The project is for the renovation of the northern half of building 28 and a portion of building 1 basement to provide adequate and secure command and control administrative source for the US army V…

Active Definitive Contract Awarded Last action

Contract number
W912GB25C0012
Awardee
Awarding agency
Obligated
$40,773,869

Award facts

Opportunity
Contract value 96% obligated
$42,333,598.08 Current and potential, with all options
Completion date 53% complete
Current and potential, with all options
Contracting staff
Funding agency
ENDIST Europe US Army Corps of Engineers, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Poland

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00003 · Scope of work change: CR004 waterproofing buildings 1, 2 and 28 contract for PPI EDI command and control facility and technical control facility buildings 1 and… $2,380,375
Change Order P00002 · Scope of work change: CR010 disposal of hazardous waste material (PAH mastic) $174,069
Supplemental Agreement for work within scope A00002 · Scope of work change: CR002 descope organizational parking lot -$426,867
Supplemental Agreement for work within scope A00001 · Furnish all necessary plant, labor, material, equipment, transportation, and supervision to provide changes to the staging and laydown area in accordance with… $0
Exercise an Option P00001 · Command and control facility (C2F) $884,861
Original award $37,761,431

About this award

ENDIST Europe, a Defense organization, awarded a definitive firm fixed price contract with a $40.77 million ceiling value to SKE & VFS JV on April 28, 2025, with no set-aside used. The work renovates the northern half of Building 28 and a portion of the Building 1 basement at the Poznan Command and Control Facility and Technical Control Facility in Poznan, Poland, to provide a secure command and control administrative space for the U.S. Army V Corps Headquarters (Forward). Scope also includes change order CR004, which adds waterproofing to Buildings 1, 2, and 28. Ultimate completion date is April 19, 2028, and place of performance is Poland.

The originating notice was a Pre-Solicitation Sources Sought issued by the U.S. Army Corps of Engineers, posted January 23, 2024, with responses due May 17, 2024. It described major architectural, structural, electrical, mechanical, and telecommunications upgrades, plus security systems, fire protection, and energy monitoring controls. The notice anticipated a construction value between $25 million and $100 million, a completion timeline of no more than 24 months after award, and NAICS 236220, Commercial and Institutional Building Construction. It waived small and small disadvantaged business requirements.

Description

The project is for the renovation of the northern half of building 28 and a portion of building 1 basement to provide adequate and secure command and control administrative source for the US army V corps headquarters (FORWARD).

Quick answers

Who was awarded contract W912GB25C0012?

W912GB25C0012 was awarded to SKE & VFS JV by Army European Command (Department of the Army) on April 28, 2025.

How much is contract W912GB25C0012 worth?

The government has obligated $40,773,869 on W912GB25C0012. Its current value, with exercised options, is $42,333,598.

Which agency awarded contract W912GB25C0012?

Army European Command (Department of the Army) awarded W912GB25C0012, with funding from ENDIST Europe (US Army Corps of Engineers).

Was contract W912GB25C0012 competed?

The extent of competition for W912GB25C0012 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award