Lake ponchartrain and vicinity, hurricane protection project, I-10 HWY crossing levee enlargement reach LPV 109.02B south point to CSX railroad

Ended Definitive Contract Awarded Last action

Contract number
W912P810C0071
Awardee
Awarding agency
Obligated
$17,316,288

Award facts

Opportunity
Contract value 100% obligated
$17,316,287.85 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y299 Contruct/All Other Non-Bldg Facs
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
New Orleans, LA 70118, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00009 · Add far 52.222-50 combating trafficking in persons (FEB 2009) $0
Definitize Change Order A00020 · HPO - lake ponchartrain and vicinity, 109.02B, I-10 crossing levee enlargement, reach, south point to CSX railroad, orleans parish, LA. $26,360
Change Order A00019 -$86,634
Change Order A00018 · HPO - lake ponchartrain and vicinity, 109.02B, I-10 highway crossing levee enlargement, reach, south point to CSX railroad, orleans parish, LA. $0
Other Administrative Action A00012 · HPO - LPV 109.02B highway crossing levee enlargement, reach, south point to CSX railroad, orleans parish, LA. $0
Funding Only Action A00017 -$104,000
Change Order A00015 $42,348
Change Order A00016 $0
Other Administrative Action A00014 $0
Change Order P00007 -$14,063
Change Order A00011 $19,888
Change Order A00013 $14,693
Change Order A00010 $0
Change Order P00006 $555,000
Change Order P00005 $920,404
Change Order P00003 $0
Change Order P00002 · HPO - lake ponchartrain and vicinity, -$437,300
Supplemental Agreement for work within scope A00009 · CIN-011 substitute superpave asphalt ILO SMA for HPO - lake ponchartrain and vicinity, -$88,728
Change Order A00008 · CO-004 remove stockpiled material for HPO - lake ponchartrain and vicinity, $0
Change Order A00005 · CIN-003 definitize CO-001 for HPO - lake ponchartrain and vicinity, $8,194
Change Order A00006 · CO-002 inspect/transport bridge deck panels for HPO - lake ponchartrain and vicinity, $0
Supplemental Agreement for work within scope A00007 · CIN-006 to definitize CO-002 inspect/transport bridge panel for HPO - lake ponchartrain and vicinity, $12,217
Change Order A00004 · HPO - lake ponchartrain and vicinity administrative changes $0
Additional Work (new agreement, FAR part 6 applies) P00004 $12,295
Change Order A00003 $0
Change Order A00002 $8,290
Change Order A00001 · HPO - lake ponchartrain and vicinity, $0
Other Administrative Action P00001 $0
Original award $16,427,325
Show all 29

Quick answers

Who was awarded contract W912P810C0071?

W912P810C0071 was awarded to Barriere Construction Co., L.L.C. by ENDIST New Orleans (US Army Corps of Engineers) on April 8, 2010.

How much is contract W912P810C0071 worth?

The government has obligated $17,316,288 on W912P810C0071.

Was contract W912P810C0071 competed?

The extent of competition for W912P810C0071 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award