Construction SOF battalion HQ

Ended Definitive Contract Awarded Last action

Contract number
W912HN23C3001
Awardee
Awarding agency
Obligated
$71,317,867

Award facts

Opportunity
Contract value 99% obligated
  • $71,433,764.00 Current, with exercised options
  • $71,699,764.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Fort Benning, GA 31905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00023 · BA027 settlement of reas 6-11 and 13 contract for SOF battalion headquarters at fort benning, GA $208,394
Supplemental Agreement for work within scope A00022 · BA026/R000223 $136,899
Supplemental Agreement for work within scope A00021 · BA024/R00022 $73,718
Supplemental Agreement for work within scope A00020 · BA023/R00021 modify windows in guard duty room 117 $5,089
Supplemental Agreement for work within scope A00019 · Base-construction BA022 / R00020 telecom racks, ACC panels, & vestibule $103,364
Supplemental Agreement for work within scope A00018 · Base-construction BA021 / R00019 modify RM 141 cond water expansion joint $16,882
Supplemental Agreement for work within scope A00017 · Base-construction BA018 / R00018 reroute the fiber and copper $278,929
Supplemental Agreement for work within scope A00016 · Base-construction BA017 / R00017 add safety railing above retaining walls $74,599
Supplemental Agreement for work within scope A00015 · Base-construction BA020 / R00016 modify door 142D hardware $11,764
Supplemental Agreement for work within scope A00014 · Base-construction BA019 / R00015 modify exhaust grilles & return duct $46,218
Supplemental Agreement for work within scope A00013 · Base-construction BA015 / R00014 modify VTC room 230 $322,732
Supplemental Agreement for work within scope A00012 · Base-construction BA016/ R00013 modify IDS jiant TR rooms $155,910
Funding Only Action P00004 · Base-construction $2,095,937
Supplemental Agreement for work within scope A00011 · BA003/R00011 IDS changes $102,903
Supplemental Agreement for work within scope A00010 · R00010/BA012 modify door hardware $28,687
Supplemental Agreement for work within scope A00007 · R00007-BA009 additional electrical and telecom $47,252
Supplemental Agreement for work within scope A00009 · R00009/BA011 brick ledge infill and bent plates $46,704
Supplemental Agreement for work within scope A00008 · R00008/BA010 additional drainage structure $10,937
Supplemental Agreement for work within scope A00005 · BA006/R00006 increase girts, add tube steel and channels $457,930
Supplemental Agreement for work within scope A00006 · BA004/R00004 remove abandoned sewer $19,982
Supplemental Agreement for work within scope A00004 · BA005/R00005 additional weapons lockers $58,215
Supplemental Agreement for work within scope A00003 · BA007/R00003 wage determination REA-1, NTP through 31JAN2024. $458,961
Exercise an Option P00003 · Base-construction $2,318,000
Supplemental Agreement for work within scope A00002 · BA002/R00002 CW pump, wahp, plumbing fixture, elev TW $35,268
Other Administrative Action P00002 · Base-construction $0
Supplemental Agreement for work within scope A00001 · R0001/BA001 relocate mock-UPS $307,593
Other Administrative Action P00001 · Base-construction $0
Original award $63,895,000
Show all 28

About this award

The Defense agency ENDIST Savannah awarded a firm fixed price definitive contract with a $71.6 million ceiling value to Sauer Construction, LLC on December 15, 2022, for construction of a SOF battalion headquarters at Fort Benning, Georgia, with no set-aside used. The award description also references settlement of requests for equitable adjustment (REAs) 6 through 11 and 13 under the same contract. The ultimate completion date is March 31, 2026. Sauer Construction carries no SBA set-aside designations.

The originating pre-solicitation notice, posted June 25, 2021 with responses due July 23, 2021, was issued by the Savannah District, U.S. Army Corps of Engineers, and sought contractors to build a new 92,000 square foot battalion headquarters at Fort Benning, including 27,000 square feet of Sensitive Compartmented Information Facility (SCIF) space. Respondents were to address their capability statement and experience in military construction and secure information facilities. Subcontracting plans were required where more than 60% of work would go to subcontractors. The notice carried NAICS 236220, Construction of Commercial and Institutional Buildings, with a $39.5 million size standard and an estimated value between $25 million and $100 million. Place of performance is Fort Benning, GA 31905, USA.

Quick answers

Who was awarded contract W912HN23C3001?

W912HN23C3001 was awarded to Sauer Construction, LLC by ENDIST Savannah (US Army Corps of Engineers) on December 15, 2022.

How much is contract W912HN23C3001 worth?

The government has obligated $71,317,867 on W912HN23C3001. Its current value, with exercised options, is $71,433,764. Its potential value, with all options, is $71,699,764.

Was contract W912HN23C3001 competed?

The extent of competition for W912HN23C3001 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award