Major rehabilitation, stage III, canal walls, lockport pool, illinois waterway, lockport lock, city of lockport, will county, illinois. The purpose of this construction project is to install…
Ended Definitive Contract Awarded Last action
- Contract number
- W912EK09C0097
- Awardee
-
Walsh Construction Company UEI UVDFZGCYR4J4 Part of The Walsh Group
- Awarding agency
-
ENDIST Rock Island
US Army Corps of Engineers, Department of Defense
- Obligated
- $68,798,478
Award facts
- Opportunity
-
- W912EK09R0065 Solicitation number
- RECOVERY--Z--Major Rehabilitation, Stage III, Canal Walls, Lockport Pool, Illinois Waterway, Lockport Lock, Lockport, Will County, Illinois Award Notice · Posted May 29, 2009
- Contract value 336% obligated
- $20,472,211.88 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z299 Maint, Rep/Alter/All Other
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 5 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Lockport, IL, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | -$159,485 | |
| Close Out | $159,485 | |
| Change Order | -$154,668 | |
| Change Order | $0 | |
| Change Order | -$4,817 | |
| Change Order | $0 | |
| Change Order | $15,048 | |
| Change Order | $12,844 | |
| Change Order | $0 | |
| Change Order | $5,565 | |
| Change Order | $0 | |
| Change Order | $435 | |
| Change Order | $85,215 | |
| Change Order | $0 | |
| Change Order | $10,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $92,214 | |
| Change Order | $0 | |
| Change Order | $68,473 | |
| Change Order | $0 | |
| Change Order | $20,120 | |
| Change Order | $0 | |
| Change Order | $33,146 | |
| Change Order | $0 | |
| Change Order | $85,872 | |
| Change Order | $46,168 | |
| Change Order | $109,566 | |
| Change Order | $0 | |
| Change Order | $236,397 | |
| Change Order | $422,379 | |
| Change Order | $17,200 | |
| Change Order | $0 | |
| Change Order | $2,043 | |
| Change Order | $0 | |
| Change Order | $4,025 | |
| Change Order | $0 | |
| Change Order | $16,725 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $910 | |
| Change Order | $0 | |
| Change Order | $38,261 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $30,088 | |
| Change Order | $296,497 | |
| Change Order | $0 | |
| Change Order | $26,108 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a $20,472,211.88 definitive, firm-fixed price contract awarded by the U.S. Army Corps of Engineers (USACE) to Walsh Construction Company, a subsidiary of The Walsh Group, for the major rehabilitation of the canal walls at the Lockport Lock on the Illinois Waterway in Lockport, Illinois. The purpose of the project is to install precast concrete panels on the water side of the existing canal wall to prevent seepage and protect the historic structure from a catastrophic breach. This contract does not have a small business set-aside designation. The award date was September 9, 2009, and the ultimate completion date is November 12, 2013. As a large, experienced federal construction contractor, The Walsh Group and its subsidiaries have been awarded numerous prime contracts by defense and civilian agencies for projects such as medical facilities, weapons storage, and disaster recovery efforts.
Description
Major rehabilitation, stage III, canal walls, lockport pool, illinois waterway, lockport lock, city of lockport, will county, illinois. The purpose of this construction project is to install pre-cast concrete panels on the water side of the existing perched canal wall to prevent seepage and to protect the historic man-made canal wall from a catastrophic section breach.
Quick answers
Who was awarded contract W912EK09C0097?
W912EK09C0097 was awarded to Walsh Construction Company by ENDIST Rock Island (US Army Corps of Engineers) on September 9, 2009.
How much is contract W912EK09C0097 worth?
The government has obligated $68,798,478 on W912EK09C0097. Its current value, with exercised options, is $20,472,212.
Was contract W912EK09C0097 competed?
The extent of competition for W912EK09C0097 was full and open competition. The government received 5 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award