Valb CLC bldg 170

Ended Definitive Contract Awarded Last action

Contract number
W912PL19C0001
Awardee
Awarding agency
Obligated
$181,247,638

Award facts

Opportunity
Contract value 100% obligated
$181,247,638.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Long Beach, CA 90822, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00022 · The purpose of this contract action is to definitize the direct and indirect impacts associated with RFI-380. Both parties agree to complete and total… $996,183
Supplemental Agreement for work within scope A00166 · This contract action is for full and complete resolution of RFI-0583 known as new chilled water line as referenced in serial correspondence S0601 and S0927… $117,280
Supplemental Agreement for work within scope A00164 · Contract for community living center. R00182/CC292, CC296, CC297, and CC458. Total contract price increased by $325,091.00. The contract completion date shall… $325,091
Supplemental Agreement for work within scope A00163 · Valbclc remove existing 12-inch VAV (4-227S) & install new 16" VAV227S located in patient therapy RM. Work also includes rework of ducts, fire dampers, controls… $350,881
Supplemental Agreement for work within scope A00162 · VALBCLCR00180 CC521NEW patio railings CC534KITCHEN range/hood $207,102.00+30CD days. Relocate existing guard rail to the front edge of the slight curb created… $207,102
Supplemental Agreement for work within scope A00161 · Contract for community living center, VA long beach. R00179/CC526 additional AHU-2 work. Total contract price increased by $290,981.00. The contract… $290,981
Supplemental Agreement for work within scope A00160 · Contract for CLC, valb. R00178/CC532 exterior cameras. Total contract price increased by $382,333.00. The purpose of this contract action is to extend the POP… $382,333
Supplemental Agreement for work within scope A00159 · Clcvalb R00177CC493 CPE551 curb & gutter CC512CPE581 manifold pigtails CC513CPE#574 unforeseen conc strc CC517CPE586 turf RD drain line CC519CPE588R fedvet… $258,208
Supplemental Agreement for work within scope A00158 · CLC, valb R00176/CC535 CPE599 fire access LN connection per RFP 0141. Total contract price is incr by $462,579.00. Extend the POP an 30-days changing the… $462,579
Supplemental Agreement for work within scope A00157 · CLC, valb. R00175/CC531 SEC EQP RM 1109/CC533 public address master RM 1425. Total contract price is incr by $270,319.00. The POP is extended an additional 30CD… $270,319
Supplemental Agreement for work within scope A00156 · Contract no. W912PL19C0001 - VA long beach - community living center, modification no. R00174 - dishwasher (DI22) and ICE maker (IC04), contract price increased… $489,753
Supplemental Agreement for work within scope A00155 · Valb CLC bldg 170 REF no. R00173 total contract price remains unchanged.the contract completion date shall be extended by 30 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00154 · Contract for community living center, valb. R00172/CC529 20-day time extension. Total contract price is unchanged. Both parties agree with a time extension of… $0
Supplemental Agreement for work within scope P00021 · Contract for community living center valb. R00171/CC506-3 part 2 definitization of HVAC & tab. Total contract price is incr by $5,824,377.00. Both parties agree… $5,824,377
Supplemental Agreement for work within scope A00153 · Contract for CLC, valb.R00170/CC508 CPE556 swiss pearl panel EXT DRS/CC514 CPE584 replc light pole W/wall PKS/CC516 CPE561 investig into CFM & tab. Total… $143,215
Supplemental Agreement for work within scope A00152 · Contract for CLC, valb, CA 90822. R00169/CC490 CPE546 concrete encase waterline/CC497 patient safety system at courtyard B/CC503 concrete at pavers. Total… $276,140
Change Order P00020 · Contract for community living center, valb.reference no. R00168/CC506-2 part 1 revised- HVAC & tab. Total contract price is incr by $114,415.00. The contract… $114,415
Supplemental Agreement for work within scope A00151 · Contract for CLC, valb, long beach, CA 90822. Reference no. R00167/CC507 CPE#560 unforeseen ACM water line. Total contract price is increased by $464,459.00.… $464,459
Supplemental Agreement for work within scope A00150 · Contract for CL valb. R00166/CC468 CPE#285 doors, frames and hardware delay/CC476 CPE#542 partnering. Total contract price is increased by $409,135.00. The… $409,135
Supplemental Agreement for work within scope A00149 · Contract for CLC valb, R00164/CC489 CPE#531/CC495 CPE#558/CC496 CPE#554/CC498 add MED gas headwall/CC500 RFI1745 interface for PBX system. Total contract… $197,200
Change Order P00019 $199,343
Supplemental Agreement for work within scope A00148 · Contract for community living center, VA long beach at 5901 E. 7TH street, long beach, CA 90822. Reference no. R00163/CC505 14-day time extension. Total… $0
Supplemental Agreement for work within scope A00147 · Contract for CLC, valb at long beach, CA 90822. R00162/CC499 time EXT-weather delay. Total contract price is unchanged. The contract compl date shall remain… $0
Supplemental Agreement for work within scope A00146 · Contract for CLC, valb, long beach, CA 90822. R00161/CC483 CPE#540 low wall at kitchen. CC487 CPE#555 casework removal & patchwork. Total contract price is incr… $30,552
Supplemental Agreement for work within scope P00018 · Contract for community living center long beach, CA90822. R00160/CC486 CPE#536 TIA 21 broken chilled water. Total contract price is incr by $1,684,398.00. The… $1,684,398
Supplemental Agreement for work within scope A00145 · Contract for community living center, long beach, CA 90822. R00159/CC488 time extension -weather delay (FEB 2024). Total contract price is unchanged. The… $0
Supplemental Agreement for work within scope A00144 · Contract for CLC, valb at 5901 E. 7TH street, long beach, CA 90822. R00156/CC473 CPE#507/CC477 CPE#539/CC478 CPE#526/CC479 CPE#538/CC480 CPE#541. Total contract… $315,539
Supplemental Agreement for work within scope A00143 · Contract for community living center, VA long beach at 5901 E. 7TH street, long beach, CA 90822. Reference no. R00157/CC464 CPE#523 conduit to pump floats &… $176,644
Supplemental Agreement for work within scope A00142 · Contract for CLC valb at 5901 E. 7TH street, long beach, CA 90822. R00158/CC481 CPE#543 & CC482 CPE#548. Total contract price is incr by $53,359.00. The… $53,359
Supplemental Agreement for work within scope A00141 · Contract for CL, valb, long beach, CA 90822.R00155/CC450 ATS fiber run/CC470 repair MED gas pressure/repurge/CC475 balancing valves for HWR system. Total… $394,621
Supplemental Agreement for work within scope A00140 · Contract for CLC valb CA. R00154/CC448 site concrete insp/CC462 power to DDC panels/CC465 FUR out/CC471 parapet flashing/CC472 glass railing. Total contract… $215,791
Supplemental Agreement for work within scope P00017 · Contract for community living center, valb long beach, CA. Reference no. R00153/CC272-2 part 2-GOV't impacts due to soils. Total contract price is increased… $3,906,622
Supplemental Agreement for work within scope P00016 · Contract for community living center, long beach, CA 90822. R00152/CC469 CPE#524 TIA chilled waterline. Total contract price is incr by $4,033,687.00. The… $4,033,687
Supplemental Agreement for work within scope A00139 · Contract for community living center, VA long beach at 5901 E. 7TH street, long beach, CA 90822. REF no. R00151 CC460 CPE#518 storm drain system. Total contract… $450,000
Supplemental Agreement for work within scope A00137 · Contract for CLC, long beach, CA 90822. REF no. R00149/CC445 CPE459 power circuit to fcus/CC453 CPE511 power to condensate pumps. Total contract price is incr… $166,952
Supplemental Agreement for work within scope A00138 · Contract for CLC, long beach, CA 90822. REF no. R00150/CC454 CPE#512 change in voltage to EF's/CC455 CPE#513 power to pump actuator. Total contract price is… $87,228
Supplemental Agreement for work within scope A00135 · Contract for community living center, long beach, CA 90822. REF no. R00148/CC436 RFP-128 CPE#520 patient safety system. Total contract price is increased by… $471,318
Supplemental Agreement for work within scope A00134 · Contract for community living center, VA long beach, CA. REF no. R00147/CC438 CPE#489 federal holidays. Total contract price is incr by $478,284.00. The… $478,284
Supplemental Agreement for work within scope A00133 · Contract for CLC, valb. REF no. R00146/CC244 CPE#231 glass type/CC337 CPE#421 wall paneling/CC451 CPE#484 lobby entr/CC459 CPE#493 site stabiliz.total… $281,581
Supplemental Agreement for work within scope A00132 · Valb CLC bldg 170. R00145, no time $171,533
Supplemental Agreement for work within scope A00131 · Valb CLC bldg 170. R00144, no time. $228,002
Supplemental Agreement for work within scope A00130 · Valb CLC bldg 170. R00143 no time, 4 changes $296,048
Supplemental Agreement for work within scope A00129 · Valb CLC bldg 170. R00142 bulletin 16 part 8, no time $173,174
Supplemental Agreement for work within scope A00128 · Valb CLC bldg 170. R00141 CC261 CPE#239 access hatch at areaway lock CC288 CPE#198 added temp power CC329 CPE#474 added PVC roof at canopy $234,123
Supplemental Agreement for work within scope A00127 · Valb CLC bldg 170. R00140 - no time. $311,104
Supplemental Agreement for work within scope A00126 · Valb CLC bldg 170. R00139 CC308 CPE#433 added bars at footings CC320 CPE#388 run fire line through tunnel CC321 CPE#467 relocation of push button plates $127,084
Supplemental Agreement for work within scope A00125 · Valb CLC bldg 170. CC290 slurry coat waterproofing resolution no time. $457,713
Supplemental Agreement for work within scope A00124 · Valb CLC bldg 170. R00137 added HAT channel, no time. $459,568
Supplemental Agreement for work within scope P00015 · Valb CLC bldg 170. R00136 soil impact, no time. $2,412,530
Supplemental Agreement for work within scope A00122 · Valb CLC bldg 170. R00133 no time $470,047
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

ENDIST Los Angeles, a Defense Department organization, awarded a $181.2 million firm fixed-price definitive contract to S.j. Amoroso Construction Co., LLC on May 21, 2019, to definitize the direct and indirect impacts associated with RFI-380 on the VALB CLC Building 170 project. Both parties agree to complete and total resolution of RFI-380 and everything associated with it. The contract used no set-aside, and the prime holds no SBA set-aside certifications. Place of performance is Long Beach, California 90822, with an ultimate completion date of September 11, 2026.

Quick answers

Who was awarded contract W912PL19C0001?

W912PL19C0001 was awarded to S.j. Amoroso Construction Co., LLC by ENDIST Los Angeles (US Army Corps of Engineers) on May 21, 2019.

How much is contract W912PL19C0001 worth?

The government has obligated $181,247,638 on W912PL19C0001.

Was contract W912PL19C0001 competed?

The extent of competition for W912PL19C0001 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award