Construct arcyber COF, fort gordon, GA

Ended Definitive Contract Awarded Last action

Contract number
W912HN19C3000
Awardee
Awarding agency
Obligated
$14,768,955

Award facts

Opportunity
Contract value 90% obligated
  • $14,768,954.64 Current, with exercised options
  • $16,460,184.80 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 8 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Fort Gordon, GA 30905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00006 · Warranty enforcement $0
Supplemental Agreement for work within scope A00018 · Funding for clin 0001 arcyber COF unilateral modification for GC030 tab & commissioning delays no cost 116 non-compensable calendar days $0
Supplemental Agreement for work within scope P00005 · Funding for clin 0001AB modification for GC028 unit heater vestibule add cost $6,266.63 and time 12 calendar days $6,267
Supplemental Agreement for work within scope A00017 · Funding for clin 0002A modification for GC023 concrete flume added cost $138,304.00 added time 45 calendar days $138,304
Supplemental Agreement for work within scope A00016 · Funding for clin 0002 for modification GC021 add fire hydrant arcyber COF added cost $175,851.00 and no time. $175,851
Supplemental Agreement for work within scope P00004 · Funding for clin 0001AB modification for GC025 upgrade forklift charging station power added cost $15,027.68 and time 14 calendar days. $15,028
Supplemental Agreement for work within scope P00003 · Funding for clin 0001AB modification for GC026 add bollards to protect HVAC equipment added cost $5,081.00 and time 14 calendar days. $5,081
Supplemental Agreement for work within scope P00002 · Funding for clin 0001AB modification for GC027 install lintels in hallway shear walls added cost $11,015.00 added time 14 days. $11,015
Supplemental Agreement for work within scope A00015 · Funding for clin 0001AB modification for GC024 revise ceiling grid added cost $12,245.48 and added time 60 calendar days. $12,245
Supplemental Agreement for work within scope A00014 · Funding for clin 0001AB modification for GC029 delete AWP1 deobligated cost -$50,219.00 and no time. -$50,219
Supplemental Agreement for work within scope A00013 · GC022 revise security cages arcyber COF, funding for clin 0001AA $4,724.69, clin 0001AB $13,413.31, 63 calendar days, non-compensable $18,138
Supplemental Agreement for work within scope A00012 · Modification GC020 leed design review fee for the arcyber COF funding for clin 0001AB $4,250.53, no time. $4,251
Supplemental Agreement for work within scope A00011 · Modification for GC015 missing security revise life safety added cost and time, $70,694.90, 14 days, funding for clin 0001AB $70,695
Supplemental Agreement for work within scope P00001 · 129 day compensable time extension modification arcyber company operations facility, fort gordon GA $143,288
Supplemental Agreement for work within scope A00010 · Modification for GC017 revised duct bank 107TH & 15TH arcyber COF, added cost no time, funding for clin 0001AB $21,440
Supplemental Agreement for work within scope A00009 · Modification for GC013 add roof drain splash protection for arcyber COF, added cost $5,593.73 and no time. Funding for clin 0001AB $5,594
Supplemental Agreement for work within scope A00008 · GC010 REA for 15TH ST comms ductbank for arcyber COF added cost $38,070.11, no time, funding for clin 0001AB $38,070
Supplemental Agreement for work within scope A00007 · Modification for GC011 metal roof shimming arcyber COF, funding for clin 0001AB, added cost of $90,266.24, added time 17 days. $90,266
Supplemental Agreement for work within scope A00006 · Modification for changed site conditions added cost no time. Funding for clin 0001 $8,535
Supplemental Agreement for work within scope A00005 · Funding for clin 0001 added cost no time MOD for added sprinkler heads at AHP's $5,639
Supplemental Agreement for work within scope A00004 · Modification for GC019 weather time extension added time no cost funding for clin 0001 $0
Supplemental Agreement for work within scope A00003 · Modification for COF added cost and time funding for clin 0001 $27,230
Supplemental Agreement for work within scope A00002 · Modification for security changes added cost no time. $27,230
Supplemental Agreement for work within scope A00001 · Funding for clin 0001 -$4,994
Original award $14,000,000
Show all 25

About this award

This is a $16,460,184.80 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) Savannah District to Odyssey International, Inc. for the construction of the Army Cyber Command (ARCYBER) Complex Operations Facility at Fort Gordon, Georgia. The contract was awarded on January 18, 2019 with a completion date of October 29, 2021. Odyssey International, Inc. is a small disadvantaged, woman-owned business. This contract was not set aside for any special designation.

Quick answers

Who was awarded contract W912HN19C3000?

W912HN19C3000 was awarded to Odyssey International, Inc. by ENDIST Savannah (US Army Corps of Engineers) on January 18, 2019.

How much is contract W912HN19C3000 worth?

The government has obligated $14,768,955 on W912HN19C3000. Its potential value, with all options, is $16,460,185.

Was contract W912HN19C3000 competed?

The extent of competition for W912HN19C3000 was full and open competition. The government received 8 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award