Upgrade perimeter chain-link fence to concrete-panels, replace north and south gates W ITH access control, install close- circuit television (CCTV) and post bollards. Provide new 30-foot high light…

Ended Definitive Contract Awarded Last action

Contract number
W912P618C0014
Awardee
Awarding agency
Obligated
$3,413,095

Award facts

Opportunity
Contract value 100% obligated
$3,413,094.56 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
East Chicago, IN 46312, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00002 · Removal of access road and final quantities $30,819
Supplemental Agreement for work within scope A00001 · Dispose gravel in CDF $26,801
Other Administrative Action P00002 · Deobligation nmod - the funding was applied to individual obligation line items in cefms. The funding will be reapplied in a subsequent modification by… -$3,355,474
Other Administrative Action P00003 · Precast concrete wall installation $3,355,474
Other Administrative Action P00001 · Admin correction to correct obligation error made at cefms (line item 0013AB, stamped-concrete pavement installation) $0
Original award $3,355,474

About this award

This is a definitive, firm fixed-price contract awarded by the Department of the Army Corps of Engineers to Schwartz Construction Group, Inc., a self-certified small disadvantaged business, to perform various facility upgrades at a location in East Chicago, Indiana. The contract scope includes upgrading the perimeter chain-link fence to concrete panels, replacing the north and south gates with access controls, installing closed-circuit television (CCTV), and other site improvements such as new light poles, flag poles, and an access road. The total potential value of the contract is $3,413,094.56, and it was awarded on September 17, 2018 with a scheduled completion date of October 18, 2019. The contract was set aside for small businesses.

Description

Upgrade perimeter chain-link fence to concrete-panels, replace north and south gates W ITH access control, install close- circuit television (CCTV) and post bollards. Provide new 30-foot high light poles and electrical service to northern gate. Install three flag poles W ITH solar-POW ered lighting. Demolish and remove and dispose of existing concrete curbs along indianapolis boulevard in addition to the chain-link fence materials. Install gravel access road along outside of fencing on north side of facility. Optional W ORK consists of replacing sections of sidew ALK along indianapolis boulevard, replacing existing stone along indianapolis boulevard W ITH architectural concrete, and installing planter security bollards along indianapolis blvd near each gate.

Quick answers

Who was awarded contract W912P618C0014?

W912P618C0014 was awarded to Schwartz Construction Group, Inc. by ENDIST Chicago (US Army Corps of Engineers) on September 17, 2018.

How much is contract W912P618C0014 worth?

The government has obligated $3,413,095 on W912P618C0014.

Which agency awarded contract W912P618C0014?

ENDIST Chicago (US Army Corps of Engineers) awarded W912P618C0014, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W912P618C0014 competed?

The extent of competition for W912P618C0014 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award