FMM SE-1B

Active Definitive Contract Awarded Last action

Contract number
W912ES24C0008
Awardee
Awarding agency
Obligated
$15,061,184

Award facts

Opportunity
Contract value 99% obligated
$15,161,184.17 Current and potential, with all options
Completion date 78% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Horace, ND 58047, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00005 $0
Other Administrative Action P00004 $0
Supplemental Agreement for work within scope P00003 · (r-004) compensate the contractor for removal and replacement of unsuitable material and for impact costs related to traffic control; provide a contract time… $779,976
Supplemental Agreement for work within scope A00003 · This contract is modified to: (r-004) extend the contract completion date by 42 calendar days to account for adverse weather between april 2024 through december… $0
Change Order A00002 · (r-005) assume authority and responsibility for the storm water pollution prevention plan for SE-2A, to include installation of features (plugs, straw bales,… $137,168
Change Order A00001 · R-002: remove approximately 10" thick concrete discovered under asphalt road (CR16) west of CR17/16 intersection to the west project limit line, r-003:… $69,099
Other Administrative Action P00002 · FMM SE-1B funding $0
Change Order P00001 · Require the contractor to remove all borrow material from the city of fargo stockpile within 2024, alter seasonal limitation dates, and specify that seeding… $866,683
Original award $13,208,258

About this award

The U.S. Army Corps of Engineers, St. Paul District, awarded a $15.16 million definitive contract to HSG Park Joint Venture 2, LLC, a woman-owned small business, for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1B, on February 27, 2024, under a total small business set-aside.

The contract is firm fixed price. The originating solicitation called for construction of approximately 0.5 miles of earthen dam embankment, relocation of two county roads including a roundabout, and related ditching. Embankment material is sourced from adjacent borrow sites and a stockpile near Fargo. Place of performance is Horace, North Dakota.

The ultimate completion date is August 1, 2027. The contract includes two modifications: removal and replacement of unsuitable material with contractor compensation and impact cost reimbursement for traffic control activities, and a 51-calendar-day time extension. NAICS code 237990 (other heavy and civil engineering construction) applies, with a size standard of $45 million.

Quick answers

Who was awarded contract W912ES24C0008?

W912ES24C0008 was awarded to HSG Park Joint Venture 2, LLC by ENDIST St Paul (US Army Corps of Engineers) on February 27, 2024.

How much is contract W912ES24C0008 worth?

The government has obligated $15,061,184 on W912ES24C0008. Its current value, with exercised options, is $15,161,184.

Was contract W912ES24C0008 competed?

The extent of competition for W912ES24C0008 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe