$46,790,630

Award facts

Contract value 100% obligated
$46,790,715.49 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
ENDIST Europe US Army Corps of Engineers, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Germany

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00014 · CR048 emergency sewer cleaning $546,896
Change Order P00013 · Sofa ABG-x construction, part 1C -$160,948
Supplemental Agreement for work within scope A00036 · Contract for ABG4 AB4-15-0018 vehicle maintenance shop, REF # R00048, total contract price is increased by 12,291.84 EU. The contract completion date shall… $13,176
Supplemental Agreement for work within scope A00035 · Contract for ABG4 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS skeet range / environmental… $17,985
Supplemental Agreement for work within scope A00034 · Contract for ABG4 AB4-15-0018 vehicle maintenance shop (MCA)/skeet range demolition (FY15 OMA)/environmental study EAS skeet range / environmental study at… $24,345
Supplemental Agreement for work within scope A00033 $24,008
Supplemental Agreement for work within scope A00032 · Contract for ABG4 AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - skeet range /… $24,501
Supplemental Agreement for work within scope A00031 · Contract for vehicle maintenance shop /skeet range demolition (FY15 OMA)/environmental study EAS, P2 450846 skeet range / environmental study, at grafenwoehr.… $0
Supplemental Agreement for work within scope A00030 · Contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - skeet range /… $143,934
Supplemental Agreement for work within scope A00029 · Contract for vehicle maintenance shop skeet range demolition environmental study EAS skeet range / environmental study - PN 44-00946-5, P2 451317 at… $4,305
Supplemental Agreement for work within scope A00028 $15,220
Supplemental Agreement for work within scope A00027 · Contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study, reference no. R00039 CR037… $13,995
Supplemental Agreement for work within scope A00026 · Contract for AB4-15-0018 vehicle maintenance shop EAS PHS 1 MCA skeet range demolition/environmental study. Contract amount is increased by 67,061.71 EU,… $74,186
Supplemental Agreement for work within scope A00025 · Contract for vehicle maintenance shop, MCA /skeet range, demolition, OMA environmental study, at grafenwoehr. Contract amount is increased by 3,053.00 EU,… $3,286
Supplemental Agreement for work within scope A00024 · Contract for vehicle maintenance shop skeet range, demolition and environmental study at grafenwoehr. Reference no. R00036 CR033 92.05 & 92.06 copper… $126,669
Supplemental Agreement for work within scope A00023 $30,528
Supplemental Agreement for work within scope A00022 · Contract for vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition at grafenwoehr. Contract amount is unchanged, contract duration is… $0
Supplemental Agreement for work within scope A00021 · Contract for vehicle maintenance shop MCA)/skeet range demolition skeet range / environmental study at grafenwoehr. Contract amount is increased by 8,003.27 EU,… $8,854
Supplemental Agreement for work within scope A00020 $0
Supplemental Agreement for work within scope A00019 · Contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition environmental study skeet range / environmental study - PN… $9,930
Supplemental Agreement for work within scope A00018 $410,453
Supplemental Agreement for work within scope A00017 · Contract for vehicle maintenance shop (skeet range demolition environmental studyskeet range / environmental study at grafenwoehr. Reference no. R00029 CR025… $40,759
Supplemental Agreement for work within scope A00016 · Construction, part 1C, vehicle maintenance shop (EAS phase 1), at grafenwoehr, reference no, R00028, CR024 93.09 drainage connection. Contract amount is… $38,363
Supplemental Agreement for work within scope A00015 · Contract for vehicle maintenance shop EAS phase 1 FY16 MCA skeet range demolition skeet range / environmental study - PN 44-00946-5, P2 451317 at grafenwoehr.… $2,032
Supplemental Agreement for work within scope A00014 · Construction, part 1C, contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA) skeet range contract for, skeet range / environmental study… $41,939
Supplemental Agreement for work within scope A00013 · Vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition, environmental study at grafenwoehr. Contract amount is increased by 208,906.02,… $231,099
Supplemental Agreement for work within scope A00012 · Vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition skeet range / environmental study reference no. R00024 CR016 deduct fee lines to… -$1,074
Supplemental Agreement for work within scope A00011 · (OMA)/environmental study EAS -skeet range / environmental study at grafenwoehr. Reference no. R00023 CR012 91.02 vehicle exhaust material change CR013… $5,629
Supplemental Agreement for work within scope A00010 · Contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - PN 86825, P2 450846 skeet… -$5,620
Supplemental Agreement for work within scope A00009 · Vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - skeet range / environmental study -at grafenwoehr.… $92,662
Supplemental Agreement for work within scope A00008 · Contract for AB4-15-0018 vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - PN 86825, P2 450846 skeet… $249,907
Supplemental Agreement for work within scope A00007 · Contract for vehicle maintenance shop (P2 450846 skeet range / environmental study - PN 44-00946-5, P2 451317 at grafenwoehr. Reference no. R00019 CR008 NT… $28,341
Change Order P00012 · Sofa ABG-x vehicle maintenance shop grafenwoehr -$512,857
Change Order P00011 · Sofa ABG-x award construction, part 1C $92,195
Supplemental Agreement for work within scope A00006 -$357,860
Supplemental Agreement for work within scope A00005 -$784
Supplemental Agreement for work within scope A00004 -$2,280
Supplemental Agreement for work within scope A00003 $4,959
Supplemental Agreement for work within scope A00002 · Contract for vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - PN 86825, P2 450846 skeet range /… $51,767
Change Order P00010 · Sofa ABG-x vehicle maintenance shop, grafenwoehr $1,218,874
Change Order P00009 · Sofa ABG-x termination of PART2 -$120,837
Change Order P00008 · Sofa ABG-x vehicle maintenace shop & skeet range grafenwoehr, add and award part 1D $1,356,924
Supplemental Agreement for work within scope A00001 · Sofa:: contract for vehicle maintenance shop (EAS phase 1) (FY16 MCA)/skeet range demolition (FY15 OMA)/environmental study EAS - PN 86825, P2 450846 skeet… $49,893
Supplemental Agreement for work within scope P00007 · Sofa ABG-x 7.1.5-7.1.7 request for part 1C $37,257,437
Change Order P00006 · Sofa ABG-x award part 1B, vehicle maintenance shop, grafenwoehr $788,544
Supplemental Agreement for work within scope P00005 · Sofa ABG-x award part 1B heating line - admin MOD to correct the counter !! $0
Supplemental Agreement for work within scope P00004 · Award part 1B, vehicle maintenance shop, grafenwoehr $2,620,264
Change Order P00003 · FY16, 7.1.3-7.1.4 086824 vehicle maintenance shop $316,881
Supplemental Agreement for work within scope P00002 · Sofa vehicle maintenance shop, grafenwoehr, germany $130,056
Supplemental Agreement for work within scope P00001 · Vehicle maintenance shop/skeet range demolition/environmental study, grafenwoehr, germany $1,459,373
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

ENDIST Europe awarded a definitive firm fixed-price contract for vehicle maintenance shop and skeet range demolition with environmental study at Grafenwoehr, Germany, with a ceiling value of $46,790,715.49. The award date was March 19, 2015, with an ultimate completion date of December 22, 2024.

The scope includes emergency sewer cleaning, FPCON gate access delay mitigation, miscellaneous mechanical and civil changes, radiant panel mounting revision, warehouse sprinkler system revision, and BMS requirements additions, along with miscellaneous FPCON exercise delays. No set-aside was used. Place of performance is Germany.

Quick answers

How much is contract W912GB15C0007 worth?

The government has obligated $46,790,630 on W912GB15C0007. Its current value, with exercised options, is $46,790,715.

Which agency awarded contract W912GB15C0007?

Army European Command (Department of the Army) awarded W912GB15C0007, with funding from ENDIST Europe (US Army Corps of Engineers).

Was contract W912GB15C0007 competed?

The extent of competition for W912GB15C0007 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award