FY21 cssc O & M:barrier IIA encl. Contract

Ended Definitive Contract Awarded Last action

Contract number
W912P621C0022
Awardee
Awarding agency
Obligated
$5,764,352

Award facts

Opportunity
Contract value 100% obligated
$5,764,352.03 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Romeoville, IL 60446, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00021 · A. Scope of work $113,306
Terminate for Convenience P00002 · Case NN031 - partial termination for convenience of the government - vsrs $3,733
Change Order A00020 · Case NN029 - time extension for disconnect switches $0
Change Order A00019 · Case no. NN028 - site investigation for VSR $31,387
Change Order P00001 · Case number NN027 - connect raceway roof to 2A REV 1 $160,145
Change Order A00018 · NN015 - change fiberglass gutters to metal, NN018 - relocating wall to clear overhead bus bar, NN020 - add exit lights, NN022 - REA for roof furring strips,… $97,807
Change Order A00017 · NN026 - time extension for completing mods $0
Change Order A00016 · Time extension for delay of switches $0
Change Order A00015 · Time extension FO rcompleting modification $0
Change Order A00014 · Revision of power source panels -$12,488
Change Order A00013 · FY21 cssc O & M:barrier IIA encl. Contract costs of design delay $311,991
Change Order A00012 · Time extension to complete delay costs $0
Supplemental Agreement for work within scope A00011 · Additional time for negotiation of modification $0
Change Order A00010 · Additional time for modification proc $0
Change Order A00009 · Time extension to allow for negotiation $0
Change Order A00008 · 2B duct bank obstruction $120,343
Change Order A00007 · Time extension for partial suspension $0
Change Order A00006 · Partial suspension of raceway work $84,840
Change Order A00005 · Differing site conditions, remove abandoned generator conduit $20,784
Change Order A00004 · Change overhead door spec $95,341
Change Order A00003 · Time extension due to covid supply delay $0
Change Order A00002 · Reconnection of grounding $8,585
Change Order A00001 · Contract clarifications $193,578
Original award $4,535,000
Show all 24

About this award

The Department of the Navy ENDIST Chicago awarded a $5.76 million definitive contract to Accel Construction Services Group, LLC, an SBA Certified 8(a) Program Participant, for construction of an enclosure at the 2A Raceway fish barrier on September 29, 2021, under a total small business set-aside.

The originating solicitation, posted in March 2021, sought construction services at the United States Army Corps of Engineers' fish barrier facility in Romeoville, Illinois. The contractor is responsible for constructing enclosures over the barrier raceway and rectifiers, installing grounding bus bars, lighting, and heating systems. The contract carries a firm fixed price and an ultimate completion date of June 5, 2025. Place of performance is Romeoville, IL.

Quick answers

Who was awarded contract W912P621C0022?

W912P621C0022 was awarded to Accel Construction Services Group, LLC by ENDIST Chicago (US Army Corps of Engineers) on September 29, 2021.

How much is contract W912P621C0022 worth?

The government has obligated $5,764,352 on W912P621C0022.

Was contract W912P621C0022 competed?

The extent of competition for W912P621C0022 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award