Arra::yes::arra chicago harbor lock gates replacement project

Ended Definitive Contract Awarded Last action

Contract number
W912P609C0015
Awardee
Awarding agency
Obligated
$17,669,603

Award facts

Opportunity
Contract value 111% obligated
$15,967,338.53 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Chicago, IL 60611, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00031 -$45,570
Funding Only Action P00031 · Deobligation of unexpended funds -$56,581
Additional Work (new agreement, FAR part 6 applies) P00030 · Fabrication & painting of west sector $0
Additional Work (new agreement, FAR part 6 applies) P00030 · MOD P00024, HPU revisions $0
Additional Work (new agreement, FAR part 6 applies) P00029 · Fabrication & painting of west sector $0
Additional Work (new agreement, FAR part 6 applies) P00029 · MOD P00024, HPU revisions $0
Funding Only Action P00028 $0
Funding Only Action P00028 · This modification is for a credit to the government. -$2,000
Change Order P00027 $24,948
Change Order P00027 · Deleting lifting beam delivery, gate survey, deleting HPU recess grating, and adjusting the price for champion bond amount -$7,728
Additional Work (new agreement, FAR part 6 applies) P00026 · Arra::yes::arra addition of clins 0060 through 0070 for additional work, such as replacing limit switches, performing lock openings, and providing misc. HPU… $200,614
Additional Work (new agreement, FAR part 6 applies) P00026 · Addition of clins 0060 through 0070 for additional work, such as replacing limit switches, performing lock openings, and providing misc. HPU changes. Addition… $193,474
Change Order P00025 · This modification decreased the contract total amount in arra funding. MOD P00024, HPU revisions $0
Change Order P00025 · Arra::yes::arra close out modification reflects final quantities. Total contract is decreased by $200,614.00 in arra funding. -$200,614
Supplemental Agreement for work within scope P00024 · Arra::yes::arra case NN038 demolish existing concrete and construct revised cantilever slab, relocate electrical conduits and associated wiring and modify… $0
Supplemental Agreement for work within scope P00024 · Case NN038 demolish existing concrete and construct revised cantilever slab, relocate electrical conduits and associated wiring and modify handrail system; case… $0
Supplemental Agreement for work within scope P00023 · Arra::yes::arra case NN073 implement increased funds reservation for various construction activities based on anticipated costs associated with pending… $0
Supplemental Agreement for work within scope P00023 · Case NN073 implement increased funds reservation for various construction activities based on anticipated costs associated with pending repairs to hydraulic… $400,000
Supplemental Agreement for work within scope P00022 · Case NN070 establish allowance for construction activities including services necessary to improve overall safety and operation of lock gates, such as repairs… $970,000
Supplemental Agreement for work within scope P00022 · Arra::yes::arra case NN070 establish allowance for construction activities including services necessary to improve overall safety and operation of lock gates,… $0
Supplemental Agreement for work within scope P00021 · Arra::yes::arra case NN064 coordination with quality assurance consultant, paid from funds allocated by modification P00020, chicago harbor lock gates… $0
Supplemental Agreement for work within scope P00021 · Case NN064 coordination with quality assurance consultant, paid from funds allocated by modification P00020, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00020 · Case NN063 authorization for construction services associated with electrical, mechanical, structural, concrete, guardrails, demolition, hauling, disposal,… $100,000
Supplemental Agreement for work within scope P00020 · Arra::yes::arra case NN063 authorization for construction services associated with electrical, mechanical, structural, concrete, guardrails, demolition,… $0
Supplemental Agreement for work within scope P00019 · Case NN045 add features to lock gate system - gate over travel monitoring and automatic reset; oil temperature and pressure monitoring; float switch monitoring;… $72,424
Supplemental Agreement for work within scope P00019 · Arra::yes::arra case NN045 add features to lock gate system - gate over travel monitoring and automatic reset; oil temperature and pressure monitoring; float… $13,360
Supplemental Agreement for work within scope P00018 · Case NN050 equitable adjustment for installation of feeder conduit to new commonwealth edison transformer, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00018 · Arra::yes::arra case NN050 equitable adjustment for installation of feeder conduit to new commonwealth edison transformer, chicago harbor lock gates replacement… $10,155
Supplemental Agreement for work within scope P00017 · Case NN059 confirmation of email notice to proceed for removal of rack shims on southwest and southeast gates, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00017 · Arra::yes::arra case NN059 confirmation of email notice to proceed for removal of rack shims on southwest and southeast gates, chicago harbor lock gates… $21,012
Supplemental Agreement for work within scope P00016 · Case NN058 equitable adjustment for costs to repair cracks of undetermined volume at west gate block, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00016 · Arra::yes::arra case NN058 equitable adjustment for costs to repair cracks of undetermined volume at west gate block, chicago harbor lock gates replacement… $21,779
Supplemental Agreement for work within scope P00015 · Arra::yes::arra case NN055 adjust bottom seals of all 4 sector gates and survey elevation and radius of all 4 gates, chicago harbor lock gates replacement… $38,158
Supplemental Agreement for work within scope P00015 · Case NN055 adjust bottom seals of all 4 sector gates and survey elevation and radius of all 4 gates, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00014 · Case NN049 implement allowance for expedited warranty response for nonstandard work hours, chicago harbor lock gates replacement project $0
Supplemental Agreement for work within scope P00014 · Arra::yes::arra case NN049 implement allowance for expedited warranty response for nonstandard work hours, chicago harbor lock gates replacement project $25,000
Supplemental Agreement for work within scope P00013 · Case NN040 infill with steel cover plates above existing cover plated wall embedment for new side seal angle; case NN041 install new 1" diameter raceway for… $0
Supplemental Agreement for work within scope P00013 · Arra::yes::arra case NN040 infill with steel cover plates above existing cover plated wall embedment for new side seal angle; case NN041 install new 1" diameter… $7,411
Supplemental Agreement for work within scope P00012 · Case NN030 place northwest gate control cabinet inside northwest gate control house and relocate electrical equipment as required; case NN036 modify operation… $0
Supplemental Agreement for work within scope P00012 · Arra::yes::arra case NN030 place northwest gate control cabinet inside northwest gate control house and relocate electrical equipment as required; case NN036… $102,698
Supplemental Agreement for work within scope P00011 · Case NN012 fabricate and install 1" stiffener plate; case NN027 delete requirement to plug weld and ground smooth abandoned holes; case NN037 set aside one of… $0
Supplemental Agreement for work within scope P00011 · Arra::yes::arra case NN012 fabricate and install 1" stiffener plate; case NN027 delete requirement to plug weld and ground smooth abandoned holes; case NN037… $5,052
Supplemental Agreement for work within scope P00010 · Arra::yes::arra case NN026 coordinate demolition of west-most section of 12" slab over former oinkage track cavity; case NN033 move 2 precast concrete panels… $10,376
Supplemental Agreement for work within scope P00010 · Case NN026 coordinate demolition of west-most section of 12" slab over former oinkage track cavity; case NN033 move 2 precast concrete panels from east BAY east… $0
Supplemental Agreement for work within scope P00009 · Case NN020 provide laboratory analysis confirming asbestos content of transite panels, remove and dispose of transite panels and provide soil analysis for… $0
Supplemental Agreement for work within scope P00009 · Arra::yes::arra case NN020 provide laboratory analysis confirming asbestos content of transite panels, remove and dispose of transite panels and provide soil… -$5,120
Supplemental Agreement for work within scope P00008 · Arra::yes::arra case NN016 cut 2 1" diameter drain holes through web of each horizontal P1 girder; case NN017 perform trial bulkhead installation and removal… $47,566
Supplemental Agreement for work within scope P00008 · Case NN016 cut 2 1" diameter drain holes through web of each horizontal P1 girder; case NN017 perform trial bulkhead installation and removal cycle; case… $0
Supplemental Agreement for work within scope P00007 · Arra::yes::arra case NN022 increase quantity on clin 0017 concrete spall repairs on vertical recess walls, west gate block, chicago harbor lock gates… $80,000
Supplemental Agreement for work within scope P00007 · Case NN022 increase quantity on clin 0017 concrete spall repairs on vertical recess walls, west gate block, chicago harbor lock gates replacement project $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $15,967,338.53 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to James McHugh Construction Co., a subsidiary of McHugh Enterprises, Inc. The contract is for the Chicago Harbor Lock Gates Replacement Project, which is part of the American Recovery and Reinvestment Act (ARRA) efforts. The contract has an ultimate completion date of September 30, 2013 and did not utilize a set-aside designation. The project involves the replacement of lock gates at the Chicago Harbor.

Quick answers

Who was awarded contract W912P609C0015?

W912P609C0015 was awarded to James Mchugh Construction Co by ENDIST Chicago (US Army Corps of Engineers) on July 15, 2009.

How much is contract W912P609C0015 worth?

The government has obligated $17,669,603 on W912P609C0015. Its current value, with exercised options, is $15,967,339.

Was contract W912P609C0015 competed?

The extent of competition for W912P609C0015 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award