PN 88724 SCI training, research & network center, fort gordon, georgia

Ended Definitive Contract Awarded Last action

Contract number
W912HN20C3006
Awardee
Awarding agency
Obligated
$99,719,007

Award facts

Opportunity
Contract value 97% obligated
$102,632,205.60 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Gordon, GA 30905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00052 · MCA1 - SCI training, research network center at fort gordon, GA GC074 REA - curtain wall delays $76,258
Supplemental Agreement for work within scope A00051 $274,863
Supplemental Agreement for work within scope A00050 · MCA1 - SCI training, research network center at fort gordon, GA $0
Supplemental Agreement for work within scope A00049 · Primary facility construction MCA1 GC072 move stairwell thermostats for fcus added cost and time, $8,687.63, 2 calendar days. $0
Supplemental Agreement for work within scope A00048 · Primary facility construction MCA1 modification for GC071 delete lights in labs 443 & 446 deleted cost -$5,437.00, no time $0
Supplemental Agreement for work within scope A00047 · Primary facility construction MCA1 modification for GC070 GC060 follow-up, added cost $68,308.00, no time, additionally, a correction for A00019 move funds from… $68,308
Change Order A00046 · Primary facility construction MCA1 modification for GC068 add film for command suite & exit signs added cost $7,389.00, added time 4 calendar days $0
Change Order A00044 · Primary facility construction modification for GC060 descope irrigation, a credit of $55,780.00. Unilateral. -$55,780
Supplemental Agreement for work within scope A00043 · Primary facility construction MCA1 modification for GC067 door fire rating, added cost $2,663.00 added time 1 calendar day $0
Supplemental Agreement for work within scope A00042 · Primary facility construction modification for MCA1 GC065 hurricane helene excusable delay no cost, added time 19 calendar days. $0
Supplemental Agreement for work within scope A00041 · Primary facility construction MCA1 GC063 floor stops for doors added cost $379.00, 1 calendar day. $0
Supplemental Agreement for work within scope A00040 · Primary facility construction MCA1 modification for GC062 add RF media converters and wave guides added cost $6,799.00 and time 13 calendar days. $0
Change Order A00038 · Primary facility construction MCA1 modification for GC061 elevator lights & power for damper R00044 A0040, added cost $5,914.00, added time 3 calendar days,… $0
Change Order A00037 · Primary facility construction MCA1 modification for GC059 miscellaneous architectural changes added cost $6,008.00, added time $3 non-compensable calendar days $6,008
Change Order A00036 · Primary facility construction MCA1 unilateral modification for GC056 misc. Changes added cost $33,387.64 added time 9 calendar days. $0
Supplemental Agreement for work within scope A00035 · Primary facility construction MCA1 telecommunications pathway corrections added cost $9,280.00, one calendar day, unilateral $9,280
Supplemental Agreement for work within scope A00034 · Primary facility construction MCA1 modification for GC052 delete requirement for keyed connectors no time or cost $0
Supplemental Agreement for work within scope A00033 · Primary facility construction MCA1 GC051 remove bollard on hthw lid added cost $10,762.00 no time $10,762
Supplemental Agreement for work within scope A00032 · Primary facility construction MCA1 GC054 secure perimeter changes 2 added cost $93,066.00 and time 41 calendar days. Unilateral. $0
Supplemental Agreement for work within scope A00031 · Primary facility construction MCA1 MOD for GC049 chilled beam/lighting conflict added cost $9,381.93, no time. $0
Supplemental Agreement for work within scope A00030 · Primary facility construction modification for MCA1 GC055 weather july-SEP 2023, add two days $0
Supplemental Agreement for work within scope A00029 · Primary facility construction modification for MCA1 GC048 secure perimeter changes added cost $123,222.00 no time. $0
Supplemental Agreement for work within scope A00028 · Primary facility construction modification for MCA1 GC046 dock station changes & relocate bollards added cost no time, $22,161.00. $22,161
Supplemental Agreement for work within scope A00027 · Primary facility construction modification for MCA1 GC045 relocate humidifier & elevator ctrl panel added cost no time, $40,260.00 $0
Change Order P00010 · Primary facility construction $456,914
Supplemental Agreement for work within scope A00026 · Primary facility construction MCA1 modification for GC042 move exterior lights and power for pumps, added cost $21,637.00, no time. $0
Change Order A00025 · Primary facility construction MCA1 modification GC041 delete insulation from exterior walls, credit -$77,259.00. $0
Supplemental Agreement for work within scope A00024 · Primary facility construction modification for MCA1 REA - chilled water strike added cost $71,564.00, no time $71,564
Supplemental Agreement for work within scope A00023 · Primary facility construction modification for MCA1 GC038 REA curtainwall supply chain delay no cost, added time 67 calendar days. $0
Supplemental Agreement for work within scope A00022 · Primary facility construction MCA1 modification for GC040 door hardware conflicts added cost $48,361.00, no time. $0
Supplemental Agreement for work within scope A00021 · Primary facility construction MCA1 modification for GC039 misc. Wall changes R00027 A00023, added cost $47,641.00, no time $0
Supplemental Agreement for work within scope A00020 · Primary facility construction MCA1 modification for GC032 correct roof drains at slab on grade added cost $99,600.00 no time. $0
Supplemental Agreement for work within scope A00019 · Primary facility construction modification for MCA1 GC033 add QEI acceptance testing, insp. CX added cost $10,250.00, no time. $0
Supplemental Agreement for work within scope A00018 · Primary facility construction weather time extension JAN 22 - JUN 22 added 5 calendar days no cost. $0
Supplemental Agreement for work within scope A00017 · Primary facility construction modification for MCA1 GC028 misc. Electrical changes added cost no time $0
Supplemental Agreement for work within scope A00016 · Primary facility construction GC027 covid-19 delays through 12JAN22 (unilateral) R00021 A00018 no cost added time 8 calendar days $0
Supplemental Agreement for work within scope A00015 · Primary facility construction modification for MCA1 GC017 provide RM621 walls, lights, finishes R00020 added cost $46,407.00 on clin 0001 an adjustment of… -$72
Supplemental Agreement for work within scope A00014 · Primary facility construction MCA1 modification for GC026 USACE office trailer upgrades R00019 added cost $25,627.00, and no time. $25,627
Supplemental Agreement for work within scope A00013 · Primary facility construction modification for GC025 partnering laydown yard no cost no time. MCA1 $0
Supplemental Agreement for work within scope A00012 · Primary facility construction modification for MCA1 GC021 comms duct bank conflict reduced cost -$60,180.00, no time -$60,108
Supplemental Agreement for work within scope A00011 · Primary facility construction modification for GC023 connect saltzman hall roof drain added cost $29,786.00, no time $29,786
Supplemental Agreement for work within scope A00010 · Primary facility construction modification for GC020 bathroom accessory changes added cost $9,099.00 no time. MCA1 $0
Supplemental Agreement for work within scope A00009 · Primary facility construction modification for GC009 elevator and leed V4.1 spec change no cost no time MCA1 $0
Supplemental Agreement for work within scope A00008 · GC019 west hot water tie-INS added cost $6,307.00, no time for MCA1 $6,307
Other Administrative Action P00008 $0
Change Order P00007 · Primary facility construction $870,762
Supplemental Agreement for work within scope P00006 · Primary facility construction modification for GC006 arch. Electrical panel conflict added cost $7,000.00 and no time. $0
Supplemental Agreement for work within scope P00005 · Primary facility construction unilateral GC016 hot water vault changes added cost $35,846.00 no time, $0
Supplemental Agreement for work within scope A00007 · Primary facility construction modification for GC004 georgia power revised scope added cost $135,266.00 and add time 43 calendar days. $0
Supplemental Agreement for work within scope A00006 · Primary facility construction modification for GC005 R00010 revised storm drain and detention pond credit for -$24,109.00 no time $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Department of the Army Corps of Engineers awarded a $102.6 million definitive firm fixed price contract to Gilbane Federal for construction of a Sensitive Compartmented Information Training, Research & Network Center at Fort Gordon, Georgia on June 19, 2020.

The project entails construction of a Top Secret/Sensitive Compartmented Information facility housing an Automation-Aided Instructional area with classrooms, labs, offices and break areas, a Mission Command Facility, and General Purpose Administrative space. Place of performance is Fort Gordon, GA 30905. The ultimate completion date is December 14, 2023.

NAICS code 236220 (Commercial and Institutional Building Construction) applies. RML Acoustics LLC performed National INFOSEC Implementation Capability and Organizational INFOSEC Implementation Capability testing work as a subcontractor, with the sub-award dated April 30, 2025.

Subawards

Subcontractor Amount Awarded
RML Acoustics LLC PN 88724 SCI TRAINING, RESEARCH&NETWORK CENTER, FORT GORDON, GEORGIA NIC and OINIC testing. $35,000

Quick answers

Who was awarded contract W912HN20C3006?

W912HN20C3006 was awarded to Gilbane Federal by ENDIST Savannah (US Army Corps of Engineers) on June 19, 2020.

How much is contract W912HN20C3006 worth?

The government has obligated $99,719,007 on W912HN20C3006. Its current value, with exercised options, is $102,632,206.

Was contract W912HN20C3006 competed?

The extent of competition for W912HN20C3006 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award