Construct a replacement hospital at fort irwin, CA to provide new tertiary care, emergency medicine, clinical support activities, and renovation of existing mary walker clinic. Vacated facilities will…

Ended Definitive Contract Awarded Last action

Contract number
W912PL12C0005
Awardee
Awarding agency
Obligated
$236,243,158

Award facts

Opportunity
Contract value 97% obligated
  • $236,244,894.20 Current, with exercised options
  • $244,089,450.20 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 9 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Irwin, CA 92310, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00196 · Construct the hospital replacement. R00047 signed JAN 2015. $20,238
Supplemental Agreement for work within scope P00195 · Construct the hospital replacement. R00046 ACO signed 2015 JAN 08 $145,320
Supplemental Agreement for work within scope P00194 · Construct the hospital replacement. ACO signed 15 JAN 2015. $20,000
Supplemental Agreement for work within scope P00193 · Construct the hospital replacement. SF30 ACO signed 07 JAN 2015. No time. $6,750
Supplemental Agreement for work within scope P00192 · Construct the hospital replacement. R00043 ACO signed 05 JAN 2015 $0
Supplemental Agreement for work within scope P00191 · Construct the hospital replacement. R00039 ACO signed 15 JAN 2015 no time $67,876
Supplemental Agreement for work within scope P00190 · R00038 SF30 ACO signed 05 DEC 2014 $21,448
Supplemental Agreement for work within scope P00189 · Construct the hospital replacement. R00037 signed 13 NOV 2014. No time MOD. $19,601
Supplemental Agreement for work within scope P00188 · Construct the hospital replacement. R00036 SF30 signed 13 NOV 2014. No time. $12,161
Supplemental Agreement for work within scope P00187 · Construct the hospital replacement R00034 signed 11 NOV 2014 $8,750
Supplemental Agreement for work within scope P00186 · Construct the hospital replacement. R00033 no time MOD. Cross bracing. $84,931
Supplemental Agreement for work within scope P00185 · Construct the hospital replacement. R00032 add plant spec. No time. -$2,500
Supplemental Agreement for work within scope P00184 · Construct the hospital replacement. R00031 b 17 revision of spec credit - no time. -$2,500
Supplemental Agreement for work within scope P00183 · Construct the hospital replacement. R00030 credit for corps trailer - no time. -$113,500
Supplemental Agreement for work within scope P00182 · Construct the hospital replacement. R00029 SF30 signed 02OCT2014. No time MOD. $4,667
Supplemental Agreement for work within scope P00181 · Construct the hospital replacement. R000028 SF30 signed 20 OCT 14. No time $21,909
Supplemental Agreement for work within scope P00180 · Construct the hospital replacement. R00027 SF30 signed 20OCT14. No time. -$3,750
Supplemental Agreement for work within scope P00179 · Construct the hospital replacement. R00026 SF30 signed 11 SEP 2014. No time. -$5,000
Supplemental Agreement for work within scope P00178 · Construct the hospital replacement. R00025 SF30 signed 29 NOV 2014. $7,200
Supplemental Agreement for work within scope P00177 · Construct the hospital replacement, global settlement part 2 $25,250,000
Supplemental Agreement for work within scope P00176 · Construct the hospital replacement global settlement and release $4,000,000
Change Order P00175 · Construct the hospital replacement $1,472,693
Supplemental Agreement for work within scope P00174 · SH461, SH464 & SH69 R00230 no time construct the hospital replacement $126,800
Supplemental Agreement for work within scope P00172 · SH457 SH459 SH460 no time R00229 construct the hospital replacement $56,900
Supplemental Agreement for work within scope P00171 · R00228 SH445 SH451 SH454 no time construct the hospital replacement $113,900
Supplemental Agreement for work within scope P00170 · R00227 no time - SH371, SH406 and SH437 construct the hospital replacement $160,000
Supplemental Agreement for work within scope P00169 · SH052 R00025 no time construct the hospital replacement $7,200
Supplemental Agreement for work within scope P00168 · SH449 & SH458 R00226 no time construct the hospital replacement $74,620
Supplemental Agreement for work within scope P00167 · SH462 & SH463 construct the hospital replacement $24,800
Supplemental Agreement for work within scope P00166 · SH431 & 438 no time construct the hospital replacement $16,100
Supplemental Agreement for work within scope P00165 · SH447, SH448, SH450, SH452, SH453 R00224 construct the hospital replacement $54,220
Supplemental Agreement for work within scope P00164 · SH440, SH441, SH442, SH444 & SH446 R00223 construct the hospital replacement $49,780
Supplemental Agreement for work within scope P00163 · SH433, SH434, SH435 & SH439 R00222 construct the hospital replacement $197,900
Supplemental Agreement for work within scope P00162 · SH432 no time construct the hospital replacement $149,960
Supplemental Agreement for work within scope P00161 · SH409, SH414 & SH418 R00219 no time construct the hospital replacement $54,500
Supplemental Agreement for work within scope P00158 · SH429 & SH430 R00217 no time construct the hospital replacement $42,800
Supplemental Agreement for work within scope P00160 · SH397; SH405; SH420 R00218 no time construct the hospital replacement $47,000
Supplemental Agreement for work within scope P00156 · SH398; SH417; SH419 R00215 no time construct the hospital replacement $40,600
Supplemental Agreement for work within scope P00157 · SH422, SH426 & SH428 R00216 construct the hospital replacement $48,200
Supplemental Agreement for work within scope P00155 · SH376, SH387, SH421 R00214 no time construct the hospital replacement $49,600
Supplemental Agreement for work within scope P00154 · SH415 R00213 time extension 100 CD compensable $149,000
Supplemental Agreement for work within scope P00153 · SH394 R00212 construct the hospital replacement $148,000
Supplemental Agreement for work within scope P00152 · SH392 & SH396 R00211 construct the hospital replacement $109,200
Supplemental Agreement for work within scope P00151 · R00210 SH180 construct the hospital replacement $143,000
Supplemental Agreement for work within scope P00150 · SH305 R00209 construct the hospital replacement $112,800
Supplemental Agreement for work within scope P00149 · SH395 R00207 construct the hospital replacement $7,000
Change Order P00148 · SH403 time extension of 21 calendar days construct the hospital replacement $0
Supplemental Agreement for work within scope P00147 · SH037 R00023 construct the hospital replacement $0
Supplemental Agreement for work within scope P00146 · SH058 R00022 construct the hospital replacement $33,500
Supplemental Agreement for work within scope P00145 · SH373 & SH393 R00203 construct the hospital replacement $41,500
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Description

Construct a replacement hospital at fort irwin, CA to provide new tertiary care, emergency medicine, clinical support activities, and renovation of existing mary walker clinic. Vacated facilities will be demolished. Supporting facilities include utilities, site improvements, parking, access roads, signage and environmental protection measures. The project will be designed in accordance with criteria prescribed in 000 unified facilities criteria (UFC) 4 -510-01, world class and evidence based design principles, 000 minimum anti terrorism standards for buildings UFC 4-010-01, barrier-free design in accordance with DOD criteria and the depsecdef memorandum "access for people with disabilities act dated october 31 2008, base architectural guidelines, and applicable energy conservation legislation. Enhanced commissioning, operations and maintenance (o & m) manuals, comprehensive interior design (CID), and construction (DOC) will be provided. Demolish 5 buildings (106,950 total SF).

Quick answers

Who was awarded contract W912PL12C0005?

W912PL12C0005 was awarded to Turner Construction Company by ENDIST Los Angeles (US Army Corps of Engineers) on May 9, 2012.

How much is contract W912PL12C0005 worth?

The government has obligated $236,243,158 on W912PL12C0005. Its current value, with exercised options, is $236,244,894. Its potential value, with all options, is $244,089,450.

Was contract W912PL12C0005 competed?

The extent of competition for W912PL12C0005 was full and open competition. The government received 9 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award