Contracto for peoria riverfront development, illinois (ecosystem restoration) upper mid-sized island critical restoration project, stage I, illinois waterway, river miles 165.5 - 166.0, tazewell…
Ended Definitive Contract Awarded Last action
- Contract number
- W912EK09C0052
- Awardee
-
Midwest Foundation Corporation UEI DALNM91VL748
- Awarding agency
-
ENDIST Rock Island
US Army Corps of Engineers, Department of Defense
- Obligated
- $2,971,612
Award facts
- Opportunity
-
- W912EK09R0010 Solicitation number
- Peoria Riverfront Ecosystem Development Project, Illinois Waterway, River Miles 165. 5-166. 1, Tazewell County, Illinois. Award Notice · Posted Mar 31, 2009
- Peoria Riverfront Ecosystem Development Project, Illinois Waterway, River Miles 165. 5-166. 1, Tazewell County, Illinois. Award Notice · Posted Oct 31, 2008
- Contract value 120% obligated
- $2,477,044.49 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z299 Maint, Rep/Alter/All Other
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 7 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- East Peoria, IL, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | -$208,897 | |
| Close Out | $208,897 | |
| Supplemental Agreement for work within scope | -$556,708 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $10,356 | |
| Change Order | $19,589 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Exercise an Option | $683,875 | |
| Exercise an Option | $0 | |
| Exercise an Option | $91,000 | |
| Change Order | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Modification | $2,723,500 | |
| Original award | $0 |
Show all 32
About this award
This is a $2,477,044.49 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers, Rock Island District (ENDIST Rock Island) to Midwest Foundation Corporation for the Peoria Riverfront Development, Illinois (Ecosystem Restoration) Upper Mid-Sized Island Critical Restoration Project, Stage I. The project is located on the Illinois Waterway in Tazewell County, Illinois. The contract has an ultimate completion date of August 26, 2013 and was awarded on March 19, 2009. This contract was not set aside for any specific business type.
Description
Contracto for peoria riverfront development, illinois (ecosystem restoration) upper mid-sized island critical restoration project, stage I, illinois waterway, river miles 165.5 - 166.0, tazewell county, illinois at illinois waterway, tazewell county, illinois.
Quick answers
Who was awarded contract W912EK09C0052?
W912EK09C0052 was awarded to Midwest Foundation Corporation by ENDIST Rock Island (US Army Corps of Engineers) on March 19, 2009.
How much is contract W912EK09C0052 worth?
The government has obligated $2,971,612 on W912EK09C0052. Its current value, with exercised options, is $2,477,044.
Was contract W912EK09C0052 competed?
The extent of competition for W912EK09C0052 was full and open competition. The government received 7 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award