Fargo diversion inlet structure

Ended Definitive Contract Awarded Last action

Contract number
W912ES17C0003
Awardee
Awarding agency
Obligated
$55,657,308

Award facts

Opportunity
Contract value 100% obligated
  • $55,657,307.90 Current, with exercised options
  • $55,808,307.90 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
North River, ND 58102, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00029 · (R-062) adjust the estimated quantities to final quantities for clin 0017AC bedding B1 over 2,600 CY, clin 0021 geotextile type 2, clin 0025 seeding; and to… $103,893
Change Order A00028 · (R-063) extend the contractor completion date by 220 days for completion of administrative requirements related to closeout. $0
Change Order A00027 · (R-061) correct the flow calculation equation for the PLC system. $6,439
Change Order A00026 · (R-058) replace light poles replace communication cabling run new conduit to the mechanical add low flow radar and wire weight mount add a wind sensor tower and… $371,573
Change Order P00011 · This contract is modified to: use a helical gear (parallel shaft reducer) instead of the worm gear originally specified in the contract for the machinery… $1,297,129
Change Order A00025 · Increase the contract quantity to a final quantity for clin 0028AB steel H-pile (HP 14X73) and 0029 steel sheetpile. $55,666
Change Order A00024 · Add a PLC manual override option adjust the safety chain height remove the design impact load for the concrete barrier embed door add compressible joint… $8,024
Change Order P00010 · PT bar fix. $1,151,655
Change Order A00023 · (R-51) change the size of the stair platform channel. (R-54) add waterstops. (R-55) compensate the contractor for impact costs associated with the stop work… $158,917
Change Order A00022 · This contract is modified to (1) extend the contract completion date by 18 calendar days to account for delays, impacts and inefficiencies associated with a… $0
Change Order A00021 · This contract is modified to: extend the contract completion date by 41 days to account for delays, impacts and inefficiencies associated with changing the PT… $0
Change Order A00020 · This contract is modified to: revise the material used for the sill beam and side seal and bumper plate secondary placements from grout to a 7000 PSI concrete… $34,990
Change Order A00019 · This contract is modified to: (1) install a utility crossing (R-46) (2) install a tainter gate opening gage (R-46) (3) remove the barb wire on the security… $355,126
Change Order A00018 · The contract is modified to: procure 88 each longitudinal post tensioned 1-3/4 inch bar. Submit certifications documenting compliance with astm A722. $266,094
Change Order A00017 · This contract is modified to: revise the exterior light temperature, remove proximity swiches, raceway and conductors, make numerous miscellaneous changes to… $1,642
Change Order A00016 · This contract is modified to: revise the prestressed sole plate details shown on sheet S- 541 and change the expansion and fixed curved plate bearing assemblies… $37,440
Change Order A00015 · This contract is modified to add embed doors along the bridge deck, remove expansion joints parallel to the bridge, correct an error in the specifications… $15,882
Additional Work (new agreement, FAR part 6 applies) A00014 · Gauge well part II - this is the second part of a 2-part modification to install a gauge well on the upstream side of the diversion inlet structure. $487,740
Change Order P00009 · This contract is modified to: delete the requirement to conduct deep soil mixing and compensate the contractor for costs incurred in preparation for the work… -$2,163,509
Change Order A00013 · This contract is modified to: (1) update the training requirement for QC personnel monitoring the painting of hydraulic structures and mechanical equipment… $37,054
Change Order A00012 · This contract is modified to: adjust the estimated quantities to interim quantities for clins 0015AB riprap (R140), 0017AB B2 bedding, 0020 geotextile - type 1. $138,859
Change Order A00011 · Pile installation for a gauge well compensate the government for RE-inspection costs revise the reveal elevation on pier abutments surveying costs for… $43,822
Change Order A00010 · This contract is modified to: (1) ( R-16) change the trunnion girder and anchorage system duct material from grout to GEL and reduce bar size for anchorage.… $154,302
Supplemental Agreement for work within scope P00008 · Final equitable adjustment for the fargo suspension. $895,279
Change Order A00009 · This contract is modified to: (1) annotate exact camera and light pole locations (2) clarify concrete air content, slump and compression testing requirements. $0
Supplemental Agreement for work within scope P00007 · Fargo suspension MOD 7. $5,565,596
Change Order A00008 · This contract is modified to: (1) (R-19) compensate the contractor for costs incurred to splice additional pile due to a slope error in the designs (2) (R-21)… $20,432
Change Order A00006 · This contract is modified to: add sections and correct stationing for an expansion joint on the structural drawings listed below to clarify requirements and… $0
Change Order A00005 · This contract is modified to-add dimensions for clarity, make corrections to minor errors in dimensions, add sections and correct stationing for an expansion… $0
Supplemental Agreement for work within scope P00006 · Modification to pay for dewatering and channel restoration as a result of the suspension of work. $418,270
Change Order A00004 · This contract is modified to reimburse the contractor for payment for the governments half of the partnering meeting. In accordance with 52.000-4004 partnering,… $1,250
Change Order P00005 · This contract is modified to extend the contract completion date by 942 calendar days to account for time lost to the suspension of work, as well as the time… $0
Change Order A00003 · This contract is modified to: 1) R-01: change various drawings to match specification sheets and change epoxy coating requirements on steel reinforcing bars; 2)… $134,364
Other Administrative Action P00004 · Fargo funding MOD 4 $0
Change Order A00002 · This contract is modified to: install six (6) highly visible aluminum no trespassing signs on galvanize steel posts evenly spaced along the eastside of the… $1,511
Supplemental Agreement for work within scope A00001 · Structural-control structure/stilling $17,392
Other Administrative Action P00003 · Funding modification 3 $0
Other Administrative Action P00002 · Administrative modification to extend completion date due to NTP not being issued as detailed in amended RFP. $0
Other Administrative Action P00001 · Administrative funding modification $0
Original award $46,040,475
Show all 40

About this award

The US Army Corps of Engineers awarded a definitive firm fixed price contract to Ames Construction, Inc. for the Fargo Diversion Inlet Structure project on December 6, 2016, with a ceiling value of $55.7 million and an ultimate completion date of October 27, 2025.

The scope includes correction of the flow calculation equation for the PLC system (R-061) as part of the Fargo Diversion Inlet Structure. Place of performance is North River, North Dakota.

Quick answers

Who was awarded contract W912ES17C0003?

W912ES17C0003 was awarded to Ames Construction, Inc. by ENDIST St Paul (US Army Corps of Engineers) on December 6, 2016.

How much is contract W912ES17C0003 worth?

The government has obligated $55,657,308 on W912ES17C0003. Its potential value, with all options, is $55,808,308.

Was contract W912ES17C0003 competed?

The extent of competition for W912ES17C0003 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award