Recoveryproject#::114522::RP# construction of old mill creek sewer rehabilitation for ST. Louis metropolitan sewer district.
Ended Definitive Contract Awarded Last action
- Contract number
- W912P910C0405
- Awardee
-
SAK Construction LLC UEI LR28NMPH3Z37
- Awarding agency
-
ENDIST St Louis
US Army Corps of Engineers, Department of Defense
- Obligated
- $9,310,767
Award facts
- Opportunity
-
- W912P910R0702 Solicitation number
- RECOVERY--Y--RECOVERYPROJECT#::114522::RP# Construction of Old Mill Creek Sewer Rehabilitation for St. Louis Metropolitan Sewer District, St. Louis City, Missouri. Award Notice · Posted Oct 7, 2009
- Contract value 414% obligated
- $2,249,624.13 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- PSC
- Y244 Construct/Sewage & Waste
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- St Peters, MO 63366, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Vendor Address Change | $0 | |
| Vendor Address Change | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$321,659 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | -$0 | |
| Change Order | -$0 | |
| Change Order | $0 | |
| Change Order | $21,206 | |
| Change Order | $63,619 | |
| Change Order | -$63,624 | |
| Change Order | -$21,208 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $1,078 | |
| Change Order | $3,233 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $319,800 | |
| Change Order | $106,600 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | -$22,175 | |
| Change Order | $59,774 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | -$13,877 | |
| Modification | $7,000,000 | |
| Original award | $2,178,000 |
Show all 34
About this award
This is a $2,249,624.13 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers' St. Louis District to SAK Construction LLC, a for-profit limited liability company based in O'Fallon, Missouri. The contract is for the construction of the Old Mill Creek Sewer Rehabilitation project for the St. Louis Metropolitan Sewer District. This project involves the use of trenchless sewer rehabilitation techniques such as cured-in-place pipe (CIPP) installation and manhole rehabilitation to address aging and deteriorating underground infrastructure. The contract was awarded on a total small business set-aside basis, with a completion date of June 19, 2012.
Quick answers
Who was awarded contract W912P910C0405?
W912P910C0405 was awarded to SAK Construction LLC by ENDIST St Louis (US Army Corps of Engineers) on December 18, 2009.
How much is contract W912P910C0405 worth?
The government has obligated $9,310,767 on W912P910C0405. Its current value, with exercised options, is $2,249,624.
Was contract W912P910C0405 competed?
The extent of competition for W912P910C0405 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award