Stilling basin modification

Ended Definitive Contract Awarded Last action

Contract number
W912QR07C0048
Awardee
Awarding agency
Obligated
$3,128,158

Award facts

Opportunity
  • W912QR07R0031 Solicitation number
Contract value 98% obligated
  • $3,128,158.22 Current, with exercised options
  • $3,183,158.22 Potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z211 Maint-Rep-Alt/Dams
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Falls of Rough, KY 40119, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action A00012 · Equitable adjustment for additional asphalt costs incurred by contractor, stilling basin modification, rough river lake, KY $30,015
Additional Work (new agreement, FAR part 6 applies) A00011 $44,139
Supplemental Agreement for work within scope A00010 · Road repairs, rough river stilling basin modification project, rough river lake, KY $19,200
Supplemental Agreement for work within scope A00009 · Install 200' additional fencing, rough river lake stilling basin modification, KY $7,980
Supplemental Agreement for work within scope A00008 · Compensation for field overhead costs incurred due to suspension of work because of high water, rough river lake stilling basin modification, KY $34,401
Additional Work (new agreement, FAR part 6 applies) A00007 · Stilling basin modification, rough river DAM, leitchfield, KY $14,800
Supplemental Agreement for work within scope A00006 · Pump out stilling basin and add additional rebar and concrete to sidewalk atop south wall, safety modifications at rough river DAM, kentucky $5,183
Supplemental Agreement for work within scope A00005 · Furnish and install concrete for MUD mat, rough river stilling basin modification, rough river lake, KY $4,208
Exercise an Option P00002 $43,000
Supplemental Agreement for work within scope A00004 · Apron turndown extension, rough river stilling basin modification, rough river, KY $7,400
Supplemental Agreement for work within scope A00003 · Furnish and install stone under extended parking lot, rough river stilling basin unsuitable material $9,064
Supplemental Agreement for work within scope A00002 · Unstable material removal, part II final, rough river stilling basin, KY -$14,500
Change Order A00001 · Remove unstable material and place concrete in areas shown on map, rough river stilling basin, KY $60,000
Change Order P00001 $0
Original award $2,863,268
Show all 15

Quick answers

Who was awarded contract W912QR07C0048?

W912QR07C0048 was awarded to HTA Enterprises, Inc. by ENDIST Louisville (US Army Corps of Engineers) on July 31, 2007.

How much is contract W912QR07C0048 worth?

The government has obligated $3,128,158 on W912QR07C0048. Its potential value, with all options, is $3,183,158.

Was contract W912QR07C0048 competed?

The extent of competition for W912QR07C0048 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award