West shore lake pontchartrain, LA hurricane and storm damage risk reduction project, wslp 109 levee and floodwall, ST john the baptist parish, louisiana

Active Definitive Contract Awarded Last action

Contract number
W912P824C0041
Awardee
Awarding agency
Obligated
$23,378,133

Award facts

Opportunity
Contract value 95% obligated
$24,676,549.36 Current and potential, with all options
Completion date 86% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 9 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Kenner, LA 70062, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00006 · Phillips 66 pipeline impacts contract for west shore lake pontchartrain, louisiana, hurricane and storm damage risk reduction project, wslp-109 levee and… $51,795
Supplemental Agreement for work within scope A00005 · QTY VAR: clin 0007 contract for west shore lake pontchartrain, louisiana, hurricane and storm damage risk reduction project, wslp-109 levee and floodwall, ST.… $17,914
Supplemental Agreement for work within scope P00003 · DEI modification $0
Supplemental Agreement for work within scope A00003 · Weather (5/1/2025 - 7/31/2025) contract for west shore lake pontchartrain, louisiana, hurricane and storm damage risk reduction project, wslp-109 levee and… $0
Supplemental Agreement for work within scope A00002 · Weather (2/1/2025 - 4/30/2025) contract for west shore lake pontchartrain, louisiana, hurricane and storm damage risk reduction project, wslp-109 levee and… $0
Supplemental Agreement for work within scope A00001 · Weather (10/8/2024 - 1/31/2025) contract for west shore lake pontchartrain, louisiana, hurricane and storm damage risk reduction project, wslp-109 levee and… $0
Original award $23,275,555

About this award

The U.S. Army Corps of Engineers New Orleans District awarded a $23.4 million ceiling, firm fixed price definitive contract to Cycle Construction Company, L.L.C. on September 24, 2024, for levee and floodwall construction on the West Shore Lake Pontchartrain Hurricane and Storm Damage Risk Reduction Project (WSLP-109) in St. John the Baptist Parish, Louisiana. No set-aside was used on the award, although the originating pre-solicitation carried a Total Small Business set-aside under NAICS 237990 (Other Heavy and Civil Engineering Construction) with a $45 million size standard. The prime is described as a small business general contractor based in Kenner, Louisiana.

The solicitation covered clearing, floodwall and levee construction, drainage canal excavation, utility modifications, and related incidental work. It was procured as an Invitation for Bid resulting in a single firm fixed price contract, with an estimated construction magnitude of $25 million to $100 million. The pre-solicitation was posted July 17, 2024, with a due date of August 23, 2024. The contract title also references Phillips 66 pipeline impacts. Place of performance is listed as Kenner, Louisiana 70062, and the project work is located in St. John the Baptist Parish. The ultimate completion date is April 1, 2027.

Quick answers

Who was awarded contract W912P824C0041?

W912P824C0041 was awarded to Cycle Construction Company, L.L.C. by ENDIST New Orleans (US Army Corps of Engineers) on September 24, 2024.

How much is contract W912P824C0041 worth?

The government has obligated $23,378,133 on W912P824C0041. Its current value, with exercised options, is $24,676,549.

Was contract W912P824C0041 competed?

The extent of competition for W912P824C0041 was full and open competition. The government received 9 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities