$39,097,500.00 $2,850,000.00

Ended Definitive Contract Awarded Last action

Contract number
W912HY10C0004
Awardee
Awarding agency
Obligated
$66,340,555

Award facts

Opportunity
Contract value 271% obligated
$24,451,554.90 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Texas City, TX 77590, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00013 · Contract for recovery, design build project for texas city channel, TX. Reference no. R00012 NG012 overrun claim resolution $0
Supplemental Agreement for work within scope P00013 · Design build project for texas city channel, TX. Reference no. R00012 NG012 overrun claim resolution $200,000
Supplemental Agreement for work within scope P00012 · Arra::yes::arra recovery project:: no cost MOD to reduce the levee elevation. $0
Supplemental Agreement for work within scope P00012 · No cost MOD to reduce levee elevation. $0
Change Order P00011 · Arra funds 96X3134 reference no. R00010 NG010 final quantities -- clins 0002 & 0003 $0
Change Order P00011 · Fcce funds 96X3125 reference no. R00010 NG010 final quantities -- clins 0002 & 0003 -$100,423
Other Administrative Action P00010 · Arra::yes::arra recovery project:: design build project for texas city channel, TX. Admin MOD to correct the funding on subclin 0010AC. $0
Other Administrative Action P00010 · Admin MOD to correct the funding on subclin 0010AC in SPS. $400,000
Change Order P00009 · 96 X 3122 and contributed funds 96 X 8862 contract for recovery, design build project for texas city channel, TX. Reference no. R00008 NG008 design interior… $8,978
Change Order P00009 · Arra funds 96X3134 contract for recovery, design build project for texas city channel, TX. Reference no. R00008 NG008 design interior breakwater -- sppa 3,4,5 $0
Change Order P00007 · Contract for recovery, design build project for texas city channel, TX. Reference no. R00007 NG007 design change -- weirs -$19,500
Change Order P00007 · Recovery arracontract for design build project for texas city channel, TX. Reference no. R00007 NG007 design change -- weirs -$58,500
Supplemental Agreement for work within scope P00006 · Arra funds 96X3134 contract for recovery, design build project for texas city channel, TX. Reference no. R00006 NG006 extension to contract POP -- levee $0
Supplemental Agreement for work within scope P00006 · Contributed funds 96X8862 contract for recovery, design build project for texas city channel, TX. Reference no. R00006 NG006 extension to contract POP -- levee $0
Supplemental Agreement for work within scope P00005 · Arra funds 96X3134 contract for recovery, design build project for texas city channel, TX. Reference no. R00005 NG005 adverse weather delays $0
Supplemental Agreement for work within scope P00005 · Contributed funds 96X8862 contract for recovery, design build project for texas city channel, TX. Reference no. R00005 NG005 adverse weather delays $0
Supplemental Agreement for work within scope P00004 · Modification P00004 - ALT. Borrow source-shoal point. $0
Supplemental Agreement for work within scope P00004 · Modification P00004 - ALT. Borrow source at shoal point. $3,612,568
Change Order P00003 · Modification P00003 for alternate borrow source - shoal point $0
Change Order P00003 · Modification P00003, alternate borrow source - shoal point $887,432
Other Administrative Action P00002 · Contributed funds 96X8862 $0
Other Administrative Action P00002 · Administrative MOD to release contractor to work on gulf oil spill at no additional cost to the government. $0
Other Administrative Action P00001 · Contributed funds 96X8862 - recovery, design-build project for texas city channel, texas. $0
Other Administrative Action P00001 · Arra 96X3134, recovery, design-build project for texas city channel, texas. $0
Modification Texas city design build, texas channel $19,462,500
Original award $41,947,500
Show all 26

About this award

This federal contract award was issued by the U.S. Army Corps of Engineers to the prime contractor Weeks Marine, Inc., a major marine construction and dredging company. The contract, valued at $41,947,500.00, is for dredging and coastal protection services, with a completion date of April 9, 2012. The contract is a definitive, firm-fixed-price agreement and was not set aside for any small business designation.

Weeks Marine, a subsidiary of Peter Kiewit Sons Inc., is an experienced provider of dredging, beach nourishment, and coastal infrastructure services to various government agencies, particularly the U.S. Army Corps of Engineers. The company holds several Indefinite Delivery/Indefinite Quantity (IDIQ) contracts with the Corps, allowing for streamlined task order awards to address ongoing navigation, dredging, and coastal protection needs across multiple regions.

Quick answers

Who was awarded contract W912HY10C0004?

W912HY10C0004 was awarded to Weeks Marine, Inc. by ENDIST Galveston (US Army Corps of Engineers) on October 26, 2009.

How much is contract W912HY10C0004 worth?

The government has obligated $66,340,555 on W912HY10C0004. Its current value, with exercised options, is $24,451,555.

Was contract W912HY10C0004 competed?

The extent of competition for W912HY10C0004 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award