Sofa shield 5, qatar

Ended Definitive Contract Awarded Last action

Contract number
W912ER18C0004
Awardee
Awarding agency
Obligated
$312,658,121

Award facts

Opportunity
Contract value 100% obligated
  • $312,658,121.40 Current, with exercised options
  • $313,868,072.40 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
ENDIV Transatlantic US Army Corps of Engineers, Department of Defense
Set-aside
No set-aside
Competition
Not Available for Competition · 3 offers Only One Source
Pricing
Firm Fixed Price
Place of performance
Qatar

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00007 · Descope hydrant and ACS add a at EG BLD $559
Supplemental Agreement for work within scope A00006 · Epic fury time extension $0
Change Order P00026 · Site civil work. Construct eight ADA missile launch pads $1,891,445
Supplemental Agreement for work within scope A00005 · QF004 weather time extension FEB 25 and JUL 25 $0
Supplemental Agreement for work within scope A00004 · CR0059 site 1 and 4A miscellaneous changes $29,206
Other Administrative Action A00003 · Change contract completion date (CCD) $0
Supplemental Agreement for work within scope A00002 · A0002-QA0056 descope chain-link fence site 4A -$256,971
Supplemental Agreement for work within scope P00025 · Additional buildings and site work added. $21,830,644
Other Administrative Action P00024 · Rolling 2019 funding that will expire/cancel to another new clin $0
Supplemental Agreement for work within scope P00023 · QF001 REA settlement prolongation costs for REA, shield 5 site 1 and 4A, qatar $22,289,790
Other Administrative Action P00022 · Modification is issued to roll over FY14 funding to new FY 19 funding. $0
Other Administrative Action P00021 · 1.&*@~the purpose of this modification to record the payment of a request for equitable adjustment (REA) and add new clin 0425 REA site civil earthworks on… $2,379,970
Change Order A00001 · A00001 climate control & pavilion ladder - additional costs incurred for temperature controlled storage and additional costs incurred due to installation of… $69,909
Supplemental Agreement for work within scope P00020 · Modification P00020 is issued for the negotiated agreement of RFP-0025 continuation (site 4A reconfiguration), RFP-0037 (MV works), RFP-0038 (water & sewage… $2,023,783
Supplemental Agreement for work within scope P00019 · Modification P00019 is issued for the negotiated agreement of RFP-0025 (site 4A reconfiguration) and RFP-0036 (site 1, access door between rooms BE136A and… $3,176,472
Supplemental Agreement for work within scope P00018 · Modification P00018 is issued to add two (2) self-latching metal doors at the ramps leading to the swimming pool located at facility 309, officers club, on site… $7,177
Supplemental Agreement for work within scope P00016 · Miscellaneous changes issued for the negotiated agreement of the following changes on sites 1 and 4A: RFP-0021 (COP #14) RFP-0031 (network switches) RFP-0033… $1,096,245
Supplemental Agreement for work within scope P00017 · Modification P00017 is issued for the negotiated agreement of the following changes on site 1: RFP-0022 (PDS) RFP-0028 (football pitch) RFP-0030 (utility… $4,117,585
Supplemental Agreement for work within scope P00015 · Modification P00015 is issued for the negotiated agreement of the following changes on sites 1 and 4A: RFP-0014 (provide floor finish changes in various… $8,400,671
Supplemental Agreement for work within scope P00014 · Modification P00014 is to add the requirement for a design/build of a mosque, parade ground and a pavilion on site 1. $5,023,960
Supplemental Agreement for work within scope P00013 · Modification P00013 is to incorporate the changes of COP #10. $625,556
Supplemental Agreement for work within scope P00012 · Modification P00012 is to revise the auditorium seats in facility 402, administration building (LARGE) on site 1. $221,191
Supplemental Agreement for work within scope P00011 · Modification P00011 is to revise the elevator in facility 406, C2 main building (ADOC), from a one ton elevator to a two ton elevator on site 1. $41,839
Supplemental Agreement for work within scope P00010 · Modification P00010 is for additional 3D renderings as identified in the modification scope of work. $9,040
Supplemental Agreement for work within scope P00009 · Modification P00009 is for costs associated with public works authority (ASHGHAL) tie-in and roadway to the orbital highway from site 1. $151,099
Supplemental Agreement for work within scope P00008 · Modification P00008 is for abatement of asbestos containing materials (ACM) on site 4A. $19,700
Supplemental Agreement for work within scope P00007 · Modification P00007 issued for change order package one (COP #01) scope of work. $15,858,823
Supplemental Agreement for work within scope P00006 · Modification P00006 is to descope building 312 (general purpose facility) and its associated structures, roadways, and utilities at site 1. -$2,855,224
Supplemental Agreement for work within scope P00005 · Modification P00005 is for 3D renderings of rooms within facilities as identified in the modification scope of work. $23,520
Supplemental Agreement for work within scope P00004 · Modification to identify, sample, test, and provide a report of potential asbestos containing materials (ACM) on site 4A $29,407
Supplemental Agreement for work within scope P00003 · Modification for geotechnical investigation on site 4A due to COP #01. $33,167
Change Order P00002 · Additional funding to site civil work for COP #02 for the removal of trees and bushes from site 1. $129,508
Other Administrative Action P00001 · Admin modification to revise specifications $0
Original award $226,290,049
Show all 34

About this award

U.S. ENDIV Transatlantic awarded a definitive firm fixed price contract to Midmac Contracting Company W.l.l for SOFA Shield 5 construction work in Qatar, with a ceiling value of $313.9 million and an ultimate completion date of July 8, 2026.

The contract covers descoping of hydrant infrastructure and Air Conditioning Systems (ACS) add-ons at an expeditionary group building. Place of performance is Qatar. No set-aside was applied.

Quick answers

Who was awarded contract W912ER18C0004?

W912ER18C0004 was awarded to Midmac Contracting Company W.l.l by ENDIST Middle East (US Army Corps of Engineers) on November 16, 2017.

How much is contract W912ER18C0004 worth?

The government has obligated $312,658,121 on W912ER18C0004. Its potential value, with all options, is $313,868,072.

Which agency awarded contract W912ER18C0004?

ENDIST Middle East (US Army Corps of Engineers) awarded W912ER18C0004, with funding from ENDIV Transatlantic (US Army Corps of Engineers).

Was contract W912ER18C0004 competed?

The extent of competition for W912ER18C0004 was not available for competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award