Devils lake city, ramsey county, north dakota.the devils lake flood risk management phase 3 embankments construction project will provide flood protection to the city of devils lake, ND. The…
Ended Definitive Contract Awarded Last action
- Contract number
- W912ES11C0005
- Awardee
-
Swanberg Construction Inc. UEI XLUTRQHMM5G6
- Awarding agency
-
ENDIST St Paul
US Army Corps of Engineers, Department of Defense
- Obligated
- $51,003,696
Award facts
- Opportunity
-
- W912ES11B0005 Solicitation number
- Devils Lake Flood Risk Management Phase 3 Embankments construction project Award Notice · Posted Feb 1, 2011
- Contract value 100% obligated
- $51,003,695.93 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Funding agency
- ENDIST Savannah US Army Corps of Engineers, Department of Defense
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y299 Contruct/All Other Non-Bldg Facs
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Devils Lake, ND 58301, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $62,000 | |
| Close Out | -$129,780 | |
| Close Out | $67,188 | |
| Supplemental Agreement for work within scope | $364,054 | |
| Supplemental Agreement for work within scope | $7,852 | |
| Supplemental Agreement for work within scope | $25,280 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Vendor Address Change | $0 | |
| Supplemental Agreement for work within scope | $35,354 | |
| Supplemental Agreement for work within scope | $19,175 | |
| Supplemental Agreement for work within scope | $5,595 | |
| Supplemental Agreement for work within scope | $35,283 | |
| Supplemental Agreement for work within scope | $225,474 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$32,667 | |
| Supplemental Agreement for work within scope | $98,251 | |
| Supplemental Agreement for work within scope | $33,212 | |
| Supplemental Agreement for work within scope | $1,129,395 | |
| Supplemental Agreement for work within scope | $128,987 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$3,000 | |
| Supplemental Agreement for work within scope | $218,314 | |
| Supplemental Agreement for work within scope | -$23,237 | |
| Supplemental Agreement for work within scope | $5,031 | |
| Supplemental Agreement for work within scope | $173,020 | |
| Supplemental Agreement for work within scope | $189,601 | |
| Supplemental Agreement for work within scope | $9,321 | |
| Supplemental Agreement for work within scope | -$113,713 | |
| Supplemental Agreement for work within scope | -$570 | |
| Supplemental Agreement for work within scope | $11,390 | |
| Supplemental Agreement for work within scope | $6,896 | |
| Exercise an Option | $6,790,433 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $15,805 | |
| Supplemental Agreement for work within scope | $251,590 | |
| Supplemental Agreement for work within scope | $22,774 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $7,999,036 | |
| Exercise an Option | $15,790,564 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $602,826 | |
| Supplemental Agreement for work within scope | -$20,854 | |
| Other Administrative Action | $0 | |
| Original award | $17,003,816 |
Show all 45
Description
Devils lake city, ramsey county, north dakota.the devils lake flood risk management phase 3 embankments construction project will provide flood protection to the city of devils lake, ND. The contractor will be required to furnish all plant, labor, material and equipment to raise and extend the existing embankments along devils lake from elevation 1461.2 to a minimum construction grade of 1467.2 (construction grade varies by reach). Phase 3 consists of the airport reach (9,600 feet of new and existing embankment and road), golf course/eagle bend reach (9,885 feet of existing embankment), lakewood reach (6,200 feet of new embankment), north tieback/roberts reach (8,689 feet of new and existing embankment), and east end reach (4,600 feet of new embankment). Airport reach is option 1, lakewood reach is option 2, north tieback & east end reach is option 3, and roberts reach will be option 4.
Quick answers
Who was awarded contract W912ES11C0005?
W912ES11C0005 was awarded to Swanberg Construction Inc. by ENDIST St Paul (US Army Corps of Engineers) on April 20, 2011.
How much is contract W912ES11C0005 worth?
The government has obligated $51,003,696 on W912ES11C0005.
Which agency awarded contract W912ES11C0005?
ENDIST St Paul (US Army Corps of Engineers) awarded W912ES11C0005, with funding from ENDIST Savannah (US Army Corps of Engineers).
Was contract W912ES11C0005 competed?
The extent of competition for W912ES11C0005 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award