Channel cleanout excavation

Ended Definitive Contract Awarded Last action

Contract number
W912EQ25C0002
Awardee
Awarding agency
Obligated
$2,928,527

Award facts

Opportunity
Contract value 100% obligated
$2,928,526.55 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Department of the Army Department of Defense
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Caruthersville, MO 63830, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00003 $0
Supplemental Agreement for work within scope A00002 · Revise certain estimated quantities to reflect the current best estimate of quantities required to complete the work. This modification is for funding and… $187,608
Supplemental Agreement for work within scope A00001 · The contractor period of performance end date has increased by 25 calendar days from 480 days to 505 days. $0
Funding Only Action P00002 · Request for equitable adjustment modification $212,564
Supplemental Agreement for work within scope P00001 $0
Original award $2,528,354

About this award

The Department of the Army awarded a definitive contract to Randy Kinder Excavating Inc. (doing business as RKE Contractors) for channel cleanout excavation on the Belle Fountain Ditch near Caruthersville, Missouri, on January 14, 2025, under a Service-Disabled Veteran-Owned Small Business set-aside. The contract carries a ceiling value of $2,928,526.55 and firm fixed price.

RKE Contractors is an SDVOSB and SBA-certified HUBZone firm. Place of performance is Caruthersville, MO. The originating solicitation, posted October 16, 2024, with a November 1, 2024 deadline, calls for furnishing plant, labor, and materials to cleanout the Main Ditch north of County Road 442 to the confluence of Ditch 2/Ditch 1/Ditch 6 and Ditch 1 into Caruthersville, including all work per specifications and plans. Ultimate completion is August 6, 2026. This modification revised certain estimated quantities to reflect current best estimates required to complete the work for funding and payment purposes only and does not change the substantive rights of the contracting parties.

Quick answers

Who was awarded contract W912EQ25C0002?

W912EQ25C0002 was awarded to Randy Kinder Excavating Inc. by ENDIST Memphis (US Army Corps of Engineers) on January 14, 2025.

How much is contract W912EQ25C0002 worth?

The government has obligated $2,928,527 on W912EQ25C0002.

Which agency awarded contract W912EQ25C0002?

ENDIST Memphis (US Army Corps of Engineers) awarded W912EQ25C0002, with funding from Department of the Army (Department of Defense).

Was contract W912EQ25C0002 competed?

The extent of competition for W912EQ25C0002 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award