Temporary lodging facility, ramstein AB

Ended Definitive Contract Awarded Last action

Contract number
W912GB13C0007
Awardee
Not on record
Awarding agency
Obligated
$28,298,515

Award facts

Contract value 100% obligated
$28,302,325.13 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Germany

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00012 · Abgx sofa temporary lodging facility, ramstein AB germany $0
Change Order P00011 · Sofa ABG-x temporary lodging facility ramstein $37,598
Supplemental Agreement for work within scope A00039 · Basic action NAF $11,110
Change Order A00038 · Sofa ABG-x: contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00048 CR054 invoice late fees $17,148
Supplemental Agreement for work within scope A00037 · Contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00047 CR052 architectural changes IV (NAF) $32,303
Supplemental Agreement for work within scope A00036 -$30,933
Supplemental Agreement for work within scope A00035 $63,879
Supplemental Agreement for work within scope A00034 -$17
Supplemental Agreement for work within scope A00033 -$1,070
Supplemental Agreement for work within scope A00032 $281,953
Supplemental Agreement for work within scope A00031 -$1,392
Supplemental Agreement for work within scope A00030 $58,294
Supplemental Agreement for work within scope A00029 $463,907
Supplemental Agreement for work within scope A00028 $150,659
Supplemental Agreement for work within scope A00027 $1,503
Supplemental Agreement for work within scope A00026 -$861
Supplemental Agreement for work within scope A00025 $100,806
Supplemental Agreement for work within scope A00024 $212,530
Supplemental Agreement for work within scope A00023 $79,394
Supplemental Agreement for work within scope A00022 $84,268
Supplemental Agreement for work within scope A00021 -$5,918
Supplemental Agreement for work within scope A00020 $35,766
Supplemental Agreement for work within scope A00019 $54,558
Supplemental Agreement for work within scope A00018 -$848
Supplemental Agreement for work within scope A00017 · Sofa ABG-x: contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00027 CR024-1 NT27 stairwell cable… $7,415
Supplemental Agreement for work within scope A00016 · Contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00025 CR023 NT20 mechanical changes $57,818
Change Order P00010 · Sofa ABG-x temporary lodging facility, TLF, ramstein $29,198
Supplemental Agreement for work within scope A00015 $232,330
Supplemental Agreement for work within scope A00014 $13,051
Supplemental Agreement for work within scope A00013 $39,558
Supplemental Agreement for work within scope A00012 $37,312
Supplemental Agreement for work within scope A00011 $60,068
Supplemental Agreement for work within scope A00010 · Sofa ABG-x: contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Total contract price is increased by 54,288.28… $74,973
Supplemental Agreement for work within scope A00009 · Contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Total contract price is increased by 101,919.38 EU. CR011-1… $140,753
Supplemental Agreement for work within scope A00008 $68,826
Supplemental Agreement for work within scope A00007 $12,344
Supplemental Agreement for work within scope A00006 $69,409
Supplemental Agreement for work within scope A00005 $47,470
Supplemental Agreement for work within scope A00004 $3,557
Supplemental Agreement for work within scope A00003 $8,101
Change Order A00002 · Sofa ABG-x:contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00011 CR003 demolition of… -$3
Change Order A00001 · Sofa: contract for temporary lodging facility, ramstein air base, germany at ramstein air base, germany. Reference no. R00010 CR002 construction fence $13,264
Change Order P00009 · Temporary lodging facility ramstein $6,563
Change Order P00008 · Temprary lodging facility TLF ramstein $2,047,516
Supplemental Agreement for work within scope P00007 $8,544
Supplemental Agreement for work within scope P00006 · Temporary lodging facility, ramstein AB, germany $22,256,906
Change Order P00003 · Construct temporary lodging facility ramstein air base $658,893
Change Order P00002 · ABG3 to revise secondary services, NAF funded $0
Change Order P00001 $13,810
Original award $746,199
Show all 50

About this award

This is a firm fixed-price definitive contract awarded by the U.S. Army European Command (USAREUR) to an unnamed prime contractor for the construction of a Temporary Lodging Facility at Ramstein Air Base in Germany. The contract has a ceiling value of $28,302,325.13 and is set to be completed by February 24, 2024. The contract does not have a set-aside designation. Without additional information, the specific products and services being delivered under this contract, as well as the identity of the prime contractor and any major subcontractors, cannot be determined from the provided details.

Quick answers

How much is contract W912GB13C0007 worth?

The government has obligated $28,298,515 on W912GB13C0007. Its current value, with exercised options, is $28,302,325.

Was contract W912GB13C0007 competed?

The extent of competition for W912GB13C0007 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award