Repair section c

Ended Definitive Contract Awarded Last action

Contract number
W912HN21C3007
Awardee
Awarding agency
Obligated
$30,854,821

Award facts

Opportunity
Contract value 100% obligated
$30,854,821.28 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Fort Benning, GA 31905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00003 $0
Supplemental Agreement for work within scope A00010 · Repair section c BA010 / R00010 REA#2 sections b & c-modify storefronts $35,131
Supplemental Agreement for work within scope A00009 · Repair section c BA009 / R00009 sections b & c - misc. Elect $25,294
Supplemental Agreement for work within scope A00007 · Repair section c BA008 / R00008 section b - fill void under column $5,393
Supplemental Agreement for work within scope A00008 · Repair section c BA007 / R00007 sect b & c -B109 and C113 DHW tank issue $19,191
Supplemental Agreement for work within scope A00006 · BA006, R00006, sections b & c - openings, infills $94,510
Supplemental Agreement for work within scope A00005 · BA005/R00005 section b & c steel, drywall, track, p & s $6,612
Supplemental Agreement for work within scope A00003 · BA003/R00003 sections b & c-paint, asbestos, drains $29,778
Supplemental Agreement for work within scope A00004 · R00004/BA004 sections b & c-lights, doors, security $22,701
Supplemental Agreement for work within scope A00002 · Repair section b & c R00002/BA002 closed circuit coolers $148,303
Supplemental Agreement for work within scope A00001 · R00001 BA001 additional lead abatement $495,660
Other Administrative Action P00002 $0
Other Administrative Action P00001 · This is an admin MOD to clarify sections $0
Original award $29,972,248
Show all 14

About this award

Sand Point Services, LLC (doing business as TDX Holdings, LLC), an Alaska Native Corporation, was awarded a $30.85M firm fixed-price definitive contract on September 23, 2021, by the Army Corps of Engineers Engineering District Savannah to perform repairs to Building 399 at Fort Moore, Georgia. The contract, which was completed by September 5, 2023, encompassed comprehensive renovation of failed and failing building systems including exterior walls, windows, fire protection systems, interior walls, doors, floors, ceilings, plumbing, HVAC, electrical systems, and communications infrastructure. The solicitation was issued on a competitive basis using sealed bidding procedures with no set-aside designation, and the estimated project magnitude ranged from $25M to $100M with a 540-calendar-day completion timeline.

Sand Point Services executed this substantial repair project through a strategic network of specialized subcontractors, including JNB Services LLC for metal stud framing, drywall, insulation, and door installation; Bonitz Inc. for flooring installation; Wrightway Painting for interior and exterior painting and epoxy flooring; 1 Priority Environmental Services for demolition and abatement; and Columbus Automatic Sprinklers for fire suppression systems. Additional subcontractors provided mechanical, electrical, and plumbing services (Andrews, Hammock, & Powell, Inc.; Booth Plumbing Co., Inc.; Bay To Bay Balancing, Inc.; Metropower Inc.; and Flow-Pro, LLC), along with specialized trades including window and glazing installation, HVAC testing and balancing, electrical and fire alarm work, concrete and site work, and window treatments. This comprehensive subcontractor base enabled Sand Point Services to deliver the full scope of building system repairs and renovations required at the military installation.

Subawards

Subcontractor Amount Awarded
Auman Brothers, Inc. REPAIR SECTION C Supply & install bathroom shelving $96,154
Huckaby Brothers Floor Covering Inc. REPAIR SECTION C supply and install flooring $358,547
Subcontractor not on record REPAIR SECTION C Saw cutting $150,800
Subcontractor not on record REPAIR SECTION C install tile flooring $793,643
The Collins Legacy Corp REPAIR SECTION C Painting $1,830,060
Hard Rock Concrete, LLC REPAIR SECTION C Concrete work $53,615
Chaparral Mechanical Insulation Co., Inc. REPAIR SECTION C Firestopping supply/install $143,237
Subcontractor not on record REPAIR SECTION C Drywall installation $4,194,020
Subcontractor not on record REPAIR SECTION C Masonry $554,250
Blinds And Beyond Of NC, Inc. REPAIR SECTION C Supply & install blinds $151,180
Bonitz Inc. REPAIR SECTION C Install all Luxury Vinyl Tile, Resilient Base, Ceramic, Quarry, and Glass Tiling, Resilient Flooring, Porcelain Floor & Wall Tiling, Mud Bed… $1,734,424
Subcontractor not on record REPAIR SECTION C Install all Structural & Misc. Steel $102,935
Booth Plumbing Co, Inc. REPAIR SECTION C HVAC Mechanical Systems and Controls $5,746,447
Muscogee Autoglass, Inc. REPAIR SECTION C Aluminum Windows, Storefronts and Glazing $1,920,888
Flow-Pro, LLC REPAIR SECTION C Plumbing work $2,464,005
Metropower, Inc. REPAIR SECTION C Electrical and Fire Alarm $5,385,236
Warr Grading Contractor, Inc. REPAIR SECTION C Erosion Control, Demolition, Grading, Concrete, Curbs, Asphalt Paving & Base, Grassing $259,523
Columbus Automatic Sprinklers, Inc. REPAIR SECTION C Fire sprinkler systems $447,925
Show all 18

Quick answers

Who was awarded contract W912HN21C3007?

W912HN21C3007 was awarded to Sand Point Services, LLC by ENDIST Savannah (US Army Corps of Engineers) on September 23, 2021.

How much is contract W912HN21C3007 worth?

The government has obligated $30,854,821 on W912HN21C3007.

Was contract W912HN21C3007 competed?

The extent of competition for W912HN21C3007 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award