Construction of the red river structure of the fargo moorhead metropolitan area flood risk management project

Active Definitive Contract Awarded Last action

Contract number
W912ES22C0003
Awardee
Awarding agency
Obligated
$117,744,719

Award facts

Opportunity
Contract value 100% obligated
$117,744,719.34 Current and potential, with all options
Completion date 85% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fargo, ND 58104, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00014 $162,821
Supplemental Agreement for work within scope A00013 · (R-026) compensate the contractor for (REA-005) the necessity to build an access road to the red river structure site following the 3RD street closure;… $25,744
Supplemental Agreement for work within scope A00012 · Change the protective bollard along the north side of the DAM walls, ratio of nuclear density and sand cone tests, berm fill lift, compaction and moisture… $0
Supplemental Agreement for work within scope A00011 · (R-025 and 027) adjust the estimated contract quantities to actual final quantities for clin 0036AB steel H-pile (HP 14X73), 0037AB steel H-pile (HP 14X102),… $431,962
Supplemental Agreement for work within scope A00010 · This contract is modified to: (R-017) extend the contract completion date by 40 calendar days to account for adverse weather between august 2024 through… $0
Change Order A00009 · Revise the submergence ratio equation and equation 2 to correct identified errors and update associated screens identifies stain for the concrete trunnion… $29,296
Change Order A00008 · Replaces the existing square aluminum light poles, replace the communication cable, run 1.5-inch conduit to the mechanical service bridge, add low flow radar… $186,003
Supplemental Agreement for work within scope P00002 · Changes to turf reinforcement mat and J-bulb sizing $442,935
Change Order A00007 · (R-17) extend the contract completion date by 42 calendar days to account for unusually severe weather experienced at the red river structure project site… $0
Change Order P00001 · Include radiographic testing for all diagonal connections in skin plate bracings as identified in drawings SG203 and SG506. To mitigate the schedule impacts-… $1,063,795
Change Order A00006 · Require the contractor to relocate the temporary construction facilities from their current location at the red river structure site, to include moving job… $136,533
Change Order A00005 · 1. (R-0012) revise the pier and abutment stairs and install accordance with the revised design change the impervious fill lift thickness to 9 inches. 2. (R0015)… $182,509
Change Order A00004 · Change the specified machinery hoisting equipment from a worm gear reducer to a helical gear and conduct compliance verification through load testing before… $307,153
Change Order A00003 · The change encompasses design changes to the bridges and mechanical platforms schedule changes to allow earlier placement of embankment and faster reviews of… $116,173
Change Order A00002 · (1) (R-02) rebar size change and gate seal heater (2) (R-04) revise trunnion girder transverse bars (3) (R-06) compensate contractor for removal of house… $168,646
Change Order A00001 · This contract is modified to: provide 6 licenses to access the contractor's construction management software and 6 tablets similar in size and capabilities to… $25,996
Original award $114,897,115
Show all 17

About this award

The U.S. Army Corps of Engineers, St Paul District, awarded a $117.7 million definitive firm-fixed-price contract to Ames Construction, Inc. for construction of the Red River Structure of the Fargo-Moorhead Metropolitan Area Flood Risk Management Project on May 15, 2022, with ultimate completion on August 19, 2027.

The Red River Structure includes a gated structure, dam walls, bridges, stilling basin, and associated infrastructure approximately 5,000 feet in total length. The award encompasses primary construction scope and compensates the contractor for construction of an access road to the site following Third Street closure and for sealing cracks in the control structure. Place of performance is Fargo, North Dakota. The contract is classified under NAICS 237990 (heavy and civil engineering construction). No set-aside was used in this procurement.

Quick answers

Who was awarded contract W912ES22C0003?

W912ES22C0003 was awarded to Ames Construction, Inc. by ENDIST St Paul (US Army Corps of Engineers) on May 15, 2022.

How much is contract W912ES22C0003 worth?

The government has obligated $117,744,719 on W912ES22C0003.

Was contract W912ES22C0003 competed?

The extent of competition for W912ES22C0003 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award