Magnolia pump station
Ended Definitive Contract Awarded Last action
- Contract number
- W912P818C0013
- Awardee
-
Clark Construction Enterprises LLC UEI F3RJDUFA2HK9
- Awarding agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Obligated
- $16,266,259
Award facts
- Opportunity
-
- W912P818B0019 Solicitation number
- New Orleans to Venice, Hurricane Protection System, NOV-NF-W-06B. 5, Magnolia Pump Station, Plaquemines Parish, Louisiana Award Notice · Posted Mar 2, 2018
- New Orleans to Venice, Hurricane Protection System, NOV-NF-W-06B. 5, Magnolia Pump Station, Plaquemines Parish, Louisiana Award Notice · Posted Dec 7, 2017
- Contract value 100% obligated
- $16,266,258.85 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- HUBZone
- Competition
- Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Pointe ã La Hache, LA 70082, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Funding Only Action | -$353,646 | |
| Supplemental Agreement for work within scope | $8,087 | |
| Supplemental Agreement for work within scope | $7,387 | |
| Supplemental Agreement for work within scope | $28,635 | |
| Supplemental Agreement for work within scope | $13,348 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $162,224 | |
| Supplemental Agreement for work within scope | $6,584 | |
| Supplemental Agreement for work within scope | $1,533 | |
| Supplemental Agreement for work within scope | $1,297 | |
| Change Order | $2,579 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $453,000 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $77,435 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $7,290 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $50,500 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $230,648 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Original award | $15,569,358 |
Show all 25
About this award
The U.S. government agency, ENDIST New Orleans, awarded a $16,266,258.85 Firm Fixed Price contract to Clark Construction Enterprises LLC, a HUBZone certified small business, for the MAGNOLIA PUMP STATION project. This definitive contract has a completion date of December 21, 2021 and was set aside for HUBZone firms. The contract was awarded on March 2, 2018 and the place of performance is Pointe à La Hache, Louisiana.
Quick answers
Who was awarded contract W912P818C0013?
W912P818C0013 was awarded to Clark Construction Enterprises LLC by ENDIST New Orleans (US Army Corps of Engineers) on March 2, 2018.
How much is contract W912P818C0013 worth?
The government has obligated $16,266,259 on W912P818C0013.
Was contract W912P818C0013 competed?
The extent of competition for W912P818C0013 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: HUBZone.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award