Definitive Contract W912PM21C0003
Award Date 12/20/20
Potential Completion Date 6/5/22
Potential Value $2.1M
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Goldsboro, NC 27530, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
6
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The U.S. Army Corps of Engineers, Wilmington District awarded Trend Construction Inc. a $512,413 firm fixed-price construction contract to repair the esplanade at the William O. Huske Lock and Dam located in Bladen County, North Carolina. The original solicitation requested bids to remove, regrade, and replace a portion of the existing concrete esplanade, grout inject joints between the retaining wall and lock wall, place additional riprap downstream of the lock, and cut and grout an existing...
- <p>This is a $8,992,134.35 definitive, firm-fixed-price contract awarded by the U.S. Army Corps of Engineers to Norfolk Dredging Company for coastal storm risk management projects in North Carolina. The work involves dredging and beach nourishment at Wrightsville Beach, Carolina Beach, Kure Beach, and Ocean Isle Beach. The contract has an ultimate completion date of April 30, 2022 and was awarded on October 15, 2021. There was no small business set-aside used for this procurement.</p>
- This is a $3,600,156.31 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) Wilmington District to Precon Marine Inc., a marine construction firm, for scour hole repair, boat ramp replacement, and paving work at Lock and Dam No. 1 on the Cape Fear River in Bladen County, North Carolina. The contract, which does not have a set-aside designation, has an ultimate completion date of April 30, 2011. Precon Marine Inc. has previously provided goods and services to the federal...
- The Department of the Army awarded a $26.1 million definitive contract to Norfolk Dredging Company for coastal storm risk management at Carolina Beach and Kure Beach, North Carolina, on November 16, 2025. The contract is firm fixed-price with no set-aside and an ultimate completion date of April 30, 2026. Work encompasses dredging, transporting, placing, and shaping beach fill material, along with pre- and post-construction surveys. The project calls for 800,000 cubic yards of fill at Carolina...
- This $2,877,775.37 firm fixed-price definitive contract was awarded by the U.S. Army Corps of Engineers to Cape Romain Contractors, Inc., a for-profit small business based in Charleston, South Carolina. The contract is for the construction of a fish passage on the Cape Fear River at Lock and Dam No. 1 in Bladen County, North Carolina. The project is funded through the American Recovery and Reinvestment Act (ARRA). The contract has an ultimate completion date of May 30, 2013 and was awarded on...
- The U.S. Army Corps of Engineers, Wilmington District awarded a firm fixed-price contract valued at $22,003,292.69 to Great Lakes Dredge & Dock Company, LLC for coastal storm risk management services at Carolina Beach and Kure Beach, North Carolina. The award is in response to a pre-solicitation notice seeking dredging, transporting, placing, planting and shaping of approximately 1.785 million cubic yards of beach fill material from the Kure Beach Borrow Area B to provide coastal protection....
- This is a $87,350.00 firm fixed-price purchase order awarded by the U.S. Army Corps of Engineers to T.d.mcghee CO., a self-certified small disadvantaged business, for the design and construction of a permanent weir and toe drain at Falls Lake in Wake Forest, North Carolina. The contract has a completion date of February 5, 2020 and was set aside for total small business participation. Based on T.d.mcghee CO.'s past prime federal contract work, the company has experience with coastal...
- The U.S. Army Corps of Engineers, Wilmington District awarded a $981,850 firm fixed-price construction contract to Ashridge Inc. to perform erosion protection work at Cell 2 of the Eagle Island Confined Disposal Facility in Brunswick County, North Carolina. The solicitation requested bids for constructing approximately 1,000 linear feet of erosion protection along the toe berm and dike toe on the Cape Fear River side, grading of the existing dike and toe berm, and placing bedding and riprap...
- This contract was awarded by the Department of the Army Corps of Engineers Engineering District Wilmington to Civil Works Contracting LLC, an SBA certified HUBZone firm, for erosion control repair work at the Wilmington, North Carolina area. The contract is a firm fixed price definitive contract with a potential value of $1,879,990.00. The contract has a total small business set-aside designation. Civil Works Contracting LLC is a limited liability company that provides diverse construction...
- The Department of the Army awarded a $28.1 million firm fixed-price definitive contract to Norfolk Dredging Company for maintenance dredging of Wilmington Harbor's Inner Ocean Bar on November 16, 2025, with ultimate completion by April 30, 2026. The originating solicitation, posted by the U.S. Army Corps of Engineers Wilmington District on February 7, 2025, calls for removal and disposal of approximately 1,350,000 cubic yards of shoaled material from the Cape Fear River to maintain a 44-foot...
The U.S. Army Corps of Engineers, Wilmington District awarded Conti Enterprises Inc. a definitive firm fixed-price contract valued at approximately $2.1 million to construct a new steel sheet pile weir structure in Goldsboro, North Carolina. The contract is associated with the NEUSE RIVER-GOLDSBORO SECTION 1135 solicitation, which sought to build the weir to an elevation of 58.0 feet NAVD 88 approximately 25 feet downstream of the city's existing temporary weir, and remove the original Corps weir and city's temporary structure. There was no set-aside designation for this procurement. Work is to be completed by June 2022 to support the Army Corps' flood risk management programs in the region.
Generated 12/29/23, 4:53 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
NEUSE RIVER-GOLDSBORO SECTION 1135 | W912PM20B0001 | Department of the Army Corps of Engineers Engineering District Wilmington | Pre-Solicitation 1/4 | 12/11/19, 9:17 AM | |
NEUSE RIVER-GOLDSBORO SECTION 1135 | W912PM20B0001 | Department of the Army Corps of Engineers Engineering District Wilmington | Solicitation 3/4 | 7/16/20, 6:20 PM | |
NEUSE RIVER-GOLDSBORO SECTION 1135 | W912PM20B0001 | Department of the Army Corps of Engineers Engineering District Wilmington | Pre-Solicitation 2/4 | 4/10/20, 10:26 AM | |
NEUSE RIVER-GOLDSBORO SECTION 1135 | W912PM21C0003 | Department of the Army Corps of Engineers Engineering District Wilmington | Award Notice 4/4 | 12/18/20, 8:54 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| A00002 | Other Administrative Action | ($17k) | 10/13/21 | |
| A00001 | Other Administrative Action | ($4) | 8/17/21 | |
| P00001 | Other Administrative Action | $0 | 2/10/21 | |
| Not listed | Not listed | $2.1m | 12/18/20 |