CHL chamber floor and wall repairs located in chicago, IL - $19,603,980.00

Active Definitive Contract Awarded Last action

Contract number
W912P621C0020
Awardee
Awarding agency
Obligated
$43,055,065

Award facts

Opportunity
Contract value 100% obligated
$43,055,065.45 Current and potential, with all options
Completion date 90% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Chicago, IL 60611, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00008 · Chicago harbor lock chamber floor and wall repairs modification $0
Supplemental Agreement for work within scope A00011 · NN0019- railing layout on chamber walls. Additional in scope work to realign the railing to prevent damage in boating season. $69,436
Change Order A00010 $236,353
Change Order P00007 · NN013 sidewalk demolition depth and slab thickness $3,306,848
Change Order A00009 · Case NN016 - REA - paint, joints, cleats, rebar $73,586
Change Order A00008 · Case NN015 - USACE trailer $39,197
Change Order A00007 · NN014 - REA - geotextile fabric $176,104
Change Order A00006 · Case number NN012 - REA DSC for lock bottom $87,844
Change Order A00005 · NN011 - sheetpile protruding into chamber $48,267
Change Order A00004 · REA cut off sheetpile in way of demo slab $31,675
Change Order A00003 · Addition of BIL signs to the contract $4,416
Change Order P00006 · Tension micropiles $0
Change Order A00002 · REA-additional items due to DSC $42,601
Exercise an Option P00005 · CHL chamber floor and wall repairs contract modification to exercise option 2. $11,290,458
Other Administrative Action P00004 · Admin MOD, wage rates IL20210018 $0
Change Order P00003 · POP extension from 04 june 2024 to 04 june 2025 $0
Exercise an Option P00002 · CHL chamber floor and wall repairs base, exercised option 1 $8,044,300
Change Order A00001 · Correcting option clins $0
Other Administrative Action P00001 · CHL chamber floor and wall repairs notice to proceed $0
Original award $19,603,980
Show all 20

About this award

The U.S. Army Corps of Engineers Chicago District awarded a $43.1 million definitive contract to J.F. Brennan Company, Inc. for Chicago Harbor Lock chamber floor and wall repairs on September 29, 2021, under full and open competition with no set-aside.

The work addresses structural rehabilitation of the lock chamber to prevent deterioration and ensure the structure can withstand weather and vessel traffic. Place of performance is Chicago, IL. The contract runs through June 4, 2027 at firm fixed price. The originating solicitation, posted June 23, 2021 with proposals due August 31, 2021, was estimated between $25 million and $100 million and classified under NAICS 237990 (other heavy and civil engineering construction).

Quick answers

Who was awarded contract W912P621C0020?

W912P621C0020 was awarded to J.f. Brennan Company, Inc. by ENDIST Chicago (US Army Corps of Engineers) on September 29, 2021.

How much is contract W912P621C0020 worth?

The government has obligated $43,055,065 on W912P621C0020.

Was contract W912P621C0020 competed?

The extent of competition for W912P621C0020 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award