Supplemental Agreement for work within scope
P00014
$0
Change Order
P00013
$737,703
Change Order
P00012 · Repair floors 2-4 infill slabs using 2IN. Ultra-high performance lightweight concrete (fiber/non-fiber) with pinned/sealed galvanized plates. Joist repairs…
$200,000
Change Order
P00011
$400,000
Definitize Change Order
P00010 · Contractor shall rebuild end wing slab to be flush with the existing structural slab and provide product data and shop drawings for final approval prior to…
$192,557
Supplemental Agreement for work within scope
P00009 · Cost escalation for sierra electric and peterson mechanical for delay.
$1,596,650
Supplemental Agreement for work within scope
A00066
$38,750
Supplemental Agreement for work within scope
P00008 · As a result of modification P00007 the period of performance and contract required completion date was extended to 3/20/2027. This change compensates all BRB…
$448,190
Supplemental Agreement for work within scope
P00007 · VR081-increase the period of performance by 361 calendar days, to include shotcrete remobilization and support, mechanical/electrical/plumbing storage costs,…
$1,867,939
Change Order
P00006 · VR086-1: RFI-0303 end room slab rebuild
$104,588
Change Order
A00063 · Contractor to demo additional material around existing windows to achieve a suitable installation surface for the new windows.
$269,138
Supplemental Agreement for work within scope
A00062 · Contractor is to provide fire dampers per updated specification 23 31 00. Additionally, fire damper locations were removed from the fire alarm sheets and…
$50,437
Supplemental Agreement for work within scope
A00061 · Per RFI-0262 contractor is to infill joist as shown in updated detail 08/08-SS6.01. Any interrupted bars are to follow detail 02/08-SS0.22. Per RFI-0257…
$33,701
Supplemental Agreement for work within scope
A00060 · Contractor is to demolish joist in way of collector bars and infill resulting void on gridline 8 on the fourth floor. Demo and resulting infill are to follow…
$46,792
Supplemental Agreement for work within scope
A00059 · Contractor is to demolish topping layers down to bottom structural layer with large aggregate. Once floor is down to structure, contractor is to survey…
$80,408
Supplemental Agreement for work within scope
A00058 · All interior doors are to be 7FT. Tall per updated door schedule and interior elevations.
$104,904
Supplemental Agreement for work within scope
A00057 · Contractor is to vacate the laydown yard to the west of bldg. 209. The medical center awarded a new contract and has rescinded the right to use the laydown…
$9,256
Supplemental Agreement for work within scope
A00056 · SF VA building 8
$19,051
Change Order
A00053 · SF VA building 8. Bilateral. VR053 RFP0053 window update.
$100,000
Change Order
A00052 · SF VA building 8 VR070 elevator lobby slab reference no. R00057 total contract price increased by $129,194.76. The contract completion date shall remain…
$129,195
Change Order
A00051 · SF VA building 8 VR055 entryway drain reference no. R00056 total contract price increased by $77,355.63. The contract completion date shall remain unchanged…
$77,356
Change Order
A00050 · SF VA building 8
-$15,096
Change Order
A00049 · SF VA building 8 VR063 slab joist infills updates reference no. R00054 total contract price increased by $199,216.12. The contract completion date shall…
$199,216
Change Order
A00047 · SF VA building 8 VR067 RAT slab removal reference no. R00052 total contract price increased by $45,102.45. The contract completion date shall remain unchanged…
$45,102
Change Order
A00048 · SF VA building 8 VR062 pull test credit total contract price decreased by $4500. The contract completion date shall remain unchanged by this modification.
-$4,500
Change Order
A00046 · SF VA building 8, change VR054/RFP055
$65,000
Change Order
A00045 · SF VA building 8 additional MEP curb RFI-0201 VR061 +$13,432.38
$13,432
Change Order
A00044 · SF VA building 8 VR060 dedicated TMS circuits (reference no. R00049) total contract price is increased by $3,546.61. The contract completion date shall remain…
$3,547
Change Order
A00043 · SF VA building 8 VR057 chiller update, reference no. R00048 total contract price is increased by $41,957.93. The contract completion date shall remain unchanged…
$41,958
Change Order
A00042 · SF VA building 8 VR056 additional floor float & chiller well reference no R00047 the total contract price is increased by $ 318,234.28 the contract completion…
$318,234
Change Order
A00041 · SF VA building 8, change VR058/RFP-059
$7,306
Change Order
A00040 · SF VA building 8 VR050 new campus network connection reference no. R00045
$42,093
Supplemental Agreement for work within scope
A00039 · SF VA building 8, change VR044/RFP-054
$36,500
Change Order
A00038 · VR047 gravity beam changes contract for bldg 8 seismic retrofit at 4150 clement street, SAN francisco. Reference no. R00043 total contract price is increased by…
$15,736
Change Order
A00037 · SF VA building 8 VR024 plumbing change reference no.R00042 total contract price is increased by $151,537.04 the contract completion date shall remain…
$151,537
Change Order
A00036 · SF VA building 8 reference no. R00041 VR043 door changes
$11,204
Change Order
A00035 · SF VA building 8 reference no. R00040 VR037 shearwalls at GL 4 & 10 total contract price is increased by $165,230.04. The contract completion date shall…
$165,230
Change Order
A00034 · SF VA building 8 BIM model integration contract for bldg 8 seismic retrofit at 4150 clement street, SAN francisco, CA 94121. Reference no. R00039 VR048 BIM…
$54,696
Change Order
A00033 · SF VA building 8 VR 038 MEP shaft GS 5 & a
$165,535
Change Order
A00032 · SF VA building 8 VR046 micropile waterproofing
$57,366
Definitize Change Order
P00005 · SF VA building 8 seismic retrofit- definitize P00003 for pile cap and grade beam depths.
$2,091,605
Change Order
A00031 · SF VA building 8 VR041 additional dobie data
$212,873
Change Order
A00030 · SF VA building 8 VR045 electrical room switch
$0
Change Order
A00029 · SF VA building 8 VR035 janitor's closets
$126,793
Change Order
A00028 · SF VA building 8 VR036 MEP roof structure infill
$59,786
Change Order
A00027 · SF VA building 8 VR042 spalling investigation
$0
Change Order
A00026 · SF VA building 8 VR040, existing elevator shaft changes
$18,503
Change Order
A00025 · SF VA building 8 VR032 additional joist infill
$361,374
Supplemental Agreement for work within scope
P00004 · SF VA building 8 VR034 western stair gradebeam access
$568,923
Change Order
A00024 · SF VA building 8 VR025, fire safety updates
The Department of Veterans Affairs, through ENDIST San Francisco, awarded a $65.4 million definitive contract to Brice Builders, LLC, an Alaska Native Corporation-owned 8(a) firm, for seismic retrofit work at San Francisco VA Medical Center Building 8 on March 1, 2023, under an 8(a) sole-source set-aside.
The contract is firm fixed price. Work includes repair of floors 2–4 infill slabs using 2-inch ultra-high performance lightweight concrete (fiber and non-fiber variants) with pinned and sealed galvanized plates, and joist repairs per plan. Fireproofing membrane and floor float work are descoped. Place of performance is San Francisco, CA. Ultimate completion is March 24, 2027.
Quick answers
Who was awarded contract W912P723C0005?
W912P723C0005 was awarded to Brice Builders, LLC by ENDIST San Francisco (US Army Corps of Engineers) on March 1, 2023.
How much is contract W912P723C0005 worth?
The government has obligated $65,153,277 on W912P723C0005. Its current value, with exercised options, is $65,550,429.
Was contract W912P723C0005 competed?
The extent of competition for W912P723C0005 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.