Port isabel detention center (pidc) kitchen facility and waste water treatment plant renovations

Ended Definitive Contract Awarded Last action

Contract number
W912HY19C0024
Awardee
Awarding agency
Obligated
$10,282,501

Award facts

Opportunity
Contract value 100% obligated
$10,282,500.97 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Port Isabel, TX, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00008 · Kitchen facility REA $565,000
Change Order P00006 · Administrative MOD $164,520
Change Order A00040 · Time extension $0
Vendor DUNS or Name Change - Non-Novation P00005 · Kitchen facility $0
Change Order A00039 · REA 018 $35,556
Change Order A00038 · REA 1,5,6,7 $70,864
Change Order A00037 · Misc. Changes_definitization $17,090
Change Order A00036 · Kitchen facility and wwtp misc changes - life safety and security $57,481
Change Order A00035 · Correction to NTP $0
Vendor DUNS or Name Change - Non-Novation P00004 · Kitchen facility surety takeover agreement -$128,874
Change Order A00034 · Shunt trip deficiency $0
Change Order A00032 · Nfpa 820 changes wwtp_definitization -$3,442
Change Order A00031 · Wwtp nfpa 820 electrical changes $100,000
Change Order A00030 · Polymer, pump elect, exit, alarm lights $26,775
Change Order A00029 · Time for concurrent delay and LD deoblig -$164,520
Change Order A00028 · Credit for demo of pump station #1 -$7,517
Change Order A00027 · Kitchen facility - definitization of MOD A00025 (NVR and l:ight fixtures) $7,179
Change Order A00026 · April 2021 to september 2021 weather MOD extend the period of performance by three (3) calendar days due to the adverse weather experienced since april 2021… $0
Change Order A00025 · NTE MOD_NVR delta, d-switches, & lights $12,667
Change Order A00020 · New driveway & detention pond revisions $20,678
Change Order A00022 · Water heater vent & HVAC return $9,092
Change Order A00024 · Kitchen facility bollards $20,913
Change Order A00023 · Kitchen facility MOD for trash compactor power $19,136
Change Order A00021 · Drip pan and VAV boxes electrical power $22,945
Change Order A00019 · Grease trap slab & housekeeping pads $9,001
Change Order A00018 · Kitchen facility - note effective date is actually 28 june 2021, SPS system does not allow completion date to be changed prior to an effective date $35,568
Change Order A00016 · Link corridor new door to exist kitchen $14,973
Change Order A00017 · 3" gas line connection & SS base -$5,139
Change Order A00015 · ESS security door hardware $43,053
Change Order A00014 · Contract plans_18 non-compensable days $0
Change Order A00013 · ACP removal wwtp_NTE MOD definitization -$7,500
Change Order A00012 · December 2019 to march 2021 weather MOD $0
Change Order A00011 · Link corridor, kitchen drains & HW rebar $110,290
Other Administrative Action P00003 · Contractor name change to triun, LLC $0
Change Order A00010 · Wwtp electrical building & hardware $68,000
Change Order A00009 · ACP removal wwtp $30,000
Change Order A00008 · Underground electrical relocation_DSC $53,449
Other Administrative Action P00002 · Kitchen facility administrative funding MOD $0
Change Order A00007 · Kitchen facility concrete pad $8,570
Change Order A00006 · Covid-19 time extension - 9 days $0
Change Order A00005 · Kitchen facility $106,644
Change Order A00004 · Access to grease trap $9,918
Change Order A00003 · Kitchen facility - asbestos pipe removal NTE $20,000 $20,000
Change Order A00002 · Asbestos-containing material testing $1,434
Change Order P00001 · Kitchen equipment REA $1,103,277
Change Order A00001 · Kitchen facility equipment $140,419
Original award $7,695,000
Show all 47

About this award

Harco National Insurance Company was awarded a firm fixed-price definitive contract on September 26, 2019, valued at $10.28 million for kitchen facility and wastewater treatment plant renovations at Port Isabel Detention Center (PIDC) in Port Isabel, Texas. The contract was funded by the Defense Counterintelligence and Security Agency (formerly known as ENDIST Galveston) and carries an ultimate completion date of August 19, 2025. The solicitation was posted on July 10, 2019, with a deadline of September 9, 2019, and no set-aside designation was used for this competitive procurement.

The project encompasses renovation and rehabilitation work on critical infrastructure systems at the detention facility, specifically focusing on the kitchen operations and wastewater treatment capabilities. As a definitive contract with firm fixed-price terms, Harco National Insurance Company assumes responsibility for delivering the specified renovations within the established budget and timeline, with pricing established at contract award and no provision for adjustment based on cost changes.

Quick answers

Who was awarded contract W912HY19C0024?

W912HY19C0024 was awarded to Harco National Insurance Company by ENDIST Galveston (US Army Corps of Engineers) on September 26, 2019.

How much is contract W912HY19C0024 worth?

The government has obligated $10,282,501 on W912HY19C0024.

Was contract W912HY19C0024 competed?

The extent of competition for W912HY19C0024 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award