Base year, philpott--cpaf contract

Ended Definitive Contract Awarded Last action

Contract number
W912HN09C0015
Awardee
Awarding agency
Obligated
$6,243,350

Award facts

Opportunity
Contract value 99% obligated
  • $6,289,457.27 Current, with exercised options
  • $6,289,457.35 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
561210 Facilities Support Services
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 2 offers Negotiated Proposal / Quote
Pricing
Cost Plus Award Fee
Place of performance
Bassett, VA 24055, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00066 · W kerr scott operations and maintenance services contract modification to release assignment of claims from united bank in virginia to the contractor, RBS, INC. -$92,822
Funding Only Action P00065 · Option year 4, 12 (twelve) day extension to o & m contract for services at w. Kerr scott lake project, wilkesboro, north carolina. $45,624
Exercise an Option P00064 · Option year 4, 33 (thirty-three) day extension to o & m contract for services at w. Kerr scott lake project, wilkesboro, NC. $94,289
Exercise an Option P00063 · 30 day extension of 4TH option year IAW far 52.217-8 $91,247
Exercise an Option P00062 · 31 day extension of 4TH option year IAW far 52.217-8 $94,289
Change Order P00061 · Additional 31 day extension to option year 4 to provide o & m services to w kerr scott DAM & reservoir. Additional POP added: 01 JUL - 31 JUL 2014. $91,247
Change Order P00060 · Modification to operations and maintenance services contract at w. Kerr scott lake project to fund remaining month of option year 4 and extend the performance… $182,494
Funding Only Action P00059 · Modification to add funds for april 2014 for operation and maintenance services at w. Kerr scott lake in wilkesboro, NC. $85,164
Funding Only Action P00058 · Add funding for FEB/MAR 2014. $85,164
Funding Only Action P00057 · Funding modification for w kerr scott DAM & reservoir for JAN-FEB 2014. $85,164
Supplemental Agreement for work within scope P00056 · Replace existing security lights with led lights at WKS with sustainability funds. $5,881
Funding Only Action P00055 · Deobligation modification. -$701
Funding Only Action P00054 · Funding modification for JAN 2014 $85,164
Funding Only Action P00053 · December funding modification for operations and maintenance at w. Kerr scott reservoir $42,582
Funding Only Action P00052 · Funding modification to add incremental funding while under CRA. $36,203
Funding Only Action P00051 · Modification to add funds in OY4 for operations and maintenance at w kerr scott lake. $42,878
Change Order P00050 · Modification to o & m services for w. Kerr scott reservoir to add a vault toilet at keowee park, renovate campsites at warrior creek park and DE-obligate unused… $50,794
Funding Only Action P00049 · Cpaf modification to add funding for AUG through OCT 2013 regarding w. Kerr scott lake project. $213,238
Change Order P00048 · Modification to w. Kerr scott lake o & m contract to correct clin 200121 amounts to match financial system amounts. $1,174
Supplemental Agreement for work within scope P00047 · Modification to w. Kerr scott lake project o & m to deobligate unused funds in the amount of $426.53 from OY2. -$427
Change Order P00046 · Modification to w kerr scott lake project o & m contract to fund $170,000 unilaterally for the month of july. $170,000
Change Order P00045 · MOD to add water testing services and winter camping cleaning services in option year 4 at w. Kerr scott lake. $5,999
Exercise an Option P00044 · Modification to exercise option year 4 with a period of performance from 6/1/2013 - 5/31/2014. $85,164
Funding Only Action P00043 · WKS april & may 2013 funding modification $133,654
Change Order P00042 · Additional work modification for striping at warrior creek, additional mowing areas, and winter camping maintenance for w kerr scott reservoir. $16,954
Funding Only Action P00041 · Funding only action for FEB 2013 in OY 3 $85,145
Other Administrative Action P00040 · Option year 1, w kerr scott-- deobligation MOD for excess funds -$640
Additional Work (new agreement, FAR part 6 applies) P00039 · Additional work in option period 3 determined to be within the scope of the contract. $349,501
Additional Work (new agreement, FAR part 6 applies) P00038 · Construction of ADA vault toilet at w kerr scott $10,232
Exercise an Option P00037 · Exercise 3RD option period, WKS o & m contract $460,761
Additional Work (new agreement, FAR part 6 applies) P00036 · WK scott sustainability package $55,826
Additional Work (new agreement, FAR part 6 applies) P00035 · Bandit's roost showerhouse upgrades. $17,957
Supplemental Agreement for work within scope P00034 · Base year, w kerr scott-- $262,976
Funding Only Action P00033 · Funding modification for 2ND option year $291,432
Additional Work (new agreement, FAR part 6 applies) P00032 · Buoy line and paving modification. $62,766
Additional Work (new agreement, FAR part 6 applies) P00031 · Construction of vault toilets at w kerr scott $15,262
Additional Work (new agreement, FAR part 6 applies) P00030 · Remove existing and install new HVAC system at w kerr scott visitor assistance center. $62,512
Funding Only Action P00029 · MOD to correct dollar amounts for option year 2. $0
Exercise an Option P00028 · Exercise of 2ND option period $427,569
Funding Only Action P00027 $28,213
Funding Only Action P00026 · Funding modification $0
Funding Only Action P00025 · Base year, w kerr scott-- $7,229
Supplemental Agreement for work within scope P00024 · Shower house improvements at berry mountain park, w kerr scott $13,696
Additional Work (new agreement, FAR part 6 applies) P00023 · Modification for paving at smithy's creek parking area $6,892
Other Administrative Action P00022 · Deobligate remaining unused funds from the base year of the contract $0
Other Administrative Action P00021 · Deobligating unused funds from the base year of the contract $0
Other Administrative Action P00020 · Reassignment of claims $0
Funding Only Action P00019 · March funding modification $85,000
Funding Only Action P00018 · Base year, w kerr scott funding MOD $170,000
Funding Only Action P00017 · Operations and maintenance at w kerr scott lake $30,325
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a cost-plus-award-fee (CPAF) contract awarded on May 4, 2009 by the U.S. Army Corps of Engineers to Re-Engineered Business Solutions, Inc., a minority-owned small business and certified HUBZone firm. The contract, valued at a ceiling of $6,289,457.35, is for base year facilities support services at the Philpott location, with a final completion date of August 31, 2014. Re-Engineered Business Solutions specializes in providing comprehensive facilities support services, including operations and maintenance, minor construction, repairs, and specialized tasks across various federal sites. This contract is part of the company's broader portfolio of facilities management work with the U.S. Army Corps of Engineers, including multiple award IDIQ contracts covering locations in Florida, Arkansas, and Georgia.

Quick answers

Who was awarded contract W912HN09C0015?

W912HN09C0015 was awarded to Re-Engineered Business Solutions, Inc. by ENDIST Wilmington (US Army Corps of Engineers) on May 4, 2009.

How much is contract W912HN09C0015 worth?

The government has obligated $6,243,350 on W912HN09C0015. Its current value, with exercised options, is $6,289,457. Its potential value, with all options, is $6,289,457.

Was contract W912HN09C0015 competed?

The extent of competition for W912HN09C0015 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award