concrete slab;…
$97,191
Supplemental Agreement for work within scope
A00008 · Case 014 credit for removal of fune hoods and associated cabinets, add requirement for 6' fume hood adjacent to current unit and 8' walk-in fume hood adjacent…
$21,878
Change Order
A00007
$54,609
Change Order
A00006 · Advanced power lab, wpafb
$22,432
Supplemental Agreement for work within scope
A00005 · Case 018 remove walls from between specified rooms, widen door openings and remove doors; case 021 install new 200 copper pair wiring for telephone and LAN…
-$9,926
Supplemental Agreement for work within scope
A00004 · Case 0006 repair all structural deficiencies found in steel members supporting roof and wall structures in existing electrical room and mechanical rooms,…
$29,300
Supplemental Agreement for work within scope
A00003 · Case 003 delete requirement to add RF shielding between metal studs and drywall for rooms 114, 115, 116 and 118; add RF shielding for rooms 114, 115, 116 and…
$323,967
Change Order
A00002
$189,923
Additional Work (new agreement, FAR part 6 applies)
A00001
$307,062
Other Administrative Action
P00002
$0
Exercise an Option
P00001 · Advanced power lab, wpafb
$1,850,000
Original award
$19,954,000
Show all 39
Quick answers
Who was awarded contract W912QR10C0060?
W912QR10C0060 was awarded to Messer Construction CO. by ENDIST Louisville (US Army Corps of Engineers) on June 14, 2010.
How much is contract W912QR10C0060 worth?
The government has obligated $24,135,916 on W912QR10C0060.
Was contract W912QR10C0060 competed?
The extent of competition for W912QR10C0060 was full and open competition. The government received 7 offers.