Construct new SOF maintenance hangar

Active Definitive Contract Awarded Last action

Contract number
W912HV25C0003
Awardee
Awarding agency
Obligated
$61,197,993

Award facts

Opportunity
Contract value 100% obligated
$61,197,992.92 Current and potential, with all options
Completion date 67% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Japan
Defense program
Status of Forces Agreement

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00005 $0
Supplemental Agreement for work within scope P00004 · Various engineering changes covering- item 1. Fire pump house redesign, item 2. Change transformer ductbank size, item 3. Remove OH coiling door no.115B, item… $352,390
Supplemental Agreement for work within scope A00004 · OT005 - add spec section 07 81 00 $0
Supplemental Agreement for work within scope A00003 $105,084
Supplemental Agreement for work within scope A00002 · A.&*@~scope of work $0
Supplemental Agreement for work within scope A00001 · OT001 - remove various unforeseen mat contract for AFSOC103021 SOF maintenance hangar and LXEZ153953 SOF composite maintenance facility, kadena air base at… $25,725
Other Administrative Action P00003 · Implement executive order 14173 and class deviation 2025-O0003 and execute order 14148 and class deviation 2025-O00004. $0
Other Administrative Action P00002 · Establish the official contract completion date based on contractors acknowledgment of the notice to proceed on 11 april 2025 $0
Supplemental Agreement for work within scope P00001 · Construct new SOF maintenance hangar - update submittal register. $0
Original award $60,714,794

About this award

ENDIST Japan, the U.S. Army Corps of Engineers Engineering District Japan, awarded a $61.2 million firm-fixed-price definitive contract to Exeo-Nakamoto Kogyo JV on March 14, 2025, to construct a new Air Force Special Operations Command maintenance hangar at Kadena Air Base, Okinawa, Japan. No set-aside was used. The award is a Defense-side transaction and the source lists an ultimate completion date of October 1, 2027.

The award scope includes engineering changes to the hangar project: a fire pump house redesign, a transformer ductbank size change, removal of overhead coiling door No. 115B, and additional bollards for fire hydrants. The originating pre-solicitation, posted November 1, 2023, sought design-bid-build construction of the hangar (approximately 150,000 square feet) and a composite maintenance facility (approximately 50,000 square feet), with an estimated 588-day period of performance. Respondents were required to be physically located and licensed to conduct business in Japan. The procurement is coded NAICS 236220 (commercial and institutional building construction) and PSC Y1BZ (construction of other airfield structures).

Quick answers

Who was awarded contract W912HV25C0003?

W912HV25C0003 was awarded to Exeo-Nakamoto Kogyo JV by ENDIST Japan (US Army Corps of Engineers) on March 14, 2025.

How much is contract W912HV25C0003 worth?

The government has obligated $61,197,993 on W912HV25C0003. Its current value, with exercised options, is $61,197,993.

Was contract W912HV25C0003 competed?

The extent of competition for W912HV25C0003 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award