B1819 admin renovation

Ended Definitive Contract Awarded Last action

Contract number
W912PL24C0021
Awardee
Awarding agency
Obligated
$4,700,227

Award facts

Opportunity
  • W912PL24R0019 Solicitation number
Contract value 100% obligated
$4,700,226.61 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Lompoc, CA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00010 · Contract for B1819 admin reno-MDA. Reference no. R00010. Total contract price increased by $10,177.78.the contract completion date shall remain unchanged by… $10,178
Supplemental Agreement for work within scope A00009 · Contract for B1819 admin reno-MDA. Reference no. R00009 add 120 calendar days, the contract completion date shall be extended by 120 calendar days by reason… $0
Supplemental Agreement for work within scope A00008 · Contract for B1819 admin reno-MDA. Reference no. R00008 extend walls and provide power to vavs. Total contract price increased by $58,267.59. The contract… $58,268
Supplemental Agreement for work within scope A00007 · 59 day no cost time extension contract for B1819 admin reno MDA (MX) at vandenberg SFB, CA $0
Supplemental Agreement for work within scope A00006 · Contract for B1819 admin reno MDA (MX) at vandenberg SFB, CA WC007 title: 113 day no cost time extension add one hundred-thirteen (113) calendar days at no cost… $0
Supplemental Agreement for work within scope A00005 · Provide PS200 galvanized unistrut beam clamps, and 12-GA hangar wires at 48-inches on center between existing i-beams to suspend new t-bar ceiling system.… $21,323
Supplemental Agreement for work within scope A00004 · W912PL24C0021 B1819 admin reno-MDA (MX) modification no. R00004 - furr out CMU walls rooms 102,103,105. Total contract price increased by $12,941.06.the… $12,941
Supplemental Agreement for work within scope A00003 · B1819 admin renovation W912PL24C0021 B1819 admin reno-MDA (MX) modification no. R00003 - infill 2ND floor HVAC duct penetrations. Total contract price increased… $22,331
Supplemental Agreement for work within scope A00002 · Provide a credit for changing the drywall finishes required in specification section 09 29 00, paragraph 3.3, from a level 5 finish to a level 3 finish. Price… -$6,482
Supplemental Agreement for work within scope A00001 · Contract for B1819 admin reno MDA (MX) at vandenberg SFB, CA reference no. R00001 WC002 lobby and corridor total contract price is increased by $142,276.97.… $142,277
Original award $4,439,391
Show all 11

About this award

ENDIST Los Angeles awarded a $4.7 million definitive contract to MX Construction, Inc. for B1819 administrative renovation at Lompoc, California on October 1, 2024, under an 8(a) sole-source set-aside. MX Construction, Inc. is an Economically Disadvantaged Women-Owned Small Business and 8(a) Program Participant.

The contract scope covers flooring, HVAC, fire suppression, communications systems, and demolition work. Ultimate completion is scheduled for August 10, 2026. The pricing type is firm fixed price.

MX Construction subcontracted major renovation trades to specialized vendors: Floor Connection Inc. for floor installation, Smith Mechanical-Electrical-Plumbing for HVAC, RLH Fire Protection, Inc. for fire suppression systems, and Apple Valley Communications, Inc. for communications systems. Additional subcontractors include RK & G Construction Inc. (woman-owned small business) for doors, hardware, gypsum, and acoustical ceilings; Above Green LLC (woman-owned small business) for building commissioning; Dotzler Construction, Inc. (woman-owned small business, HUBZone) for concrete, plumbing, cabinets, and countertops; and MEC Environmental, LLC for demolition and environmental abatement.

The contract modification increased the total contract price by $10,177.78, with the ceiling value now $4.7 million. The completion date remains unchanged by this modification.

Subawards

Subcontractor Amount Awarded
Floor Connection Inc. B1819 ADMIN RENOVATION Floor installation $41,890
Smith Mechanical-Electrical-Plumbing B1819 admin renovation HVAC $945,369
Mcclanahan Inc. B1819 admin renovation tab $34,450
RLH Fire Protection, Inc. B1819 admin renovation fire suppression $58,000
Apple Valley Communications, Inc. B1819 admin renovation communications systems $255,775
RK & G Construction Inc. B1819 ADMIN RENOVATION Insulation, Steel Doors, Wood Doors, Hardware, Gypsum, Acoustical Ceilings $305,000
Above Green LLC B1819 admin renovation commissioning $69,720
Dotzler Construction, Inc. B1819 admin renovation concrete, plumbing, cabinets, and countertops $179,743
MEC Environmental, LLC B1819 admin renovation demo $413,991

Quick answers

Who was awarded contract W912PL24C0021?

W912PL24C0021 was awarded to MX Construction, Inc. by ENDIST Los Angeles (US Army Corps of Engineers) on October 1, 2024.

How much is contract W912PL24C0021 worth?

The government has obligated $4,700,227 on W912PL24C0021.

Was contract W912PL24C0021 competed?

The extent of competition for W912PL24C0021 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award