Arra::yes::arra recoveryproject#::104637::RP# GLU-LAM beam replacement, WSD fish hatch recovery -- MARRA260 09-dry creek arra fhvc GLU-lams. The purpose of the work is to replace a damaged…
Ended Definitive Contract Awarded Last action
- Contract number
- W912P710C0007
- Awardee
-
B & B Construction, Inc. UEI GDACNDMK5UK5
- Awarding agency
-
ENDIST San Francisco
US Army Corps of Engineers, Department of Defense
- Obligated
- $73,400
Award facts
- Opportunity
-
- W912P709R0023 Solicitation number
- RECOVERY Glu-Lam Beam Replacement, WSD Fish Hatchery, Lake Sonoma, CA Award Notice · Posted Nov 17, 2009
- Contract value 100% obligated
- $73,400.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 238350 Finish Carpentry Contractors
- PSC
- Z179 Maint-Rep-Alt/Other Warehouse Bldgs
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 5 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Geyserville, CA, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $13,400 | |
| Original award | $60,000 |
About this award
This is a definitive, firm-fixed price contract awarded by the U.S. Army Corps of Engineers (USACE) to B & B Construction, Inc. (doing business as Tim & Matt Brown Construction), a woman-owned, veteran-owned small business, in the amount of $73,400.00. The purpose of the contract is to replace a damaged structural glue-laminated beam and appurtenances within the main building of the Don Clausen Fish Hatchery in Geyserville, California. This contract is part of the American Recovery and Reinvestment Act (ARRA) and is designated as Recovery Project #104637. The work is required to support the hatchery's fish rearing activities for endangered steelhead trout and coho salmon. This contract is not set aside.
Description
Arra::yes::arra recoveryproject#::104637::RP# GLU-LAM beam replacement, WSD fish hatch recovery -- MARRA260 09-dry creek arra fhvc GLU-lams. The purpose of the work is to replace a damaged structural GLU-LAM beam and appurtenances within the main building to the DON clausen fish hatchery. The beam, situated within the southeast entrance area, serves as a support member for the building s upper (2ND) floor. The upper floor houses an interpretive center open for public education, while the lower floor is where fish and game personnel conduct fish rearing activities for the endangered steelhead trout and coho salmon. Directly below the worksite are a series of fish rearing tanks, which will need to be protected during work activity.
Quick answers
Who was awarded contract W912P710C0007?
W912P710C0007 was awarded to B & B Construction, Inc. by ENDIST San Francisco (US Army Corps of Engineers) on February 26, 2010.
How much is contract W912P710C0007 worth?
The government has obligated $73,400 on W912P710C0007.
Was contract W912P710C0007 competed?
The extent of competition for W912P710C0007 was full and open competition. The government received 5 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award