Birdland park levee system improvements, DES moines, polk county, iowa.
Ended Definitive Contract Awarded Last action
- Contract number
- W912EK10C0067
- Awardee
-
Ceres Environmental Services, Inc. UEI CBUJM4NJVJR6
- Awarding agency
-
ENDIST Rock Island
US Army Corps of Engineers, Department of Defense
- Obligated
- $8,359,978
Award facts
- Opportunity
-
- W912EK10B0006 Solicitation number
- RECOVERY--Z--PROJECT NUMBER 13490, Des Moines and Raccoon Rivers, IA Des Moines and Raccoon Rivers, IA Birdland Park Levee Award of Option A Award Notice · Posted Jan 8, 2010
- Contract value 157% obligated
- $5,313,000.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z299 Maint, Rep/Alter/All Other
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 8 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Des Moines, IA 50309, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | $0 | |
| Close Out | $0 | |
| Change Order | -$34,118 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | -$7,571 | |
| Change Order | $860 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | -$6,902 | |
| Change Order | $0 | |
| Change Order | $1,801 | |
| Change Order | $0 | |
| Change Order | $115,158 | |
| Change Order | $21,668 | |
| Change Order | $0 | |
| Change Order | $1,480 | |
| Change Order | $0 | |
| Change Order | $5,561 | |
| Change Order | $0 | |
| Change Order | $19,977 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $7,640 | |
| Change Order | $0 | |
| Change Order | $13,035 | |
| Change Order | $0 | |
| Change Order | $1,401 | |
| Change Order | -$4,260 | |
| Change Order | $0 | |
| Change Order | $8,352 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $4,380 | |
| Change Order | $0 | |
| Change Order | $22,967 | |
| Change Order | $0 | |
| Change Order | $16,689 | |
| Change Order | $0 | |
| Change Order | $39,138 | |
| Change Order | $17,232 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $161,333 | |
| Change Order | $6,256 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $62,460 | |
| Change Order | $266,424 | |
| Change Order | $0 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a $5,313,000.00 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers to Ceres Environmental Services, Inc. for the Birdland Park Levee System Improvements project in Des Moines, Iowa. The contract was awarded on March 23, 2010 with a completion date of February 12, 2013. Ceres Environmental Services, Inc. is a for-profit general contracting firm that specializes in disaster recovery, environmental response, and demolition and debris operations. This contract was not set aside for any designated business type. In addition to this contract, Ceres holds several indefinite delivery contracts with the Army Corps of Engineers for temporary roofing services across various regions, valued up to $45 million each.
Quick answers
Who was awarded contract W912EK10C0067?
W912EK10C0067 was awarded to Ceres Environmental Services, Inc. by ENDIST Rock Island (US Army Corps of Engineers) on March 23, 2010.
How much is contract W912EK10C0067 worth?
The government has obligated $8,359,978 on W912EK10C0067. Its current value, with exercised options, is $5,313,000.
Was contract W912EK10C0067 competed?
The extent of competition for W912EK10C0067 was full and open competition. The government received 8 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award