- <p>The Department of the Army Corps of Engineers Engineering District Chicago awarded a Firm Fixed Price Definitive Contract worth $751,828.69 to Amalgamated / Hill JV, LLC, a joint venture small disadvantaged business, for the replacement of the FB 2A Cooling System. This contract has a Total Small Business set-aside designation. The work will be performed in Romeoville, Illinois.</p>
- The U.S. Department of the Army Corps of Engineers awarded a Firm Fixed Price Definitive Contract in the amount of $131,500.00 to B-Ct JV, a joint venture women-owned small business, for the installation of cooling equipment at a facility in Romeoville, Illinois. The contract has a completion date of February 16, 2024. The original solicitation was a pre-solicitation notice for a construction project to upgrade the cooling system in the Power Quality Building at the Chicago Sanitary and Ship...
- The Department of the Army Corps of Engineers Engineering District Louisville awarded a firm fixed-price purchase order to Coulee Region Mechanical Contractors, Inc., a woman-owned small business, to modify an existing modular chiller at a facility in Homewood, Illinois. The contract, valued at $112,000.00, has a completion date of October 24, 2019 and was set aside for total small business participation. The original solicitation, a request for quote (RFQ), was posted on June 26, 2019 and...
- The General Services Administration (GSA) Public Buildings Service Region 5 has awarded a firm-fixed price, definitive contract to Voris Mechanical Inc., a woman-owned small business, to replace chillers, cooling towers, and transformers at the Paul Findley Federal Building and U.S. Courthouse in Springfield, Illinois. The $1,374,046.48 contract is a total small business set-aside and has a completion date of October 1, 2021. Voris Mechanical Inc. has previously completed similar mechanical...
- The U.S. Army Corps of Engineers, Chicago District awarded a $29,747.43 firm fixed-price purchase order to Arabic Interpreters LLC, doing business as MZ Federal, for condenser coil replacement services at the Chicago Sanitary and Ship Canal Fish Dispersal Barrier AHU1 facility in Lockport, Illinois. The contract, awarded on January 29, 2026, with an ultimate completion date of March 7, 2026, was designated as a Total Small Business set-aside procurement. MZ Federal, a self-certified small...
- The U.S. Army Corps of Engineers awarded a purchase order valued at $422,645.53 on September 18, 2025, to Better By Design LLC for performance at Morris, Illinois, with a completion deadline of December 5, 2025. The contract is structured as a Firm Fixed Price agreement with no set-aside designation. Better By Design LLC, a Brookfield, Missouri-based small business, holds multiple SBA certifications including Economically Disadvantaged Women-Owned Small Business (EDWOSB), 8(a) Program...
- This is a $38,380.65 firm fixed-price purchase order awarded by the U.S. Army Corps of Engineers to Supplied Industrial Solutions, Inc., an 8(a) certified small disadvantaged business. The contract is for the FY25 DEMO BARRIER AHU REPLACEMENT project in Chicago, Illinois, with a performance period ending on May 5, 2025. Supplied Industrial Solutions, Inc. is a veteran-owned, minority-owned small business that holds several indefinite delivery vehicles (IDVs) with the Army Corps of Engineers...
- The Department of the Army Corps of Engineers awarded a purchase order contract to American Building Environments LLC, doing business as American Mechanical, for $2,930.00 to provide a Liebert chiller for a district server room in St. Louis, Missouri. The contract has a firm fixed price and a completion date of July 10, 2021. It was set aside for total small business participation. American Building Environments LLC, a limited liability company operating as a for-profit organization, has...
- This $276,560 firm fixed price purchase order was awarded by the Department of the Army Corps of Engineers to Reagent World Inc. for the replacement of two air-cooled air compressors, an air receiver with a minimum 127 cubic foot capacity, and optional additional receivers and compressed air piping at the Carlyle Lake/Kaskaskia facility in Carlyle, Illinois. The solicitation also provided an option to replace one 480V panelboard, 480V-208Y/120V transformer and one 208Y/120V panelboard. The...
- The U.S. Defense Department's Construction and Equipment division awarded a delivery order valued at $42,192.21 to Supplycore LLC for an air-cooled water scroll chiller cooling unit. The award, issued on October 12, 2025, represents a firm fixed-price procurement with a completion deadline of January 28, 2026, and will be performed in Rockford, Illinois. This delivery order was issued on a non-competitive, non-set-aside basis and falls under a broader multiple-award indefinite delivery...
Voris Mechanical Inc. was awarded a $823,407 firm fixed price definitive contract by the U.S. Army Corps of Engineers, Chicago District, to replace the cooling system and filtration equipment at the Barrier IIIB facility in Romeoville, Illinois. The solicitation sought an air-cooled chiller package and plate and frame heat exchangers to replace the existing cooling tower and filtration system. Designated as a total small business set aside opportunity under NAICS code 237110 for heavy and civil engineering construction, the contract supports the Corps' mission to maintain critical infrastructure and addresses the need identified in the solicitation to upgrade the more than $500,000 cooling system at the Barrier IIIB location. Performance will take place at the Romeoville facility and conclude in March 2022.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
USACE CHICAGO DISTRICT - Replace IIB Cooling System | W912P620C0029 | Department of the Army Corps of Engineers Engineering District Chicago | Award Notice 3/3 | 10/1/20, 2:44 PM | |
USACE CHICAGO DISTRICT - Replace IIB Cooling System | W912P620B0028 | Department of the Army Corps of Engineers Engineering District Chicago | Pre-Solicitation 1/3 | 8/12/20, 1:07 PM | |
USACE CHICAGO DISTRICT - Replace IIB Cooling System | W912P620B0028 | Department of the Army Corps of Engineers Engineering District Chicago | Solicitation 2/3 | 8/26/20, 6:13 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| A00003 | Change Order | $91.0k | 11/29/21 | |
| A00002 | Change Order | $4.6k | 9/7/21 | |
| A00001 | Change Order | $14.8k | 6/25/21 | |
| Not listed | Not listed | $713.0k | 9/30/20 |