Definitive Contract W912P522C0012

Award Date 9/29/22
Potential Completion Date 2/27/29
Potential Value $96M
Funding Federal Agency
US Army Corps of Engineers
Contracting Federal Agency
ENDIST Nashville
Ultimate Awardee
Not listed
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Lancaster, TN 38569, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
2
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a $49,293,483.27 definitive, firm-fixed-price contract awarded by the U.S. Army Corps of Engineers to Thalle Construction Co Inc. for the Center Hill Dam Auxiliary Dam Reinforcing Berm & Left Rim Stabilization project in Lancaster, Tennessee. The contract does not have a set-aside designation. Thalle Construction Co Inc. is a for-profit construction company specializing in large-scale infrastructure projects for federal agencies, particularly the U.S. Army Corps of Engineers. The...
This $1,202,525.47 firm fixed-price delivery order contract was awarded by the U.S. Army Corps of Engineers (USACE) to Stantec Consulting Services Inc., a subsidiary of Stantec Incorporated, for the FY16 Center Hill Dam Safety Instrumentation Installation project. The contract does not have a set-aside designation. Stantec is a global design and consulting firm that provides a wide range of services to the U.S. federal government, particularly the USACE, including engineering, architecture,...
The Department of the Army Corps of Engineers, Nashville District awarded a $891,000 firm fixed price contract to Grace Contracting LLC. The contract calls for electrical rework services at the Center Hill RCC dam near Lancaster, Tennessee. Specifically, the work includes relocating existing electrical equipment from inside the RCC dam to a new above-ground building, which will be provided as part of the contract. The solicitation sought these electrical rework services to improve conditions...
This $3,470,686.00 firm fixed price contract was awarded by the U.S. Army Corps of Engineers to Precision Build Solutions LLC, doing business as Tampa Tank, for the fabrication and delivery of Stennis Spillway Gate #2 for the John C. Stennis Lock and Dam on the Tennessee-Tombigbee Waterway near Columbus, Mississippi. The new 60-foot wide, 29-foot tall, 180,000-pound gate is to be delivered via barge by July 2025. The contract also includes an option to repair the existing Spillway Gate #3....
This is a firm fixed-price delivery order awarded by the U.S. Army Corps of Engineers (USACE) to Shimmick Construction Company, Inc., a subsidiary of AECOM, for the Dale Hollow Dam Spillway Gate Recoating and Machinery Control Rehabilitation project. The contract has a ceiling value of $9,501,685.72 and a period of performance through March 8, 2025. The contract was issued under the USACE LRD (Louisville District) Regional Construction multiple-award Indefinite Delivery/Indefinite Quantity...
The U.S. Army Corps of Engineers (USACE), Nashville District awarded a $908,876.73 firm-fixed-price definitive contract to TEM Group Inc., a minority-owned, self-certified small disadvantaged business, to provide construction services to replace the control cables at the Center Hill Power Plant in Lancaster, Tennessee. This contract was funded under the American Recovery and Reinvestment Act (ARRA) and has an ultimate completion date of February 16, 2011. The contract was awarded on a...
This is a firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to BCI Construction USA Inc., a Veteran-Owned and Service-Disabled Veteran-Owned Small Business, to provide brakes, gearmotors, shafts, and coupling. The contract has a potential value of $6,700,644.70 and a completion date of February 18, 2022. The place of performance is located in Lancaster, Tennessee. BCI Construction USA Inc. has been awarded over $130 million in federal contracts since 2019 to...
This is a $6,754,577 definitive contract awarded by the U.S. Army Corps of Engineers to Advanced American Construction, Inc., a small disadvantaged business based in Portland, Oregon. The contract is for structural work on Tainter Gate 2, with a completion date of May 1, 2025. The contract was set aside for total small business participation. This award is part of a larger multiple-award task order contract (MATOC) with a $99.9 million ceiling value that Advanced American Construction holds with...
This is a $499,652.52 firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) to Ilsi-Arcadis Small Business Joint Venture LLC, a minority-owned, woman-owned, and economically disadvantaged small business joint venture. The contract is for the replacement of dam gates at the Jim Woodruff Lock and Dam on the Chattahoochee River in Chattahoochee, Florida. The work is scheduled for completion by December 16, 2025. Ilsi-Arcadis Small Business Joint Venture LLC...
This is a $6,727,870.82 definitive firm fixed price contract awarded by the U.S. Army Corps of Engineers to BCI Construction USA Inc., a Service Disabled Veteran Owned Small Business, for the rehabilitation of the Howard A. Hanson Dam Emergency Closure System in Ravensdale, WA. This contract was set aside for total small business and originated from a sources sought notice for the removal and replacement of the dam's existing emergency gate and hoist system, as well as cleaning of trash racks...

This is a firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to American Bridge Company, a self-certified small disadvantaged business, for the CENTER HILL DAM SPILLWAY GATES & MACHINERY REPLACEMENT PROJECT in Lancaster, TN. The $96,401,244.34 contract is for the fabrication and installation of 8 new spillway tainter gates, removal of existing gates, and replacement of the gate lifting machinery equipment at the Center Hill Dam facility. This project was not set aside and was awarded on September 29, 2022 with a completion date of February 27, 2029. The original contract opportunity was posted in August 2021 as a sources sought notice to determine contractor capability for this $100-250 million project.

Generated 5/16/25, 11:55 AM