FMM SE-4 construction

Active Definitive Contract Awarded Last action

Contract number
W912ES24C0011
Awardee
Awarding agency
Obligated
$24,921,046

Award facts

Opportunity
Contract value 100% obligated
$24,921,046.38 Current and potential, with all options
Completion date 72% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Comstock, MN, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00005 · (R-006) adjust the contract quantities to actual final quantities for the following clin 0008 removal of road surfacing-180TH AVE S, clin 0018 aggregate surface… $224,329
Supplemental Agreement for work within scope P00005 $0
Supplemental Agreement for work within scope A00004 · (R-008) compensate the contractor for sealing of two (2) wells on the SE-4 project site which had not been identified prior to award. $9,289
Supplemental Agreement for work within scope A00003 · This contract is modified to: correct an error in modification numbering. $0
Change Order P00004 · (R-009) extend the contract completion date by 15 calendar days to account for adverse weather. (R-005) adjust the class 5 to class 13, to include additional… $557,578
Change Order A00002 · (R-002) change the southern embankment and inspection trench starting station (at the north end of the project) from 53+80.00 to 60+00.13. -$25,984
Change Order A00001 · (R-004) remove aggregate surface material on 180TH AVE S and 3RD ST. S and replace with suitable material. Conduct testing for clay content and PI to meet mndot… $201,358
Change Order P00003 · R-001: adjust the compaction and moisture control requirements for the road embankment portions of SE-4. $70,018
Other Administrative Action P00002 $0
Other Administrative Action P00001 $0
Original award $23,893,747
Show all 11

About this award

The U.S. Army Corps of Engineers, St. Paul District awarded a $24.9 million firm fixed price definitive contract to PWS Inc. on May 30, 2024 for construction work on the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-4, in Comstock, Minnesota.

The award adjusts contract quantities to actual final quantities for removal of road surfacing, aggregate surface, aggregate base along 180th Avenue South, and riprap work. The originating pre-solicitation, posted February 13, 2024, described construction of 5.8 miles of dam embankment including associated structures and features for the flood risk management project located in Clay County, Minnesota. No set-aside was used. Ultimate completion is scheduled for October 15, 2027.

Quick answers

Who was awarded contract W912ES24C0011?

W912ES24C0011 was awarded to PWS Inc. by ENDIST St Paul (US Army Corps of Engineers) on May 30, 2024.

How much is contract W912ES24C0011 worth?

The government has obligated $24,921,046 on W912ES24C0011.

Was contract W912ES24C0011 competed?

The extent of competition for W912ES24C0011 was full and open competition. The government received 6 offers.

On GovTribe