FY 25 petaluma river channel maintenance dredging project

Ended Definitive Contract Awarded Last action

Contract number
W912P725CA016
Awardee
Awarding agency
Obligated
$6,272,317

Award facts

Opportunity
Contract value 100% obligated
$6,272,317.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Petaluma, CA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00002 -$3,024,645
Supplemental Agreement for work within scope A00002 $0
Supplemental Agreement for work within scope A00001 $131,562
Original award FY 25 petaluma river channel maintenance dredging project, location: sonoma county california $9,165,400

About this award

The Army Corps of Engineers' Engineering District San Francisco (ENDIST San Francisco) awarded a $6.27 million firm-fixed-price definitive contract to The Dutra Group, doing business as Dutra Dredging, on August 28, 2025, for FY 25 Petaluma River channel maintenance dredging in Sonoma County, California. The award was made with no set-aside. The source states a $6.27 million ceiling value, and ultimate completion is February 11, 2026. It does not describe a base-plus-option structure.

Place of performance is Petaluma, California. The originating pre-solicitation, posted April 22, 2025, sought maintenance dredging of the Petaluma River channel to -8 feet MLLW with 1 foot of paid over-depth, plus transport of dredged material by reach. Reaches 1 through 6 go to a contractor-furnished upland beneficial reuse site, and reaches 7 through 9 go to aquatic site SF-10. The notice described full-and-open competition under NAICS 237990 with a $37,000,000 size standard and an estimated cost range of $5 million to $10 million.

Subcontract activity was recorded between September 25 and November 10, 2025. It covers fuel and slops removal, tug and towing services, scow mobilization and charters, and dredging quality monitoring (DQM) and surveying. Woolpert, Inc. handled DQM, surveys, and tug setup, and Billeter Marine LLC provided tug towing. Fuel, scow, and additional tug providers make up the remainder of the subcontracting team.

Subawards

Subcontractor Amount Awarded
Yaypen Supply, LLC FY 25 petaluma river channel maintenance dredging project $100,000
Ryzhka International LLC FY 25 petaluma river channel maintenance dredging project $50,000
Billeter Marine LLC FY 25 petaluma river channel maintenance dredging project $404,200
Woolpert, Inc. FY 25 petaluma river channel maintenance dredging project $66,964
Brusco Tug & Barge, Inc. FY 25 petaluma river channel maintenance dredging project $938,400
Brusco Tug & Barge, Inc. FY 25 petaluma river channel maintenance dredging project $60,300
R.e. Staite Engineering, Inc. FY 25 petaluma river channel maintenance dredging project $600,000

Quick answers

Who was awarded contract W912P725CA016?

W912P725CA016 was awarded to The Dutra Group by ENDIST San Francisco (US Army Corps of Engineers) on August 28, 2025.

How much is contract W912P725CA016 worth?

The government has obligated $6,272,317 on W912P725CA016.

Was contract W912P725CA016 competed?

The extent of competition for W912P725CA016 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award