Supplemental Agreement for work within scope
A00038 · Case 068 compensation for utility and trailer rental costs, full facility restoration, esek hopkins U.S. Armed forces reserve center, cranston, RI
$44,676
Supplemental Agreement for work within scope
A00038 · Arra::yes::arra case 068 compensation for utility and trailer rental costs, full facility restoration, esek hopkins U.S. Armed forces reserve center,…
$0
Supplemental Agreement for work within scope
A00037 · Case 070 equitable adjustment for provision of card reader system, full facility restoration of esek hopkins U.S. Armed forces reserve center, cranston, RI
$20,838
Supplemental Agreement for work within scope
A00037 · Arra::yes::arra case 070 equitable adjustment for provision of card reader system, full facility restoration of esek hopkins U.S. Armed forces reserve center,…
$3,183
Change Order
P00003 · Arra::yes:: arra
$0
Change Order
P00003 · Option 1
-$4,079
Supplemental Agreement for work within scope
A00036 · Arra::yes::arra case 062 delete 2 monarch electric latch retraction kits and provide 3 rutherford controls surface mounted rim strike and power circuits, full…
-$3,183
Supplemental Agreement for work within scope
A00036 · Case 062 delete 2 monarch electric latch retraction kits and provide 3 rutherford controls surface mounted rim strike and power circuits, full facility…
$0
Supplemental Agreement for work within scope
A00035 · Case 066 demolish fence and 2 floodlights for armory, demolish electrical conductor, analog cabling and fiber cabling from trailer to armory, demolish…
$9,529
Supplemental Agreement for work within scope
A00035 · Arra::yes::arra case 066 demolish fence and 2 floodlights for armory, demolish electrical conductor, analog cabling and fiber cabling from trailer to armory,…
$0
Supplemental Agreement for work within scope
A00034 · Case 063 reimburse contractor for payment of electric service bills for OMS building, full facility restoration of esek hopkins U.S. Armed forces reserve…
$23,816
Supplemental Agreement for work within scope
A00034 · Arra::yes::arra case 063 reimburse contractor for payment of electric service bills for OMS building, full facility restoration of esek hopkins U.S. Armed…
$0
Supplemental Agreement for work within scope
A00033 · Arra::yes::arra case 064 compensation for quarterly fire suppression charges from city of cranston, U.S. Army reserve center, cranston, RI (no arra funds…
$0
Supplemental Agreement for work within scope
A00033 · Case 064 compensation for quarterly fire suppression charges from city of cranston, U.S. Army reserve center, cranston, RI
$8,091
Change Order
A00032 · Arra FFR cranston, RI construction
$0
Change Order
A00032 · Option 1
$0
Change Order
A00031 · Arra FFR cranston, RI construction
$0
Change Order
A00031 · Option 1
$6,996
Change Order
A00030 · Arra::yes::arra arra FFR cranston, RI construction
$0
Change Order
A00030 · Option 1 FFR cranston, RI construction
$21,909
Supplemental Agreement for work within scope
A00029 · Arra::yes::arra case 048-2 day gate for marines arms vault; case 052-2 EMT conduits and power for nmci IDS, full facility restoration of esek hopkins U.S. Armed…
$0
Supplemental Agreement for work within scope
A00029 · Case 048-2 day gate for marines arms vault; case 052-2 EMT conduits and power for nmci IDS, full facility restoration of esek hopkins U.S. Armed forces…
$4,801
Supplemental Agreement for work within scope
A00028 · Case 042 electrical and telecom changes (power circuits, phone and data cables, junction box covers, additional circuitry, replacement of damaged ceiling tiles;…
$67,322
Supplemental Agreement for work within scope
A00028 · Arra::yes::arra case 042 electrical and telecom changes (power circuits, phone and data cables, junction box covers, additional circuitry, replacement of…
$0
Supplemental Agreement for work within scope
A00027 · Arra::yes::arra case 033-2 fire alarm for OMS building, part 2 final, full facility restoration of esek hopkins U.S. Armed forces reserve center, cranston, RI…
$0
Supplemental Agreement for work within scope
A00027 · Case 033-2 fire alarm for OMS building, part 2 final, full facility restoration of esek hopkins U.S. Armed forces reserve center, cranston, RI
$9,842
Supplemental Agreement for work within scope
A00026 · Arra::yes::arra case 023 electrical and mechanical changes to vehicle access gate, full facility restoration of the esek hopkins U.S. Armed forces reserve…
$0
Supplemental Agreement for work within scope
A00026 · Case 023 electrical and mechanical changes to vehicle access gate, full facility restoration of the esek hopkins U.S. Armed forces reserve center, cranston, RI
$113,011
Supplemental Agreement for work within scope
A00025 · Case 55 provide 4'X8'X3/4" fire rated plywood on west and north walls, 4" EMT conduit from cable tray to telecommunications rack, telecommunications ground…
$9,413
Supplemental Agreement for work within scope
A00025 · Arra::yes::arra case 55 provide 4'X8'X3/4" fire rated plywood on west and north walls, 4" EMT conduit from cable tray to telecommunications rack,…
$0
Change Order
A00024 · Arra::yes::arra case 033-1 demolish existing fire alarm cabling, devices and conduit, provide new EMT conduit, fire alarm cabling, mass notification devices,…
$0
Change Order
A00024 · Case 033-1 demolish existing fire alarm cabling, devices and conduit, provide new EMT conduit, fire alarm cabling, mass notification devices, manual pull…
$59,000
Additional Work (new agreement, FAR part 6 applies)
A00023 · Option 1
$89,066
Additional Work (new agreement, FAR part 6 applies)
A00023 · Arra FFR cranston, RI construction
$0
Supplemental Agreement for work within scope
A00022 · Arra::yes::arra case 031 electrical and telecommunications changes including installaton of telecom rack, surface mounted combination nipr voice/data outlet,…
$0
Supplemental Agreement for work within scope
A00022 · Case 031 electrical and telecommunications changes including installaton of telecom rack, surface mounted combination nipr voice/data outlet, EMT conduits and…
$34,075
Supplemental Agreement for work within scope
A00021 · Case 037 provide new conduit and telephone wiring between new fire alarm control panel and property limits, test to confirm that local fire department…
$28,108
Supplemental Agreement for work within scope
A00020 · Arra::yes::arra case 047-4 segregation of marines/navy data system, part II final, full facility restoration of esek hopkins U.S. Armed forces reserve center,…
$0
Supplemental Agreement for work within scope
A00020 · Case 047-4 segregation of marines/navy data system, part II final, full facility restoration of esek hopkins U.S. Armed forces reserve center, cranston, RI
$69,611
Supplemental Agreement for work within scope
A00021 · Arra::yes::arra case 037 provide new conduit and telephone wiring between new fire alarm control panel and property limits, test to confirm that local fire…
$0
Additional Work (new agreement, FAR part 6 applies)
A00019 · Option 1 restoration of the existing esek hopkins armed forces reserve center, cranston, providence counry, rhode island construction
$73,266
Additional Work (new agreement, FAR part 6 applies)
A00019 · Arra::yes::arra restoration of the existing esek hopkins armed forces reserve center, cranston, providence counry, rhode island construction
$0
Change Order
A00018 · Case 048 demolish existing day gate 148 and provide new right-swing day gate with lockset; case 052 provide EMT conduits and power for IDS in room 224,…
$13,200
Change Order
A00018 · Arra::yes::arra case 048 demolish existing day gate 148 and provide new right-swing day gate with lockset; case 052 provide EMT conduits and power for IDS in…
$0
Change Order
A00017 · Case 047 segregation of marines/navy data system by disconnecting terminations of data cabling, installing telecommunications rack, terminating cabling in new…
$35,000
Change Order
A00017 · Arra::yes::arra case 047 segregation of marines/navy data system by disconnecting terminations of data cabling, installing telecommunications rack,…
$0
Change Order
A00016 · Arra FFR cranston, RI construction
$0
Change Order
A00016 · Option 1
$12,424
Supplemental Agreement for work within scope
A00015 · Case 038 change type of pedestal FIN tube radiator; case 039 install new circulating pump for domestic water heating system, full facility restoration, esek…
$2,110
Supplemental Agreement for work within scope
A00015 · Arra::yes::arra case 038 change type of pedestal FIN tube radiator; case 039 install new circulating pump for domestic water heating system, full facility…
This is a $7,416,794.43 firm fixed price contract awarded by the U.S. Army Corps of Engineers (USACE) to The Nutmeg Companies, Inc. (TNC), a small business contractor. The contract is for full facility restoration work at the Esek Hopkins U.S. Army Reserve Center in Cranston, Rhode Island, under the ARRA (American Recovery and Reinvestment Act) program. TNC has over 25 years of experience providing construction services as a prime contractor to federal agencies, including past awards from the Department of the Navy, Air National Guard, and General Services Administration. This contract has a total small business set-aside designation.
Quick answers
Who was awarded contract W912QR10C0002?
W912QR10C0002 was awarded to The Nutmeg Companies, Inc. by ENDIST Louisville (US Army Corps of Engineers) on October 9, 2009.
How much is contract W912QR10C0002 worth?
The government has obligated $8,806,545 on W912QR10C0002. Its current value, with exercised options, is $7,416,794.
Was contract W912QR10C0002 competed?
The extent of competition for W912QR10C0002 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.