NOV-NF-W-05A.2
Active Definitive Contract Awarded Last action
- Contract number
- W912P820C0050
- Awardee
-
B & K Construction Co L.l.c UEI FT7YM5MZY628
- Awarding agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Obligated
- $61,536,488
Award facts
- Opportunity
-
- New Orleans to Venice, LA, NOV-NF-W-05a. 2, Myrtle Grove to Woodpark Levee, Plaquemines Parish, Louisiana Pre-Solicitation · W912P820B0043 · Posted Apr 29, 2020
- New Orleans to Venice, LA, NOV-NF-W-05a. 2, Myrtle Grove to Woodpark Levee, Plaquemines Parish, Louisiana Award Notice · Posted Aug 25, 2020
- New Orleans to Venice, LA, NOV-NF-W-05a. 2, Myrtle Grove to Woodpark Levee, Plaquemines Parish, Louisiana Solicitation · Posted Jun 3, 2020
- New Orleans to Venice, LA, NOV-NF-W-05a. 2, Myrtle Grove to Woodpark Levee, Plaquemines Parish, Louisiana Pre-Solicitation · Posted May 15, 2020
- Contract value 100% obligated
- $61,536,488.20 Current and potential, with all options
- Completion date 81% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 4 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Braithwaite, Carlisle, LA 70040, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $1,796,637 | |
| Change Order | -$4,329,197 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $12,514 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $20,434 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $153,718 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $21,000 | |
| Supplemental Agreement for work within scope | $146,942 | |
| Supplemental Agreement for work within scope | $1,463,573 | |
| Definitize Change Order | $1,385,872 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$35,525 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $193,019 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $94,420 | |
| Supplemental Agreement for work within scope | $7,116 | |
| Supplemental Agreement for work within scope | $6,673 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $34,703 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $1,507,919 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $7,324 | |
| Supplemental Agreement for work within scope | $22,408 | |
| Supplemental Agreement for work within scope | $68,781 | |
| Supplemental Agreement for work within scope | $24,702 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $139,409 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $80,500 | |
| Supplemental Agreement for work within scope | $29,777 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $13,216 | |
| Definitize Change Order | $1,204,597 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $195,306 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
The U.S. Army Corps of Engineers, New Orleans District, awarded a $61.5 million definitive contract to B & K Construction Co L.l.c for construction of a new drainage canal between Myrtle Grove to Woodpark Levee in Plaquemines Parish, Louisiana, on August 24, 2020, under a total small business set-aside.
The originating solicitation (NOV-NF-W-05A.2) encompasses clearing, grubbing, vegetation removal, excavation, embankment placement, construction of access ramps and roads, floodgate installation, geotextile and surfacing material placement, drainage and sewer pipeline installation, and turf establishment. Place of performance is Braithwaite and Carlisle, Louisiana. The contract carries a firm fixed-price structure and an ultimate completion date of May 4, 2028. NAICS code 237990 applies (heavy and civil engineering construction).
Quick answers
Who was awarded contract W912P820C0050?
W912P820C0050 was awarded to B & K Construction Co L.l.c by ENDIST New Orleans (US Army Corps of Engineers) on August 24, 2020.
How much is contract W912P820C0050 worth?
The government has obligated $61,536,488 on W912P820C0050.
Was contract W912P820C0050 competed?
The extent of competition for W912P820C0050 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award