C-44 reservoir/STA project, contract no. 2, martin county, florida
Ended Definitive Contract Awarded Last action
- Contract number
- W912EP15C0021
- Awardee
-
Barnard Construction Company, Incorporated UEI LEGGW1TNMVC9 Part of Barnard Spencer Joint Venture
- Awarding agency
-
ENDIST Jacksonville
US Army Corps of Engineers, Department of Defense
- Obligated
- $227,984,961
Award facts
- Opportunity
-
- W912EP14R0016 Solicitation number
- C-44 Reservoir/STA Project, Contract No. 2, Martin County Florida Award Notice · Posted Aug 7, 2014
- Contract value 100% obligated
-
- $227,984,960.57 Current, with exercised options
- $228,824,960.57 Potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KB Construction Of Canals
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 7 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Indiantown, FL 34956, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $394,962 | |
| Other Administrative Action | $0 | |
| Change Order | -$5,883 | |
| Change Order | $76,000 | |
| Change Order | $64,438 | |
| Change Order | $256,955 | |
| Change Order | -$3,280 | |
| Change Order | -$4,000 | |
| Change Order | -$26,000 | |
| Change Order | $60,000 | |
| Change Order | $26,000 | |
| Change Order | $2,501 | |
| Change Order | $12,720 | |
| Change Order | $3,793 | |
| Change Order | $22,223 | |
| Supplemental Agreement for work within scope | $30,965 | |
| Supplemental Agreement for work within scope | $60,700 | |
| Change Order | $67,852 | |
| Change Order | -$229,007 | |
| Supplemental Agreement for work within scope | -$2,623 | |
| Supplemental Agreement for work within scope | -$7,300 | |
| Supplemental Agreement for work within scope | $122,137 | |
| Supplemental Agreement for work within scope | $251,460 | |
| Change Order | $290,450 | |
| Change Order | -$17,268 | |
| Change Order | -$19,526 | |
| Change Order | -$88,400 | |
| Change Order | -$474,028 | |
| Change Order | $265,404 | |
| Change Order | -$134,520 | |
| Change Order | -$209,631 | |
| Change Order | $496,099 | |
| Supplemental Agreement for work within scope | -$140,491 | |
| Change Order | -$34,429 | |
| Change Order | -$103,456 | |
| Change Order | -$80,000 | |
| Change Order | -$78,000 | |
| Change Order | -$24,032 | |
| Change Order | -$4,250 | |
| Change Order | -$138,641 | |
| Change Order | $4,545 | |
| Change Order | -$2,283 | |
| Change Order | $3,975 | |
| Change Order | -$15,708 | |
| Change Order | $119,024 | |
| Change Order | $119,000 | |
| Change Order | $88,137 | |
| Change Order | $15,442 | |
| Change Order | -$33,800 | |
| Change Order | $30,000 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a $228,824,960.57 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Barnard Construction Company, Incorporated, a large heavy civil construction firm based in Bozeman, Montana. The contract is for the C-44 Reservoir/STA Project, Contract No. 2, located in Martin County, Florida, with a completion date of November 19, 2021. No set-aside was used for this award.
The contract involves comprehensive construction services for this large-scale water infrastructure project, including clearing, earthwork, concrete structures, and other civil engineering activities. Barnard Construction Company has been awarded several notable federal contracts across various agencies, demonstrating its robust capability to execute significant infrastructure projects. The company also holds a $1 billion multiple-award indefinite delivery contract with the Naval Facilities Engineering Command for new construction, renovation, and repair of heavy horizontal and civil engineering projects.
Quick answers
Who was awarded contract W912EP15C0021?
W912EP15C0021 was awarded to Barnard Construction Company, Incorporated by ENDIST Jacksonville (US Army Corps of Engineers) on September 11, 2015.
How much is contract W912EP15C0021 worth?
The government has obligated $227,984,961 on W912EP15C0021. Its potential value, with all options, is $228,824,961.
Was contract W912EP15C0021 competed?
The extent of competition for W912EP15C0021 was full and open competition. The government received 7 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award