Herbert hoover dike rehabilitation project, S-72 embankment armoring

Ended Definitive Contract Awarded Last action

Contract number
W912EP21C0012
Awardee
Awarding agency
Obligated
$5,327,655

Award facts

Opportunity
  • W912EP21R0002 Solicitation number
Contract value 100% obligated
$5,327,654.89 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
8(a) Sole Source
Competition
Not Competed under SAP · 1 offer Simplified Acquisition
Pricing
Firm Fixed Price
Place of performance
Clewiston, FL 33440, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00010 · A00010 clins 0005 and 0011 adjustment -$3,633
Supplemental Agreement for work within scope A00009 · A00009 hurricane nicole and weather extension $0
Supplemental Agreement for work within scope A00008 · Hurricane IAN impacts $0
Supplemental Agreement for work within scope A00007 · Existing conditions at S-72. -$190,580
Funding Only Action A00006 · HHD S-72 embankment armoring administrative MOD. DE-obligated $137,825.18 from clin 0002 & 0006. Obligated $137,825.18 to clin 0017. Contract price and time… $0
Supplemental Agreement for work within scope A00004 · Contract price increased by $125,102.96 from $5,333,553.36 to $5,458,656.32. The completion date extended from 15 january 2023 to 13 february 2023. $125,103
Supplemental Agreement for work within scope A00005 · Additional turnout removal MOD. Contract price is increased from $5,458,656.32 to $5,521,868. Contract duration increased from 13 FEB 2023 to 20 FEB 2023. $63,212
Supplemental Agreement for work within scope A00003 · Contract price is increased by $228,358.73 from $5,105,194.63 to $5,333,553.36. Extended by 24 calendar days from 22 december 2022 to 15 january 2023. $228,359
Supplemental Agreement for work within scope A00002 · Change in acbm manufacturer $227,868
Supplemental Agreement for work within scope A00001 · HN002 repairs of IP levee roads $389,000
Supplemental Agreement for work within scope P00001 · HHD S-72 embankment armoring, notice to proceed to contractor $0
Original award $4,488,327
Show all 12

About this award

The Department of the Army Corps of Engineers Engineering District Jacksonville awarded a definitive contract valued at $5.3 million to Eagle Engineering & Land Development, Inc. for the Herbert Hoover Dike Rehabilitation Project in Clewiston, Florida. Under the firm fixed price contract, Eagle Engineering will perform embankment armoring services on the S-72 embankment as part of the larger Herbert Hoover Dike rehabilitation effort by the USACE to improve flood protection in the area. The contract was awarded on a sole source basis under the 8(a) set aside program designation for small businesses owned and controlled by socially and economically disadvantaged individuals. Work is expected to be completed by March 2023.

Quick answers

Who was awarded contract W912EP21C0012?

W912EP21C0012 was awarded to Eagle Engineering & Land Development, Inc. by ENDIST Jacksonville (US Army Corps of Engineers) on July 1, 2021.

How much is contract W912EP21C0012 worth?

The government has obligated $5,327,655 on W912EP21C0012.

Was contract W912EP21C0012 competed?

The extent of competition for W912EP21C0012 was not competed under sap. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award