Arra::yes::arra recoveryproject#::114877::RP# pool 8 islands phase III, stage 3A, habitat rehabilitation and enhancement project (HREP). Project consists of furnishing plant, labor, materials, and…

Ended Definitive Contract Awarded Last action

Contract number
W912ES09C0042
Awardee
Awarding agency
Obligated
$4,862,281

Award facts

Opportunity
Contract value 205% obligated
$2,366,631.57 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Brownsville, MN, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00003 -$425,195
Supplemental Agreement for work within scope P00003 · Pool 8 islands phase III stage 3A R-0007 variation in estimated quantities (EMP funds) -$103,909
Supplemental Agreement for work within scope A00003 $2,229
Supplemental Agreement for work within scope A00003 · Exercise options 1-3 $0
Supplemental Agreement for work within scope A00002 · Pool 8, phase III, stage III EMP funding $0
Supplemental Agreement for work within scope A00002 -$140,705
Supplemental Agreement for work within scope A00001 · Exercise options 1-3 $0
Supplemental Agreement for work within scope A00001 · Pool 8, phase III, stage III $13,045
Other Administrative Action P00001 $0
Other Administrative Action P00002 · Pool 8 islands phase III, stage 3A, habitat rehabilitation and enhancement project (HREP). Project consists of furnishing plant, labor, materials, and equipment… $0
Other Administrative Action P00001 $0
Exercise an Option P00002 $3,061,549
Modification Pool 8 islands phase III, stage 3A, habitat rehabilitation and enhancement project (HREP). Project consists of furnishing plant, labor, materials, and equipment… $2,455,266
Original award $0
Show all 14

About this award

This is a $2,366,631.57 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Portable Barge Service Inc. for the Pool 8 Islands Phase III, Stage 3A, Habitat Rehabilitation and Enhancement Project (HREP). The contract does not have a set-aside designation. The project consists of constructing islands using dredged material, as well as building various erosion control structures such as rocklog sills, riprap slope protection, and wildlife loafing structures. This award is for the base items, with options remaining to be exercised later. The work is being performed in Brownsville, Minnesota, and the contract has a completion date of July 30, 2011.

Description

Arra::yes::arra recoveryproject#::114877::RP# pool 8 islands phase III, stage 3A, habitat rehabilitation and enhancement project (HREP). Project consists of furnishing plant, labor, materials, and equipment to construct islands with dredged material from borrow sites, additional work includes construction of rocklog sill, riprap slope protection, riprap groins and vanes, turfing, planting, and wildlife loafing structures. This award is for base items, options remain to be exercised later.

Quick answers

Who was awarded contract W912ES09C0042?

W912ES09C0042 was awarded to Portable Barge Service Inc. by ENDIST St Paul (US Army Corps of Engineers) on April 27, 2009.

How much is contract W912ES09C0042 worth?

The government has obligated $4,862,281 on W912ES09C0042. Its current value, with exercised options, is $2,366,632.

Was contract W912ES09C0042 competed?

The extent of competition for W912ES09C0042 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award