W912PP17C0011 construct pumphouse and fuel storage, cannon air force base, curry county, new mexico.

Ended Definitive Contract Awarded Last action

Contract number
W912PP17C0011
Awardee
Awarding agency
Obligated
$21,065,224

Award facts

Opportunity
Contract value 100% obligated
$21,065,223.94 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Clovis, NM 88103, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00009 · A00009, C-014 credit clin 11 & clin 12 construct pumphouse and fuel storage -$17,500
Supplemental Agreement for work within scope A00008 · A00008 C-013 add road striping, curb pntg, stop bars north fitness center $4,668
Supplemental Agreement for work within scope A00007 · A00007, C-010 asphalt tie-in, C-011 add stair grounding, C-011 add building numbers construct pumphouse and fuel storage $23,575
Supplemental Agreement for work within scope A00006 · A00006, C-008 add static grounds/cathodic protection, C-009 add low point drains and containment pad, FY 17 construct pumphouse and tank storage, cafb $21,260
Supplemental Agreement for work within scope A00005 · A00005, C-007 add 8 fill stand pipe supports FY17 construct pumphouse and tank storage $7,434
Supplemental Agreement for work within scope A00004 · A00004, C-005 add pipe support C-006 raise fire HYD/add 4 valve box EXT FY17 construct pumphouse and tank storage $9,043
Supplemental Agreement for work within scope A00003 · A00003, C-004 led lighting FY17 construct pumphouse and tank storage $13,648
Supplemental Agreement for work within scope A00002 · A00002, C-003 Y-fittings/4" casing FY17 construct pumphouse and tank storage $10,758
Supplemental Agreement for work within scope A00001 · A00001 C-001 tank stair approach, C-002 add 4" DBB valve FY17 construct pumphouse and tank storage $19,337
Original award $20,973,000

About this award

This is a $21,065,223.94 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to MEB General Contractors Inc., a for-profit Subchapter S construction company based in Chesapeake, Virginia. The contract is for the construction of a pumphouse and fuel storage facility at Cannon Air Force Base in Curry County, New Mexico. The contract was awarded on September 30, 2017, with a completion date of June 16, 2020. This contract was not set aside for any socioeconomic program. MEB General Contractors Inc. has a robust history of federal government contracting, primarily serving the Department of Defense through large-scale infrastructure and facility upgrade projects.

Quick answers

Who was awarded contract W912PP17C0011?

W912PP17C0011 was awarded to MEB General Contractors Inc. by ENDIST Albuquerque (US Army Corps of Engineers) on September 30, 2017.

How much is contract W912PP17C0011 worth?

The government has obligated $21,065,224 on W912PP17C0011.

Was contract W912PP17C0011 competed?

The extent of competition for W912PP17C0011 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award