Recoveryproject#::111113::RP# portland avenue drainage improvements, phase 2 and phase 3, belleville, illinois. The work consists of improvements to sewers in belleville IL.
Ended Definitive Contract Awarded Last action
- Contract number
- W912P910C0404
- Awardee
-
Baxmeyer Construction Inc. UEI D3WNJHNFERL8
- Awarding agency
-
ENDIST St Louis
US Army Corps of Engineers, Department of Defense
- Obligated
- $3,310,875
Award facts
- Opportunity
-
- W912P909B0221 Solicitation number
- RECOVERY--Y--Project Number 111113, Portland Avenue Drainage Improvements, Belleville, Illinois -Tracker Number 65 and 67 Award Notice · Posted Sep 24, 2009
- Contract value 382% obligated
- $865,987.58 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- PSC
- Y244 Construct/Sewage & Waste
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Swansea, IL 62220, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | -$34,242 | |
| Change Order | $0 | |
| Change Order | $73,668 | |
| Change Order | $22,556 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $259 | |
| Change Order | $86 | |
| Change Order | $1,183 | |
| Change Order | -$4,818 | |
| Change Order | -$1,606 | |
| Change Order | $3,549 | |
| Change Order | $4,587 | |
| Change Order | $13,761 | |
| Change Order | $355 | |
| Change Order | $1,065 | |
| Change Order | $458 | |
| Change Order | $1,375 | |
| Change Order | $1,687 | |
| Change Order | -$3 | |
| Change Order | -$8 | |
| Change Order | $562 | |
| Change Order | -$21,540 | |
| Change Order | -$7,178 | |
| Change Order | $525 | |
| Change Order | $173 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $179,767 | |
| Change Order | $1,081 | |
| Change Order | $3,244 | |
| Change Order | $595,000 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Modification | $698,207 | |
| Original award | $1,777,122 |
Show all 36
About this award
This is a $865,987.58 firm fixed price contract awarded by the U.S. Army Corps of Engineers (USACE) St. Louis District to Baxmeyer Construction Inc., a small business subchapter S corporation, for the Portland Avenue Drainage Improvements, Phase 2 and Phase 3 project in Belleville, Illinois. The work consists of improvements to the sewer system in Belleville. The contract was awarded on November 25, 2009 and is set to be completed by September 26, 2011. This contract is a definitive contract, meaning it is a stand-alone contract not associated with a larger contract vehicle.
Quick answers
Who was awarded contract W912P910C0404?
W912P910C0404 was awarded to Baxmeyer Construction Inc. by ENDIST St Louis (US Army Corps of Engineers) on November 25, 2009.
How much is contract W912P910C0404 worth?
The government has obligated $3,310,875 on W912P910C0404. Its current value, with exercised options, is $865,988.
Was contract W912P910C0404 competed?
The extent of competition for W912P910C0404 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award