Design build - EDR water treatment and system design and construction activities including but not limited to the design build of a 6.0 million gallons per day (MGD) EDR water treatment plant. The…

Ended Definitive Contract Awarded Last action

Contract number
W912PL12C0022
Awardee
Awarding agency
Obligated
$102,878,710

Award facts

Opportunity
Contract value 100% obligated
$102,878,710.15 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Irwin, CA 92310, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00036 · Design build - FY12 water treatment: modification for equitable adjustment $370,764
Supplemental Agreement for work within scope A00002 · Design build - FY12 water treatment R00037 SI048, 49 & 50 - no time $448,222
Supplemental Agreement for work within scope P00035 $90,000
Supplemental Agreement for work within scope P00034 · Contract for water treatment and distribution system at fort irwin, california. Reference no. R00035. SI039 evaporation pond monitoring wells. Total contract… $382,900
Supplemental Agreement for work within scope P00033 · Contract for water treatment and distribution system at FT. Irwin, CA. Reference no. R00034. SI042 reverse cut & cap of existing pipes. Total contract price… $37,175
Supplemental Agreement for work within scope P00032 $128,847
Supplemental Agreement for work within scope P00031 $126,000
Supplemental Agreement for work within scope A00001 $0
Supplemental Agreement for work within scope P00030 $28,598
Supplemental Agreement for work within scope P00029 $10,680
Supplemental Agreement for work within scope P00028 $483,500
Supplemental Agreement for work within scope P00027 $60,900
Supplemental Agreement for work within scope P00026 $383,582
Supplemental Agreement for work within scope P00025 $21,459
Supplemental Agreement for work within scope P00024 $32,249
Supplemental Agreement for work within scope P00023 -$40,105
Supplemental Agreement for work within scope P00022 $212,421
Supplemental Agreement for work within scope P00021 $170,000
Supplemental Agreement for work within scope P00020 · Contract for water treatment and distribution system at fort irwin, california. Reference no. R00020 SI027 langford lake well l-5 depth change 14. Description… $73,000
Supplemental Agreement for work within scope P00019 · Design build - FY12 water treatment and distribution system at fort irwin, california. REF no.R00017 SI025 temporary tortoise mitigation fence 2. Change… $13,000
Supplemental Agreement for work within scope P00018 · Contract for water treatment and distribution system at fort irwin, california. Total contract price is increased by $269,000.00. The contract completion date… $269,000
Supplemental Agreement for work within scope P00017 · Design build - FY12 water treatment contract for water treatment and distribution system at fort irwin, california. Reference no. R00016 SI024 reroute RO… $66,000
Supplemental Agreement for work within scope P00016 · Contract for water treatment and distrubution system at fort irwin, california. Reference no. R00018. SI019 water line rescoping. Total contract is decreased by… -$155,000
Supplemental Agreement for work within scope P00015 · Design build - FY12 water treatment. Contract for water treatment and distribution system at fort irwin, CA. Contract amount increase $124,000.00. Reference no.… $124,500
Supplemental Agreement for work within scope P00014 · A. Scope of work SI021 deletion of cathodic protection this modification deletes the cathodic protection system for the PVC water line metallic components.… -$277,000
Supplemental Agreement for work within scope P00013 · 14. Description of modification (continued) a. Scope of work SI016 relocate power poles -SCE fee (RFI-0063) this modification compensates the government for… -$35,000
Supplemental Agreement for work within scope P00012 · A. Scope of work SI022 time extension additional 78 calendar days to current contract. The seventy-eight calendar days includes the following only: fifty-five… $0
Supplemental Agreement for work within scope P00011 · Contract for water treatment and distribution system at fort irwin, california. Reference no. R00011. SI018 temporary construction tortoise fencing. Total… $139,574
Supplemental Agreement for work within scope P00010 · Design build - FY12 water treatment. Contract for water treatment and distribution system at fort irwin, california. Contract amount decreased -$143,823.00,… -$143,823
Supplemental Agreement for work within scope P00009 · Contract for water treatment and distribution system at fort irwin, california. Reference no. R00009. SI017 desert tortoise exclusion fencing. Total contract… $99,076
Supplemental Agreement for work within scope P00008 · Design build - FY12 water treatment.contract for water treatment and distribution system at fort irwin, california. Contract amount decrease -$8,318.00,… -$8,318
Supplemental Agreement for work within scope P00007 $130,422
Supplemental Agreement for work within scope P00006 · Contract for water treatment and distribution system at fort irwin, california. Reference no. R00006. SI009 interior motor disconnects (RFI-0060). Total… -$23,183
Supplemental Agreement for work within scope P00005 · Design build - FY12 water treatment. Contract for water treatment and distribution system at fort irwin, california. AMT decreased -$379,959.00, reference no.… -$379,959
Supplemental Agreement for work within scope P00004 · R00004 SI006 water pipe segment at park (RFI-0049) delete water pipe segment at children's water park as shown on attachment 1. Design build - FY12 water… -$32,661
Supplemental Agreement for work within scope P00003 · R00003 SI005 EDR stack electrodes (RFI-0040) utilize carbon electrode at the GE stack EDR system in lieu of the specified metal electrode as approved in… -$20,070
Supplemental Agreement for work within scope P00002 · Design build - FY12 water treatment R00002 SI002 VECP2 remote site generators-fuel supply provide single fuel supply system (diesel) for all remote site… -$20,700
Other Administrative Action P00001 · Design build - FY12 water treatment reference no. R00001 SI008 electronic software - certified payroll $0
Original award $100,112,660
Show all 39

Description

Design build - EDR water treatment and system design and construction activities including but not limited to the design build of a 6.0 million gallons per day (MGD) EDR water treatment plant. The plant will treat all contaminants found in fort irwin's ground water in accordance with (IAW) federal and state requirements (i.e.: arsenic, fluoride, and total dissolved solids). The plant will include an electro-dialysis reversal (EDR) system as primary treatment. The project also includes the construction of the EDR facility with pumps, EDR stacks, filters, and an EDR waste equalization tank. The plant also includes treatment of the waste stream to achieve 99.8% potable water recovery rate with reject discharge to evaporation ponds. Construction also includes a 1 million gallon (MG) pretreatment tank and a 1 MG clear well tank. Project also includes control building, chemical building, treated water pump station, process drain pump station, standby generator, process piping, and SCADA. The project includes supporting utilities and infrastructure upgrades to the water plant include electric service, site improvements, communications, water, sewer, gas, storm water drainage and antiterrorism measures. Commissioning of the water treatment plant is also included. The water system improvements include pipelines connecting the water plant to bicycle lake booster station, replacement of expired pipe and equipment, and water supply /distribution system expansion. Other system improvements include improvement of fire flow, installation of a new water well at langford lake and connecting irwin basin wells to raw water transmission lines. Tank construction includes rehabilitation of existing welded steel water storage tanks and repair/replacement of a 1 MG above ground water storage tank. Sustainable design and development (SDD), energy independence and security act (eisa) of 2007, and energy policy act of 2005 (EPACT05) features will be included.

Quick answers

Who was awarded contract W912PL12C0022?

W912PL12C0022 was awarded to CDM Constructors Inc. by ENDIST Los Angeles (US Army Corps of Engineers) on September 12, 2012.

How much is contract W912PL12C0022 worth?

The government has obligated $102,878,710 on W912PL12C0022.

Was contract W912PL12C0022 competed?

The extent of competition for W912PL12C0022 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award